Full Judgment
W.P.No.3552/2013 06/05/2013 Shri Sunil Jain, learned counsel for the petitioner.
The dispute in question pertains to a dispute arising with regard to payment to the petitioner in relation to a works contract regarding construction of a school building.
The agreement in question and Clause-29 thereof itself contemplates an arbitration clause for resolution of the dispute between the parties.
As the dispute pertains to breach of contract and as in the agreement in question, there a provision for raising the dispute before the arbitrator, a writ petition directly before this Court is not maintainable.
Accordingly, the petition is dismissed with liberty to the petitioner to take recouRs.to the remedy available under law.
With the aforesaid, the petition is disposed of.
(Rajendra Menon) Judge nd