Delhi Development Authority Vs. Sudhir Chandra Aggarwal and anr.

Delhi Development Authority vs Sudhir Chandra Aggarwal and anr.

Disposition Appeal dismissed Court Delhi Decided May 03, 2005
~5 min read
https://sooperkanoon.com/case/697173

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Delhi High Court
Judge
Decided On
Case Number
LPA No. 1144/2004
Subject
Property;Civil
Disposition
Appeal dismissed

Case Summary

AI-generated summary - not the official court judgment text.

Government Grants Act - Section 3 -- Perpetual Lease -- Delay in construction of building required to take administrative decision after taking into consideration the circumstances of each case -- Denial of permission on the ground that power could be exercised within a period of three years from the death of allott...

Key legal issue
Property;Civil
Outcome / disposition
Appeal dismissed

Parties & Advocates

Appellant / Petitioner

Delhi Development Authority

Advocate Jagmohan Sabharwal, Sr. Adv. and; Deepak Khadaria, Adv

Respondent

Sudhir Chandra Aggarwal and anr.

Advocate Jayant Bhushan, Senior Adv. and ; Sudhir K. Makkar, Adv.

Legal References

Reported In
120(2005)DLT76; 2005(83)DRJ90

Excerpt

government grants act - section 3 -- perpetual lease -- delay in construction of building required to take administrative decision after taking into consideration the circumstances of each case -- denial of permission on the ground that power could be exercised within a period of three years from the death of allottee without considering other circumstances held illegal. - - 1. against the well reasoned order dated 28.07.2004 made by learned single judge in wp (c) no. it may be noted that if the authority has failed to exercise its discretion under misconception that clause 1.4 limits the power to grant maximum period of 3 years, it cannot be said that court is not required to interfere with the same......decision taking into consideration the circumstances of each case. this power cannot be said to be circumscribed by sub-clause (iv) of clause 1.4 here-in-above, which gives the maximum period of 3 years for exemption. needless to say that the facts must be such as would entitle the vice-chairman, dda to exercise such a power.8. the facts indicated here-in-above are clear that after 30.06.1973, the date on which shri chandra bhan aggarwal expired and as certain disputes arose, it was not possible for any of the legal heirs to carry out the construction.9. in view of pendency of the proceedings, one person could not have made an application to dda and / or all the persons too could not have made an application as there were certain disputes pending between the legal heirs of late shri chandra bhan aggarwal. the parties were before the court and after the mutation attained finality, the question was for mutation and the application thereof was allowed only on 29.04.2002. these facts were required to be taken into consideration and, in our view, considering these aspects, learned single judge has disposed of the matter and the said decision requires no interference.10. learned senior counsel for the appellant / dda further submitted that the discretion, which was exercised by the vice-chairman, dda was final and the court cannot substitute its own finding in case where the discretion is vested in the authority. it may be noted that if the authority has failed to exercise its discretion under misconception that clause 1.4 limits the power to grant maximum period of 3 years, it cannot be said that court is not required to interfere with the same. thus, the very basis of the exercise of the power is erroneous. it is not that this court sits as an appellate authority over such an administrative decision, but if on an incorrect interpretation of the clauses being clause 2.1 and clause 1.4, the decision is taken by the administrative authority, then learned single.....

Full Judgment

B.C. Patel, C.J.

1. Against the well reasoned order dated 28.07.2004 made by learned Single Judge in WP (C) No. 583/2001, the appellant Delhi Development Authority ( hereinafter to be referred to as, 'DDA' ) has preferred the present appeal.

2. The communication forwarded by DDA dated 09.07.2002 allowing extension of time to the petitioners (respondents herein) to complete construction of the building on plot bearing No. A - 25, Niti Bagh, New Delhi on composition fee in the sum of Rs.41,38,595/- was the subject matter before learned Single Judge.

3. It is required to be noted that perpetual sub-lease was executed on 30.11.1972. However, before the two years during which construction was to be completed, Shri Chandra Bhan Aggarwal in whose favor document was executed expired on 30.06.1973. In view of large estate, it appears that there was a dispute amongst the legal heirs of late Shri Chandra Bhan Aggarwal and mutation ultimately attained finality on 24.08.2000. It is thereafter the application submitted for mutation was sanctioned on 29.04.2002. Soon thereafter, an application was made for extension of time for making construction on the said plot. However, by letter dated 09.07.2002, it was stated that the application can be granted subject to certain conditions, i.e., payment of composition fee as noted here-in-above.

4. Learned senior counsel appearing for the appellant / DDA drew our attention to the relevant provisions, i.e., the extracts produced at Annexure A - 2. Clause 1.4 refers to exemption from the levy of annual composition fee. Sub-clause (iv) of clause 1.4 refers to death of the allottee and subsequent delay in mutation where 3 years is the maximum period to be granted. In other eventualities, as indicated in sub-clause (v) of clause 1.4, the maximum period is granted up to 5 years. The relevant clauses are as under:

'1.4 EXEMPTIONS : The exemption from the levy of annual composition fee in the policy will be available as follows :. ... ... ... ... ...

(iv) Death of the allottee and subsequent delays in mutation, sickness of the allottee from chronic and incurable disease which results in physical disablement to construct house ?' 3 years maximum.

(v) Where due to exigencies of service condition, lessee is out of country after allotment of plot ?' maximum period of 5 years.

(vi) Where the lessee/sub-lessee has been transferred outside Delhi. This facility would be available to all Central/Delhi Admn./All India Service/the Public Sector undertakings officials posted in Delhi including defense Personnel - maximum of 5 years.

... ... ... ... ... ...'

5. The Court examined clause 2.1, which refers to composition charges for belated construction. The said clause 2.1 is as under:

'2.1 : V.C., DDA shall be competent to condone delays in construction of building with / without composition as the circumstances of the case warrant.'

6. Thus, the Vice-Chairman, DDA was required to exercise his power under this clause. It refers to two aspects, namely, (i) delay in construction of building; and (ii) with or without composition charges.

7. In view of the aforesaid provisions, the Vice-Chairman, DDA is required to take an administrative decision taking into consideration the circumstances of each case. This power cannot be said to be circumscribed by sub-clause (iv) of clause 1.4 here-in-above, which gives the maximum period of 3 years for exemption. Needless to say that the facts must be such as would entitle the Vice-Chairman, DDA to exercise such a power.

8. The facts indicated here-in-above are clear that after 30.06.1973, the date on which Shri Chandra Bhan Aggarwal expired and as certain disputes arose, it was not possible for any of the legal heirs to carry out the construction.

9. In view of pendency of the proceedings, one person could not have made an application to DDA and / or all the persons too could not have made an application as there were certain disputes pending between the legal heirs of late Shri Chandra Bhan Aggarwal. The parties were before the Court and after the mutation attained finality, the question was for mutation and the application thereof was allowed only on 29.04.2002. These facts were required to be taken into consideration and, in our view, considering these aspects, learned Single Judge has disposed of the matter and the said decision requires no interference.

10. Learned senior counsel for the appellant / DDA further submitted that the discretion, which was exercised by the Vice-Chairman, DDA was final and the Court cannot substitute its own finding in case where the discretion is vested in the authority. It may be noted that if the authority has failed to exercise its discretion under misconception that clause 1.4 limits the power to grant maximum period of 3 years, it cannot be said that Court is not required to interfere with the same. Thus, the very basis of the exercise of the power is erroneous. It is not that this Court sits as an appellate authority over such an administrative decision, but if on an incorrect interpretation of the clauses being clause 2.1 and clause 1.4, the decision is taken by the administrative authority, then learned Single Judge was right in interfering with the same and issuing necessary directions.

11. We find no merits in the appeal. Hence, the appeal and the application are dismissed.