Skip to content
How to use Judgment tools
  1. Click Tools to open PDF, Print, Tag, Note, Favourite, and CiteSignal.
  2. Use Brief & Ask in the toolbar for the AI Brief and case chat.
  3. Jump to sections with the pills below the help bar.

Ashok Kumar Tumberia Vs. Hardwar Development Authority, Hardwar and Another

Ashok Kumar Tumberia vs Hardwar Development Authority, Hardwar and Another

Type Court Judgment Court Allahabad Decided Jan 07, 1997
~5 min read
https://sooperkanoon.com/case/451279

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Allahabad High Court
Judge
Decided On
Case Number
Civil Misc. Writ Petn. No. 1115 of 1994
Subject
Civil

Case Summary

AI-generated summary - not the official court judgment text.

Civil - levy of compounding fees - Section 32 of U.P. Urban Planning and Development Act, 1973 - notice for stopping illegal construction issued - application for quashing notices issued, demanding fees for illegal construction - construction continued - construction that comes in way of street alignment is illegal,...

Key legal issue
Civil
Acts & sections
Uttar Pradesh Urban Planning and Development Act, 1973 - Sections 32; Constitution of India - Article 226

Parties & Advocates

Appellant / Petitioner

Ashok Kumar Tumberia

Advocate Shashi Kant and ;S.N. Kesarwani, Advs.

Respondent

Hardwar Development Authority, Hardwar and Another

Advocate P.M. Gupta, Adv.

Legal References

Reported In
AIR1997All220

Excerpt

civil - levy of compounding fees - section 32 of u.p. urban planning and development act, 1973 - notice for stopping illegal construction issued - application for quashing notices issued, demanding fees for illegal construction - construction continued - construction that comes in way of street alignment is illegal, compounding cannot cure such defect - no action taken further by authorities - held, matter remanded to local administration, requiring district magistrate/ collector to make an enquiry. - - 2,67,588/- is charged, reffects very badly on an administration which is supposed to regulate urbanisation. the court also is not satisfied with the defence of the hardwar development authority in the counter affidavit......the petitioner.5. the notice of the hardwar development authority dated 30-6-1993 make it clear that on either side of the road, called upper road athardwar, on one side there is a mayur hotel andon the other side the illegal constructions of thepetitioner. these constructions are on the roadside. do these constructions violate the streetalignment? what was the petitioner's title to theland on which the constructions have been made? was the petitioner allotted the land for construction as licensee by the local administration? wasthe petitioner owner of the land as opposed to alicence? the court is reflecting on these aspectsas the petitioner has given no facts.6. prima facie from the record of the writ petition it appears that his occupation is of a land on the road side but this has to be determined as a measure of certainty. if it is on road side violating the side walk or a pavement, patri or the drain which follows the road, then the question of sanction or any compounding by the hardwar development authority does noi arise. if these constructions are beyond the line of street alignment then the set back has to be left. this set back, cannot be violated. the laws which govern an urban habitat to ensure that this space should be left as a set back from the edge of the road determines the line of street alignment. constructions on both these areas whether the road, side walk-patri, drain or the set back from the edge of the road, if violated are illegalities which cannot be cured and are incapable of being cured. far from compounding these constructions, the constructions cannot even be permitted.7. the court is concerned that the hardwar development authority seemed to be compromising its noties whereas at one stage it asked the petitioner to stop the construction, thereafter it was a silent spectator to these illegal constructions being completed gradually and violating the very notices which restrained the constructions from proceeding. this is collusion......

Full Judgment

ORDER

1. This is a matter from Hardwarwhere the petitioner desires that the notices issued to him by Hardwar Development Authority dated 28, September, 1993 and 18 October, 1993, annexures 6 and 7 respectively, demanding compounding fee of Rs. 2,67,588/- for making the illegal consirue lions, be quashed.

2. The Court has heard counsel for the petitioner Sri S. N. Kesarwani and Sri P. M. Gupta, learned counsel appearing on behalf of Hardwar Development Authority.

3. The Court neither agrees with the petitioner nor with the respondents. Of the illegalities which the petitioner has committed by making constructions without permission, the Hardwar Development Authority seems to have compromised the situation and nakedly watched the construction of a building which was not supposed to be made completed and then belittling and compromising its status as a Development Authority to compound a construction which had been made illegally.

4. As far as the writ petition concerned it is devoid of details on what exactly is the title of the petitioner to the land on which the constructions were made illegally and without permission. The petitioner avoids giving this essential fact to the Court and the Hardwar Development Authorily has made no effort to find out the petitioner's ownership on the area where the constructions were attempted and later completed despite notice to the petitioner. The first notice is dated 30-6-1993, Annexure-3 to the writ petition. It cautions that the building opposite Mayur Hotel, Upper Road, Hardwar, being made without a sanction plan, the constructions as on that day being the basement and the ground floor cease forthwith. One aspect is very relevant that at the time when this notice was delivered to the petitioner a basement had been dug and was under construction along with the ground floor. How did the petitioner proceed with the construction to complete the entire building when he had already been cautioned to stop the construction. The petitioner completed the construction in the face of this notice. He violated the law. Both law and equity are against the petitioner.

5. The notice of the Hardwar Development Authority dated 30-6-1993 make it clear that on either side of the road, called Upper Road atHardwar, on one side there is a Mayur Hotel andon the other side the illegal constructions of thepetitioner. These constructions are on the roadside. Do these constructions violate the streetalignment? What was the petitioner's title to theland on which the constructions have been made? Was the petitioner allotted the land for construction as licensee by the local administration? Wasthe petitioner owner of the land as opposed to alicence? The Court is reflecting on these aspectsas the petitioner has given no facts.

6. Prima facie from the record of the writ petition it appears that his occupation is of a land on the road side but this has to be determined as a measure of certainty. If it is on road side violating the side walk or a pavement, Patri or the drain which follows the road, then the question of sanction or any compounding by the Hardwar Development Authority does noi arise. If these constructions are beyond the line of street alignment then the set back has to be left. This set back, cannot be violated. The laws which govern an urban habitat to ensure that this space should be left as a set back from the edge of the road determines the line of street alignment. Constructions on both these areas whether the road, side walk-Patri, drain or the set back from the edge of the road, if violated are illegalities which cannot be cured and are incapable of being cured. Far from compounding these constructions, the constructions cannot even be permitted.

7. The Court is concerned that the Hardwar Development Authority seemed to be compromising its noties whereas at one stage it asked the petitioner to stop the construction, thereafter it was a silent spectator to these illegal constructions being completed gradually and violating the very notices which restrained the constructions from proceeding. This is collusion. First asking the petitioner not to make constructions and ultimately creating a record so that the compounding fee of Rs. 2,67,588/- is charged, reffects very badly on an administration which is supposed to regulate urbanisation.

8. In the circumstances the Court considers it appropriate that this entire matter shall stand remanded to the local administration. The Court is now requiring the District Magistrate/Collector Hardwar to make an enquiry into this matter and first find out where exactly is the location of the constructions made by the petitioner, whether it ison the road side, side walk, pavement or protected space of setbacks. If the answer to this enquity is in the affirmative, then these constructions have to go. Further the District Magistrate/Collector, Hardwar will cause an enquiry to be made how the constructions were completed after the notice of 30-3-1993 and despite the fact that the petitioner was on a notice to desist from constructions. Whoever were embroiled in this collusion, appropriate action shall be considered and taken by the District Magistrate/Collector, Hardwar. The District Magistrate/Collector, Hardwar, will also en-sure that no further constructions are carried out by the petitioner nor any finishing work under-taken nor the buildingis let out while this enquiry is in progress.

9. The Court does not find any merit in this writ petition and it is dismissed. The Court also is not satisfied with the defence of the Hardwar Development Authority in the counter affidavit.

10. The petition is dismissed with costs.

11. The interim orders dated 19-1-1994 and 16-2-1994 are discharged.

12. A copy of this order may be sent to the Principal Secretary, Urban Development, Uttar Pradesh, Shashan, Lucknow.

13. Learned Standing Counsel present in Court Mr. Krishna Prasad and Mr. P. M. Gupta, appearing on behalf of the respondents, have been authorised to send a copy of this order to the District Magistrate Collector, Hardwar.

14. Petition dismissed.