Ashok Kumar Choudhary Vs. the State of Bihar and ors.

Ashok Kumar Choudhary vs The State of Bihar and ors.

Type Court Judgment Court Patna Decided Sep 09, 2005
~2 min read
https://sooperkanoon.com/case/120549

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Patna High Court
Judge
Decided On
Case Number
CWJC No. 10489 of 2003
Subject
;Arbitration

Case Summary

AI-generated summary - not the official court judgment text.

- - right in his submission that in view of the presence of the arbitration clause in the agreement, the petitioner would be well advised to resort to the same. In anyway arising out of, or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions, or otherwis...

Key legal issue
;Arbitration

Parties & Advocates

Appellant / Petitioner

Ashok Kumar Choudhary

Advocate Surendra Kumar, Adv.

Respondent

The State of Bihar and ors.

Advocate Alok Kumar, Adv. and Prasoon Sinha, Adv. for the Respondent Nos. 2 to 5

Court's Analysis

Prior History

S.K. Katriar, J.
1. Heard learned Counsel for the parties. According to the writ petition, the petitioner had entered into three contracts with the respondent corporation on 04.07.1998 which are on record as part of Annexure B to the Counter Affidavit. The petitioner complains before this Court that the work was completed as per the specifications but the full payment is not being made to him nor the security amount is refunded. The respondents have placed on record their counter affidavit and

Excerpt

- - right in his submission that in view of the presence of the arbitration clause in the agreement, the petitioner would be well advised to resort to the same. in anyway arising out of, or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work, or alter the completion or abandonment thereof, or as to the breach of this contract, then either party shall forthwith give to the other notice of such dispute or difference and such dispute or difference shall be referred to the chief engineer of the corporation and his decision shall be final, conclusive and binding on all the parties......in his submission that in view of the presence of the arbitration clause in the agreement, the petitioner would be well advised to resort to the same. the relevant clause is setout hereinbelow for the facility of quick reference:clause 23--in case any dispute or difference shall arise between the parties or either of them upon any question relating to the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned or as to the quality of workmanship or materials used on the work, or as to the construction of any of the conditions or any clause, or thing herein contained or as to any question, claim relating to liabilities of the parties or any matter, or thing whatsoever. in anyway arising out of, or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work, or alter the completion or abandonment thereof, or as to the breach of this contract, then either party shall forthwith give to the other notice of such dispute or difference and such dispute or difference shall be referred to the chief engineer of the corporation and his decision shall be final, conclusive and binding on all the parties.3. in that view of the matter, this writ petition is disposed of with the liberty to the petitioner to resort to the arbitration clause as setout herein-above.

Full Judgment

S.K. Katriar, J.

1. Heard learned Counsel for the parties. According to the writ petition, the petitioner had entered into three contracts with the respondent corporation on 04.07.1998 which are on record as part of Annexure B to the Counter Affidavit. The petitioner complains before this Court that the work was completed as per the specifications but the full payment is not being made to him nor the security amount is refunded. The respondents have placed on record their counter affidavit and have opposed the writ petition.

2. Mr. Prasoon Sinha, learned Counsel for the respondent corporation, is. right in his submission that in view of the presence of the arbitration clause in the agreement, the petitioner would be well advised to resort to the same. The relevant clause is setout hereinbelow for the facility of quick reference:

Clause 23--In case any dispute or difference shall arise between the parties or either of them upon any question relating to the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned or as to the quality of workmanship or materials used on the work, or as to the construction of any of the conditions or any clause, or thing herein contained or as to any question, claim relating to liabilities of the parties or any matter, or thing whatsoever. In anyway arising out of, or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work, or alter the completion or abandonment thereof, or as to the breach of this contract, then either party shall forthwith give to the other notice of such dispute or difference and such dispute or difference shall be referred to the Chief Engineer of the Corporation and his decision shall be final, conclusive and binding on all the parties.

3. In that view of the matter, this writ petition is disposed of with the liberty to the petitioner to resort to the arbitration clause as setout herein-above.