Aug 31 2013 (HC)

Residents Welfare Association Urban Estate Phase-1(B), Vs. Sh.Mohinder ...

Court: Punjab and Haryana

Decided on: Aug-31-2013

..... 2245 2013 o m date of decision august 31 2013 residents welfare association urban estate phase 1 b patiala petitioner versus sh mohinder singh estate officer puda patiala respondent coram hon .....

Tag this Judgment! Ask ChatGPT

Aug 27 2013 (HC)

Present: Mr. Sukhdev Sharma Advocate Vs. M/S Kap Cones Udyog Vihar Pha ...

Court: Punjab and Haryana

Decided on: Aug-27-2013

..... of central excise commissionerate delhi iii gurgaon appellant versus m s kap cones udyog vihar phase v gurgaon respondents coram hon ble mr justice rajive bhalla hon ble mr justice dr .....

Tag this Judgment! Ask ChatGPT

Aug 26 2013 (HC)

Kaushalaya Rani Wife of Late Shri Ripudaman Singh Resident of Vs. Urmi ...

Court: Punjab and Haryana

Decided on: Aug-26-2013

..... others petitioners versus urmil sood wife of s k sood resident of house no 380 phase iii a sas nagar mohali and others respondents coram hon ble mr justice k kannan .....

Tag this Judgment! Ask ChatGPT

Jul 10 2013 (HC)

Ramesh Singh Jhaj S/O Baldev Singh Resident of Kothi No.2355 Phase X, ...

Court: Punjab and Haryana

Decided on: Jul-10-2013

..... 10 07 2013 ramesh singh jhaj s o baldev singh resident of kothi no 2355 phase x mohali petitioner versus p s b housing finance limited respondent present mr atul goel .....

Tag this Judgment! Ask ChatGPT

May 31 2013 (TRI)

Enercon (India) Limited Vs. Aloys Wobben

Court: Intellectual Property Appellate Board IPAB

Decided on: May-31-2013

..... shows a wind turbine is connected to a 6 phase two 3 phase system generator which gives output to a rectifier thus ..... the layout windings in the stator which has 6 phases and each phase is separated by 300 page 12 line 1 2 ..... synchronous machineclaim 1present3 rotorclaim 1present4 statorclaim 1present5 atleast two independent3 phase systems which are electrically isolated from each otherclaim 1not .....

Tag this Judgment! Ask ChatGPT

Aug 23 2013 (HC)

Housing Development and Infrastructure Limited Vs. Mumbai Internationa ...

Court: Mumbai

Decided on: Aug-23-2013

..... shall be completed by the petitioner in two phases as follows a phase 1 i under phase 1 i the petitioner shall commence not later ..... from the commencement date time being of the essence b phase 2 under phase 2 the petitioner shall commence not later than 36 thirty ..... cleared a single slum from the airport land covered under phase 1 or phase 2 the petitioner however submitted that time was not the .....

Tag this Judgment! Ask ChatGPT

Jan 23 2013 (TRI)

Enercon (India) Limited Vs. Aloys Wobben

Court: Intellectual Property Appellate Board IPAB

Decided on: Jan-23-2013

..... can be large enough to produce harmful electromagnetic interference emi along with common three phases primary windings an extra secondary winding 31 associated with properly chosen circuitry shown ..... however the output inductor contains four mutually magnetically coupled windings and a symmetrical three phase star connected series resonant filter which is claimed to shunt symmetrical harmonics away .....

Tag this Judgment! Ask ChatGPT

Apr 02 2013 (HC)

Maruti Ispat and Energy Private Limited, C Vs. the Central Power Distr ...

Court: Andhra Pradesh

Decided on: Apr-02-2013

..... billing at 11 kv tariff till the commencement of the third phase which would put the total contracted demand of the petitioner ..... whether they relate to the commencement or the conclusion of the phase learned standing counsel would therefore contend that the petitioner company being ..... that billing shall be done at 11 kv tariff upto 2nd phase demand does not outweigh the logic of the arrangement as .....

Tag this Judgment! Ask ChatGPT

Jan 03 2013 (TRI)

Belaire Owner's Association Vs. DLF Ltd. and Others

Court: Competition Commission of India CCI

Decided on: Jan-03-2013

..... demanded from the company and the company has allowed the apartment allottee an inspection of phase v including zone 8 and the said portion of land tentative building plans tentative location ..... a residential apartment with the full knowledge of all laws rules regulations notifications applicable to phase v in general and this group housing project in particular that the apartment allottee hereby .....

Tag this Judgment! Ask ChatGPT

Oct 22 2013 (HC)

Autodesk Inc and anr. Vs. Arup Das and ors.

Court: Delhi

Decided on: Oct-22-2013

..... reached the premises located at 142 a b noida special economic zone phase ii noida 201305 to execute the commission on 9th may 2011 ..... valves pvt ltd is 142 a b noida special economic zone phase ii noida 201 305 the certificate itself certifies that the management ..... mr sushil kumar street 142 a b noida special economic zone phase ii noida 201 305 similarly on jimtrade com the information pertaining .....

Tag this Judgment! Ask ChatGPT

  • << Prev.

Sign-up to get more results

Unlock complete result pages and premium legal research features.

Start Free Trial

Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //