In Re : Bringing Generating

Type Court Judgment Court Central Electricity Regulatory Commission CERC Decided Feb 13, 2006
~2 min read
https://sooperkanoon.com/case/52719
CiteSignal

Log in to get a daily email when new judgments cite this order.

Citation
Court
Central Electricity Regulatory Commission CERC
Judge
Decided On

Parties & Advocates

Appellant / Petitioner

In Re : Bringing Generating

Bonus Feature

AI Brief & Ask

Your first-pass case note in minutes — an 18-section AI Brief on this judgment, plus case-scoped chat. Part of AI Studio with Verdict Lens, Devil's Bench, and DocMind.

Try free for 7 days

Credentials emailed — then log in for AI Brief on this judgment. Already have an account? · Learn more

Excerpt

.....with effect from 1.12.2005.2. ntpc filed an affidavit stating that it had installed special energy meters on outgoing feeders for measurement of actual ex-bus generation and had also installed necessary communication facilities. however, the joint action plan could not be prepared since kerala state electricity board (kseb), the beneficiary, had certain reservations to the proposal of implementation of abt. it was stated that kseb would be directly approaching the commission to apprise it of the technical difficulties.no formal request was received from kseb. accordingly, notices were issued to the parties concerned.3. we have heard shri v.b.k. jain for ntpc and the representative of kseb, who narrated the technical difficulties and made a prayer for deferment of the proposal of implementation of abt on the generating station.4. we direct that the difficulties envisaged by kseb shall be placed on record before the commission through an affidavit latest by 20.2.2006.these difficulties will be considered by a one-member bench of the commission with shri bhanu bhushan, member. the bench will make appropriate recommendations to the commission after hearing the parties concerned,.....

Full Judgment

1. The Commission by its order dated 4.7.2005 had decided to implement ABT on single-beneficiary generating stations, which included Kayamkulam GPS owned by National Thermal Power Corporation Limited (NTPC), the generating company owned or controlled by the Central Government, with effect from 1.12.2005.

2. NTPC filed an affidavit stating that it had installed special energy meters on outgoing feeders for measurement of actual ex-bus generation and had also installed necessary communication facilities. However, the joint action plan could not be prepared since Kerala State Electricity Board (KSEB), the beneficiary, had certain reservations to the proposal of implementation of ABT. It was stated that KSEB would be directly approaching the Commission to apprise it of the technical difficulties.

No formal request was received from KSEB. Accordingly, notices were issued to the parties concerned.

3. We have heard Shri V.B.K. Jain for NTPC and the representative of KSEB, who narrated the technical difficulties and made a prayer for deferment of the proposal of implementation of ABT on the generating station.

4. We direct that the difficulties envisaged by KSEB shall be placed on record before the Commission through an affidavit latest by 20.2.2006.

These difficulties will be considered by a one-member Bench of the Commission with Shri Bhanu Bhushan, Member. The Bench will make appropriate recommendations to the Commission after hearing the parties concerned, latest by 5.3.2006. The parties shall appear before the Bench on 24.2.2006 at Thiruvananthapuram at 4.30 P.M.