Chloride Industries Ltd. Vs. Union of India

Chloride Industries Ltd. vs Union of India

Type Court Judgment Court Mumbai Decided Mar 21, 1989
~3 min read
https://sooperkanoon.com/case/344708

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Mumbai High Court
Judge
Decided On
Case Number
Writ Petition No. 1061 of 1989
Subject
Excise

Case Summary

AI-generated summary - not the official court judgment text.

-

Key legal issue
Excise

Parties & Advocates

Appellant / Petitioner

Chloride Industries Ltd.

Respondent

Union of India

Legal References

Reported In
1990(47)ELT318(Bom)

Excerpt

- .....not because of any sheer negligence or neglect on the part of the petitioners but because of certain circumstances not entirely within the control of the petitioners. the legal advice and opinion obtained from an advocate who later shifted to delhi and the legal advice obtained from a subsequent advocate, through not very cogent reasons for condoning the delay, are nevertheless factors which cannot be said to be totally irrelevant. the delay again is not gross but, as indicated, of 16 days. we also cannot overlook the weighty observations of the supreme court in collector, land acquisition, anantnag v. kateji - : (1987)illj500sc on which, naturally, heavy reliance has been placed by the petitioner's learned counsel mr. avinash shivade. these observations have been quoted at page ii of this petition. in the context of all these circumstance, we are inclined to condone delay and permit the petitioners to have their claim adjudicated on its own merits and in accordance with law but on payment of exemplary costs as directed below.4. hence order : this petition is allowed. the impugned order no. 1752/88/wrb, dated 9-12-1988 (exh. 'b') as also the impugned order no. 1753/88/wrb, dated 9-12-1988 (exh. 'c') are set aside and delay in filing the appeal in question is condoned and the appeal is directed to be heard and decided on its own merits and in accordance with law subject to the condition that the petitioners pay, latest by 25th april, 1989, to the collector, central excise, pune as and by way of exemplary costs of this petition, amount quantified at rs. 5000/- (rupees five thousand). if the said amount is not paid latest by 25th april 1989, the aforesaid impugned orders exhibits 'b' and 'c' shall stand confirmed and this petition shall stand dismissed.5. rule is made absolute on conditions aforesaid with order of costs as directed above.

Full Judgment

S.C. Pratap, J.

1. Rule returnable forthwith. Respondents waive service.

2. Delay of 16 days in the filing of the appeal in question was not condoned by the Tribunal. Hence this petition.

3. Now, it is very difficult for this Court to exercise its discretionary powers to interfere with the matter which itself is basically discretionary and when the said discretion could not be said to have been exercised arbitrarily. In this case, however, we find that the appeal is filed not against any demand as such but on the question of refund sought to be claimed by the petitioner company and this claim for refund runs into, what we are informed at the bar, over Rs. 40 lacs. The delay again has occurred not because of any sheer negligence or neglect on the part of the petitioners but because of certain circumstances not entirely within the control of the petitioners. The legal advice and opinion obtained from an Advocate who later shifted to Delhi and the legal advice obtained from a subsequent Advocate, through not very cogent reasons for condoning the delay, are nevertheless factors which cannot be said to be totally irrelevant. The delay again is not gross but, as indicated, of 16 days. We also cannot overlook the weighty observations of the Supreme Court in Collector, Land Acquisition, Anantnag v. Kateji - : (1987)ILLJ500SC on which, naturally, heavy reliance has been placed by the petitioner's learned Counsel Mr. Avinash Shivade. These observations have been quoted at page II of this petition. In the context of all these circumstance, we are inclined to condone delay and permit the petitioners to have their claim adjudicated on its own merits and in accordance with law but on payment of exemplary costs as directed below.

4. Hence order : This petition is allowed. The impugned Order No. 1752/88/WRB, dated 9-12-1988 (Exh. 'B') as also the impugned Order No. 1753/88/WRB, dated 9-12-1988 (Exh. 'C') are set aside and delay in filing the appeal in question is condoned and the appeal is directed to be heard and decided on its own merits and in accordance with law subject to the condition that the petitioners pay, latest by 25th April, 1989, to the Collector, Central Excise, Pune as and by way of exemplary costs of this petition, amount quantified at Rs. 5000/- (Rupees five thousand). If the said amount is not paid latest by 25th April 1989, the aforesaid impugned orders Exhibits 'B' and 'C' shall stand confirmed and this petition shall stand dismissed.

5. Rule is made absolute on conditions aforesaid with order of costs as directed above.