The State of Rajasthan Vs. Mohan Singh

The State of Rajasthan vs Mohan Singh

Disposition Appeal dismissed Court Rajasthan Decided Nov 18, 1992
~5 min read
https://sooperkanoon.com/case/763469

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Rajasthan High Court
Judge
Decided On
Case Number
S.B. Civil Second Appeal No. 126 of 1992
Subject
Civil
Disposition
Appeal dismissed

Case Summary

AI-generated summary - not the official court judgment text.

Civil Procedure Code - Section 102--Second appeal--Valuation of suit less than Rs. 3000/--Held, second appeal is not maintainable.;The plaintiff filed the suit for an amount of Rs. 2471/- and Section 102 of the Code of Civil Procedure provides that no second appeal shall lie in any suit of the nature to be heard by ...

Key legal issue
Civil
Outcome / disposition
Appeal dismissed

Parties & Advocates

Appellant / Petitioner

The State of Rajasthan

Respondent

Mohan Singh

Legal References

Reported In
1992WLN(UC)575

Excerpt

civil procedure code - section 102--second appeal--valuation of suit less than rs. 3000/--held, second appeal is not maintainable.;the plaintiff filed the suit for an amount of rs. 2471/- and section 102 of the code of civil procedure provides that no second appeal shall lie in any suit of the nature to be heard by the small causes court when the amount of the suit or the valuation of the subject-matter of the suit does not exceed rs. 3000/-. admittedly, the valuation of the present suit is less than rs. 3000/- and, therefore, in view of the bar, created by section 102 c.p.c, the second appeal is not maintainable.;(b) limitation act, 1963 - final bill not prepared--held, limitation does not start.;even as per the defendant's case, as set-up in the written-statement, the plaintiff had to complete his work upto february 26, 1972, but he actually completed the work on november 26, 1972, and took 270 days more than the period prescribed under the contract and the plaintiff has been paid 75% of the amount of the bill and only rs. 1464/- remained to be paid which can be paid to the plaintiff only after the final bill is prepared. even as per the stand taken by the defendant in the written-statement, the final bill has not been prepared and, therefore, the limitation does not start. the order passed by the learned lower court, thus, does not require any interference.;appeal dismissed - .....in case the contractor does not submit the final bill. as per the contention, raised by the learned counsel for the defendant the time starts from the date when the final bill is prepared. when no final bill was prepared then the computation of the time does not start. even as per the defendant's case, as set-up in the written-statement, the plaintiff had to complete his work upto february 26, 1972, but he actually completed the work on november 26, 1972, and took 270 days more than the period prescribed under the contract and the plaintiff has been paid 75% of the amount of the bill and only rs. 1464/- remained to be paid which can be paid to the plaintiff only after the final bill is prepared. even as per the stand taken by the defendant in the written-statement, the final bill, has not been prepared and, therefore, the limitation does not start. the order passed by the learned lower court, thus, does not require any interference. the learned lower court has taken into consideration all the facts and circumstances of the case and the order, passed by the learned lower court, cannot be said to be, in any way, unjust or arbitrary.5. in the result, i do not find any merit in the appeal and the same is hereby dismissed.

Full Judgment

B.R. Arora, J.

1. This appeal Is directed against the judgment dated May 16, 1992, passed by the Additional District Judge No. 3, Jodhpur, by which the learned Additional District Judge allow the appeal filed by the plaintiff and set-aside the decree and judgment dated May 14, 1983, passed by the Munsif and Judicial Magistrate, First Class, Jodhpur City, Jodhpur.

2. Plaintiff Mohan Singh - a 'C' Class Contractor with the Public Works Department - filed a suit for the recovery of an amount of Rs. 2471/- (Rs. 1444/- as the principal and Rs. 1027/- as interest). The case of the plaintiff, as set-out in the plaint, is that he was granted a contract for the construction of the road from Makrana to Borawar on November 27, 1971. The plaintiff completed the work in the year 1972. 10% of the amount, amounting to Rs. 5851/- was deducted from the running bills of the plaintiff which amount was to be paid to him after the final bill is prepared. No final bill upto this period was prepared, but in the year 1975, an amount of Rs. 4390 (75% of the total bill) was paid to the plaintiff. When this amount of Rs. 1464/- was not paid inspite of several requested, the palintiff served upon the defendant a notice under Section 80 C.P.C. on 4.1.80, which was received by the defendant on 10.1.80. Inspite of the service of the notice under Section 80 C.P.C, the amount was not paid and, therefore, the plaintiff filed a suit. This suit was contested by the defendant on various grounds. A preliminary objection was taken by the defendant that the suit is barred by time. According to the defendant, the limitation for filling the suit, as per Article 113 of the Limitation Act is only three years from the date of the completion of the work, which he completed in the year 1972, while the suit has been filed on 23.1.81. The learned Munsif treated this issue regarding the limitation as the preliminary issue and by his judgment dated May 14, 1982, decided the issue in favour of the defendant and against the plaintiff and held that the suit is barred by time. He, therefore, dismissed the suit filed by the plaintiff. Dissatisfied with the device any judgment dated May 14, 1982, passed by the learned Munsif, the plaintiff preferred an appeal before the learned District Judge, Jodhpur, which was transferred to the Court of the learned Additional District Judge No.3, Jodhpur, who, by his judgment dated May 16, 1992, set-aside the device any judgment passed by the learned Munsif and remanded the case to the learned trial Court to decide it in accordance with law. It is against this judgment dated May 16, 1992, that the appellant-the State of Rajasthan-has filed this appeal.

3. I have heard the learned Counsel for the appellant and perused the judgment passed by the learned lower Court. The State has filed this second appeal against the judgment dated May 16,1992, passed by the learned Additional District Judge No. 3, Jodhpur. It is not In dispute that the plaintiff filed the suit for an amount of Rs. 2472/- and Section 102 of the Code of Civil Procedure provides that no second appeal shall lie in any suit of the nature to be heard by the small causes court when the amount of the suit or the valuation of the subject-matter of the suit does not exceed Rs. 3000/-. Admittedly, the valuation of the present suit is less than Rs. 3000/- and, therefore, in view of the bar, created by Section 102 C.P.C., the second appeal is not maintainable.

4. Learned Counsel for the appellant, therefore, prays that this appeal may be treated as a revision. Even if this appeal is treated as the revision, even then no useful purpose will be served because the order passed by the learned lower Court does not require any interference. Of Course, the work was completed in the year 1972, but the plaintiff did not submit the final bill. Even no final bill was prepared by the Department, which ought to have been prepared in case the contractor does not submit the final bill. As per the contention, raised by the learned Counsel for the defendant the time starts from the date when the final bill is prepared. When no final bill was prepared then the computation of the time does not start. Even as per the defendant's case, as set-up in the written-statement, the plaintiff had to complete his work upto February 26, 1972, but he actually completed the work on November 26, 1972, and took 270 days more than the period prescribed under the Contract and the plaintiff has been paid 75% of the amount of the bill and only Rs. 1464/- remained to be paid which can be paid to the plaintiff only after the final bill is prepared. Even as per the stand taken by the defendant in the written-statement, the final bill, has not been prepared and, therefore, the limitation does not start. The order passed by the learned lower Court, thus, does not require any interference. The learned lower Court has taken Into consideration all the facts and circumstances of the case and the order, passed by the learned lower Court, cannot be said to be, In any way, unjust or arbitrary.

5. In the result, I do not find any merit in the appeal and the same Is hereby dismissed.