P.Rajamani vs the Designated Engineer

P.Rajamani vs The Designated Engineer

Type Court Judgment Court Chennai Decided Jan 27, 2026
~3 min read
https://sooperkanoon.com/case/1430276

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Chennai High Court
Judge
Decided On
Case Number
WP/9727/2025

Parties & Advocates

Appellant / Petitioner

P.Rajamani

Respondent

The Designated Engineer

Excerpt

.....same is not provided within the said time limit the application would be rejected without any further intimation. thereafter, on 11.11.2024 the petitioner made a representation to the respondents, to which the 2 nd respondent issued a reply dated 19.11.2024 queries will be clarified by the office of concerned bhavani taluk. however, there is no action on the side of the respondents. therefore, the petitioner is before this court.5. the learned counsel for the tangedco would submit thatthe petitioner has not enclosed requisite documents to provide electricity service connection. if the application is made with all the requisite documents, the same will be considered and orders passed.6. considering the facts and circumstances of the case and thesubmission made by the learned counsel for the tangedco, this writ petition is disposed of with a direction to the petitioner to apply a fresh for a new service connection, within a period of 2 weeks from the date of receipt of a copy of this order. the petitioner shall enclose a copy of the property tax receipts and an indemnity, along with the application considering the fact that the property in question is a porambokke land. on receipt of the same, the application shall be considered and orders passed by the 2nd respondent within a period of 3 weeks therefrom. no costs. 27.01.2026kan to 1.the designated engineer, o&m, anthiyur, erode. 2.the chief engineer, 949- evn road, erode- 638 009 3.the junior engineer, annamaduvu, anthiyur- 638 314 p.t. asha, j kan 27.01.2026

Full Judgment

IN THE HIGH COURT OF JUDICATURE AT MADRAS

Dated : 27.01.2026

CORAM

THE HONOURABLE Ms. JUSTICE P.T. ASHA W.P.No. 9727 of 2025 P. Rajamani ...petitioner Vs. 1.The Designated Engineer, O&M, Anthiyur, Erode. 2.The Chief Engineer, 949- EVN Road, Erode- 638 009 3.The Junior Engineer, Annamaduvu, Anthiyur- 638 314 ...respondents Prayer: Writ Petition is filed under Section 226 of the Constitution of India for issue of Writ of Mandamus, directing the 2nd respondent to grant Domestic Residential electricity connection to the petitioner's house situated at No, 11 B, Sivasakthi Nagar 2, Anthiyur, Erode. For petitioner : Mr. P.K.Harinath Babu For respondents : Mr. Syed Sibuthullah (TANGEDCO)

ORDER

This writ petition is filed for the following relief: “To direct the 2nd respondent to grant Domestic Residential electricity connection to the petitioner's house situated at No, 11 B, Sivasakthi Nagar 2, Anthiyur, Erode”

2. The petitioner would submit that she is residing in the subject

property for nearly 45 years along with her husband and her two children. The land in which they are residing is a poromboke land. The petitioner’s husband died on 09.01.2017. The petitioner would further submit that she made a request for issuance for patta on 26.11.2018, which has not been considered.

3. The case of the petitioner is that for the purpose of obtaining

electricity connection, she had obtained ‘no objection certificate’ from the Village Administrative Officer, Anthiyur, Erode on 19.06.2020. The petitioner made an application dated 21.06.2020 before the 1 st respondent seeking electricity connection for the said property.

4. On 22.06.2020, the 3rd respondent issued a notice stating that

required documents need to be furnished by the petitioner to provide new electricity supply and if the same is not provided within the said time limit the application would be rejected without any further intimation. Thereafter, on 11.11.2024 the petitioner made a representation to the respondents, to which the 2 nd respondent issued a reply dated 19.11.2024 queries will be clarified by the office of concerned Bhavani Taluk. However, there is no action on the side of the respondents. Therefore, the petitioner is before this Court.

5. The learned counsel for the TANGEDCO would submit that

the petitioner has not enclosed requisite documents to provide electricity service connection. If the application is made with all the requisite documents, the same will be considered and orders passed.

6. Considering the facts and circumstances of the case and the

submission made by the learned counsel for the TANGEDCO, this writ petition is disposed of with a direction to the petitioner to apply a fresh for a new service connection, within a period of 2 weeks from the date of receipt of a copy of this order. The petitioner shall enclose a copy of the property tax receipts and an indemnity, along with the application considering the fact that the property in question is a porambokke land. On receipt of the same, the application shall be considered and orders passed by the 2nd respondent within a period of 3 weeks therefrom. No costs. 27.01.2026

kan To 1.The Designated Engineer, O&M, Anthiyur, Erode. 2.The Chief Engineer, 949- EVN Road, Erode- 638 009 3.The Junior Engineer, Annamaduvu, Anthiyur- 638 314 P.T. ASHA, J kan 27.01.2026