Full Judgment
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 27-02-2026
CORAM
THE HONOURABLE MR.JUSTICE P. DHANABAL in CS No.123 of 2025
1. The Area Engineer Zone XIII, Office of the Water Supply and Sewage Board, Indra Nagar, Adyar, Chennai - 600 020. Applicant(s) Vs
1. K.Vanniyarajan
S/o.Kasirajan, No.70A, Kamarajar Street, Anna Nagar, Tharamani, Chennai 600 113. Respondent(s) For Applicant(s): Mr.Jerry V.V.Sundar For Respondent: Mr.R.Balachandran
ORDER
This application has been filed by the applicant to condone the delay of representation of 133 days in written statement of the eighth defendant in CS No.123 of 2025.
2. The other side has not seriously objected.
3. Considering the reasons stated in the affidavit and facts and
circumstances of the case, in order to give a fair chance to the eight defendant to put forth their defense, it is appropriate to allow this application. Accordingly, this application is allowed. Post the matter on 12.03.2026. mtl P. DHANABAL, J., mtl