Som Datt Builders Pvt Ltd vs Karan Development Services Pvt Ltd

Som Datt Builders Pvt Ltd vs Karan Development Services Pvt Ltd

Type Court Judgment Court Delhi Orders Decided Jan 05, 2026
~3 min read
https://sooperkanoon.com/case/1274635

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Delhi Orders High Court
Judge
Decided On
Case Number
ARB.P./18/2026
Subject
Arbitration

Case Summary

AI-generated summary - not the official court judgment text.

Arbitration

Key legal issue
Arbitration

Parties & Advocates

Appellant / Petitioner

Som Datt Builders Pvt Ltd

Advocate Mr. Rakesh Kharb, Mr. Mukesh Kumar, Ms. Meenakshi Sood, Ms. Muskan Katyayan

Respondent

Karan Development Services Pvt Ltd

Advocate Mr. Gaurav Srivastava

Excerpt

.....be referred to the chief executive of the contractor who shall endeavor to reach agreement. 15.2 should the above two parties fail to agree within one month, the matter shall be referred for arbitration by a panel of three arbitrators. contractor and sub-contractor shall appoint one arbitrator each and these two appointed arbitrators shall appoint the third arbitrator who shall act as the presiding arbitrator. the decision of the majority of the arbitrators shall be final and binding on both the parties subject to the provisions in arbitration and conciliation act, 1996. 15.3. the venue of the arbitration shall be new delhi and the proceedings shall be in accordance with indian arbitration and conciliation, 1996.”2. a perusal of the prayer clause in the present petition wouldshow that the same are not very happily worded as the prayers seek for appointment of an arbitrator on behalf of the respondent. further, there is another prayer sought seeking a direction to the nominee arbitrators for appointing a presiding/third arbitrator.3. there is an apparent inconsistency between the two prayers as obviously if the court were to direct the appointment of an arbitrator on behalf of the respondent, there would be no “nominee” arbitrator of the respondent.4. nonetheless, as stated, the petitioner herein has already nominated hon‟ble justice badar durrez ahmed (retd.) as the arbitrator on its behalf and have also placed on record his consent dated 26.11.2025.5. mr. gaurav srivastava, learned counsel appearing for the respondent, states that the nominee arbitrator on behalf of the respondent would be hon‟ble mr. justice alok verma (retd. judge, madhya pradesh high court).6. the record does not reflect hon‟ble mr. justice alok verma‟sconsent. nonetheless, learned counsel appearing on behalf of the respondent would state that the learned judge has already accorded his consent to act as its arbitrator.7. in view of the foregoing, the present petition,.....

Full Judgment

* IN THE HIGH COURT OF DELHI AT NEW DELHI

+ ARB.P. 18/2026 SOM DATT BUILDERS PVT LTD .....Petitioner Through: Mr. Rakesh Kharb, Mr. Mukesh Kumar, Ms. Meenakshi Sood & Ms. Muskan Katyayan, Advs.

versus

KARAN DEVELOPMENT SERVICES PVT LTD .....Respondent Through: Mr. Gaurav Srivastava, Adv.

CORAM:

HON'BLE MR. JUSTICE HARISH VAIDYANATHAN

SHANKAR

ORDER

% 05.01.2026

1. The present petition has been filed under Section 11(6) of the

Arbitration and Conciliation Act, 1996, seeking the constitution of the Arbitral Tribunal in accordance with the Sub-contract dated 19.06.2006 executed between the parties herein. The Arbitration Clause contained in the Sub-contract dated 19.06.2006 is reproduced herein below: “15. ARBITRATION 15.1 Any dispute or difference between CONTRACTOR and SUB- CONTRACTOR arising out of this Agreement which cannot be resolved amicably shall be in the first instance be referred to the Chief Executive of the CONTRACTOR who shall endeavor to reach agreement. 15.2 Should the above two parties fail to agree within one month, the matter shall be referred for arbitration by a panel of three arbitrators. CONTRACTOR and SUB-CONTRACTOR shall appoint one arbitrator each and these two appointed arbitrators shall appoint the third arbitrator who shall act as the presiding arbitrator. The decision of the majority of the arbitrators shall be final and binding on both the parties subject to the provisions in Arbitration and Conciliation Act, 1996. 15.3. the venue of the arbitration shall be New Delhi and the proceedings shall be in accordance with Indian Arbitration and Conciliation, 1996.”

2. A perusal of the prayer clause in the present Petition would

show that the same are not very happily worded as the prayers seek for appointment of an Arbitrator on behalf of the Respondent. Further, there is another prayer sought seeking a direction to the Nominee Arbitrators for appointing a Presiding/Third Arbitrator.

3. There is an apparent inconsistency between the two prayers as obviously if the Court were to direct the appointment of an Arbitrator on behalf of the Respondent, there would be no “nominee” Arbitrator of the Respondent.

4. Nonetheless, as stated, the Petitioner herein has already nominated Hon‟ble Justice Badar Durrez Ahmed (Retd.) as the arbitrator on its behalf and have also placed on record his consent dated 26.11.2025.

5. Mr. Gaurav Srivastava, learned counsel appearing for the Respondent, states that the nominee arbitrator on behalf of the Respondent would be Hon‟ble Mr. Justice Alok Verma (Retd. Judge, Madhya Pradesh High Court).

6. The record does not reflect Hon‟ble Mr. Justice Alok Verma‟s

consent. Nonetheless, learned counsel appearing on behalf of the Respondent would state that the learned Judge has already accorded his consent to act as its Arbitrator.

7. In view of the foregoing, the present Petition, along with pending application(s), if any, is disposed of.

8. The learned Arbitrators are requested to take further steps for nomination of the Third Arbitrator in terms of the arbitration clause as expeditiously as possible.

HARISH VAIDYANATHAN SHANKAR, J.

JANUARY 5, 2026/v/va