Skip to content
How to use Judgment tools
  1. Click Tools to open PDF, Print, Tag, Note, Favourite, and CiteSignal.
  2. Use Brief & Ask in the toolbar for the AI Brief and case chat.
  3. Jump to sections with the pills below the help bar.

Devendra Kumar Surana Vs. Lalit

Devendra Kumar Surana vs Lalit

Disposition Criminal revision allowed Court Madhya Pradesh Decided May 03, 2002
~4 min read
https://sooperkanoon.com/case/505150

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Madhya Pradesh High Court
Judge
Decided On
Case Number
Criminal Revision No. 136/2002
Subject
Criminal
Disposition
Criminal revision allowed

Case Summary

AI-generated summary - not the official court judgment text.

- MADHYA PRADESH NAGAR TATHA GRAM NIVESH ADHINIYAM (23 OF 1973)Section 50(4) Proviso (As inserted by Act of 2004): [Dipak Misra, Krishna Kumar Lahoti & Rajendra Menon, JJ] Preparation of Town Development Scheme Proviso prescribing time limit Held, Object of amendment is to remove hardship caused to citizens and to...

Key legal issue
Criminal
Outcome / disposition
Criminal revision allowed
Acts & sections
Negotiable Instruments Act, 1881 - Sections 138; Limitation Act, 1963 - Sections 4 and 5

Parties & Advocates

Appellant / Petitioner

Devendra Kumar Surana

Advocate N.K. Dave, Adv.

Respondent

Lalit

Advocate None

Legal References

Acts
Negotiable Instruments Act, 1881 - Sections 138; Limitation Act, 1963 - Sections 4 and 5
Cases Referred
(Naththusingh v. Jaswantsingh
Reported In
2002CriLJ4176; 2002(3)MPHT127

Excerpt

- madhya pradesh nagar tatha gram nivesh adhiniyam (23 of 1973)section 50(4) proviso (as inserted by act of 2004): [dipak misra, krishna kumar lahoti & rajendra menon, jj] preparation of town development scheme proviso prescribing time limit held, object of amendment is to remove hardship caused to citizens and to provide time limit to consider objections and suggestion and to provide a deeming clause so that the authority would act in quite promptitude. proviso unequivocal, categorical and unambiguous and does not permit any other kind of construction but a singular one. section 50 (4) proviso (as inserted by act of 2004): [dipak misra, krishn kumar lahoti & rajendra menon, jj] preparation of town development scheme held, proviso is not retrospective. scheme already finalised will not lapse and has to be completed within the time span provided under proviso. no vested right accrues in favour of authority on commencement of process of preparation of scheme, which cannot be impaired by introducing proviso. section 50(4) proviso (as inserted by act of 2004): [dipak misra, krishn kumar lahoti & rajendra menon, jj] preparation of town development scheme held, proviso uses the term shall be deemed to have lapsed. it does not convey that scheme gets automatically lapsed. - p/1-c). 5. the learned trial court has accepted the explanation submitted by the applicant and rejected the application holding that the notice was sent on 15-4-2000 well within time because 14-4-2000 was a public holiday.orders.l. kochar, j.1. this revision has been brought by the applicant before this court against the order dated 19-9-2001 passed by the learned third chief judicial magistrate, indore in cr. case no. 1295/2000.2. the facts in nut shell are that the non-applicant lalit porwal had filed a criminal complaint under section 138 of the negotiable instruments act (hereinafter referred to as the 'act') after dishonour of the cheque issued in his favour by the applicant. the cheque was dishonoured and intimation of the same was given by the bank of the non-applicant lalit porwal on 30-3-2000. he sent a notice as per provision under section 138 proviso (b) of the act on 15-4-2000. the applicant, after appearing before the court below, submitted an application on 25-1-2001 that the notice was sent after completion of 15 days i.e., 15-4-2000. therefore, it was barred by limitation and the provision relating to this purpose is mandatory and, hence, the complaint is not maintainable and is liable to be dismissed.3. the complainant non-applicant submitted before the trial court that on 14-4-2000 there was public holiday on account of ambedkar jayanti which prevented him to send a notice on the said date. therefore, he sent the notice on 15-4-2000. hence, there was no delay in sending the notice.4. the applicant examined r.l. upasani, the public relation inspector of head post office, indore who has testified on 19-9-2001 that though 14-4-2000 was a public holiday because of ambedkar jayanti, but for urgent and essential work, the head post office was functioning and the work was also performed. he submitted the photo stat copy of work register (ex. p/1-c).5. the learned trial court has accepted the explanation submitted by the applicant and rejected the application holding that the notice was sent on 15-4-2000 well within time because 14-4-2000 was a public holiday.6. the contention of the learned counsel for the applicant is that the provision of section 4 read with section 5.....

Full Judgment

ORDER

S.L. Kochar, J.

1. This revision has been brought by the applicant before this Court against the order dated 19-9-2001 passed by the learned Third Chief Judicial Magistrate, Indore in Cr. Case No. 1295/2000.

2. The facts in nut shell are that the non-applicant Lalit Porwal had filed a criminal complaint under Section 138 of the Negotiable Instruments Act (hereinafter referred to as the 'Act') after dishonour of the cheque issued in his favour by the applicant. The cheque was dishonoured and intimation of the same was given by the Bank of the non-applicant Lalit Porwal on 30-3-2000. He sent a notice as per provision under Section 138 Proviso (b) of the Act on 15-4-2000. The applicant, after appearing before the Court below, submitted an application on 25-1-2001 that the notice was sent after completion of 15 days i.e., 15-4-2000. Therefore, it was barred by limitation and the provision relating to this purpose is mandatory and, hence, the complaint is not maintainable and is liable to be dismissed.

3. The complainant non-applicant submitted before the Trial Court that on 14-4-2000 there was public holiday on account of Ambedkar Jayanti which prevented him to send a notice on the said date. Therefore, he sent the notice on 15-4-2000. Hence, there was no delay in sending the notice.

4. The applicant examined R.L. Upasani, the Public Relation Inspector of Head Post Office, Indore who has testified on 19-9-2001 that though 14-4-2000 was a public holiday because of Ambedkar Jayanti, but for urgent and essential work, the Head Post Office was functioning and the work was also performed. He submitted the photo stat copy of Work Register (Ex. P/1-C).

5. The learned Trial Court has accepted the explanation submitted by the applicant and rejected the application holding that the notice was sent on 15-4-2000 well within time because 14-4-2000 was a public holiday.

6. The contention of the learned Counsel for the applicant is that the provision of Section 4 read with Section 5 of the Limitation Act will not apply in the present case, because there is a specific provision of limitation available in Section 138 of the Act.

7. It is true that in the Act, the specific provision for limitation for sending the notice of demand within fifteen days and it is after the receipt of the information about dishonour of the cheque by the Bank. In this section, there is no provision for condonation of delay on being shown sufficient cause by the concerned party. Therefore, the question of application of Section 4 read with Section 5 of the Limitation Act would not arise. In the view of this Court, the learned Court below has not dismissed the application of the applicant on the ground that as per provision of Section 4 read with Section 5 of the Limitation Act, the non-applicant was able to show sufficient cause for not sending the notice on 14-4-2000. Therefore, no question of consideration of Sections 4/5 of the Limitation Act would arise.

8. The non-applicant could have sent the notice by Courier or by FAX or could have served himself or through his employee on 14-4-2000, because there is no provision in Section 138 Proviso (b) for sending the notice within 15 days by Registered Post. Apart from this, in view of the statement given by the Public Relation Inspector of Head Post Office, Indore on 14-4-2000 the Post Office was functioning for urgent and essential work. Therefore, the non-applicant could have sent the notice by Regd. Post on the said date also. Reference can be made to the judgment rendered by Hon'ble the Supreme Court reported in (SIL Import, USA v. Exim Aides Silk Exporters, Bangalore) AIR 1999 SC 1609.

9. Learned Counsel for the applicant has placed reliance on a judgment rendered by this Court in M.Cr.C. No. 4026/2001 (Naththusingh v. Jaswantsingh) decided on 16-1-2002 = 2002(2) M.P.H.T. 180. In this judgment, it has been held that the provision of Section 138 Proviso (b) of the Act is indispensable and breach of the same would result in the dismissal of the complaint filed by the complainant.

10. In the result, the revision is allowed. The order dated 19-9-2001 isset aside and the application of the applicant is allowed resulting in to dismissalof the complaint.