Skip to content
How to use Judgment tools
  1. Click Tools to open PDF, Print, Tag, Note, Favourite, and CiteSignal.
  2. Use Brief & Ask in the toolbar for the AI Brief and case chat.
  3. Jump to sections with the pills below the help bar.

Gopidasan Vs. Ramakrishnan

Gopidasan vs Ramakrishnan

Type Court Judgment Court Kerala State Consumer Disputes Redressal Commission SCDRC Thiruvananthapuram Decided Sep 27, 2010
~2 min read
https://sooperkanoon.com/case/1110044

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Kerala State Consumer Disputes Redressal Commission SCDRC Thiruvananthapuram
Judge
Decided On
Case Number
First Appeal No. A/10/487 (Arisen out of order dated 29/07/2010 in Case No. CC117/O9 of District Palakkad)
Subject
Land Acquisition

Case Summary

AI-generated summary - not the official court judgment text.

Land Acquisition

Key legal issue
Land Acquisition

Parties & Advocates

Appellant / Petitioner

Gopidasan

Respondent

Ramakrishnan

Excerpt

.....defects went unheeded. the complainant in order to complete the work would require an amount of rs.9000/-. he has claimed also a sum of rs. 5000/- as compensation. 3. the case of the opposite parties/appellant is that the complainant made him believe that the well is having a depth of 17-18 kole and that there is no rock under neath. the well was filled with soil. the complainant had also told that labour charges will have to be paid in addition. while removing the soil the rings stipped down and settled on the sloppy rock. the complainant became violent and directed the opposite party to leave the place. thereafter, a mediation was conducted and complainant agreed to pay rs.6,000/- for completing the work. but the complainant did not allow him to complete the work. 4. the evidence adduced consisted of the proof affidavits filed by both sides and exts.a1 to a4. 5. on a perusal of the order it appears that the appellant did not complete the work undertaken. being an expert engaged in such works, it is for the appellant to fix the amounts exactly. evidently, the appellant has left the work after executing it in part in a defective manner. 6. in the circumstances, we find that there is scope for admitting the appeal. hence the appeal is dismissed in limine. office will forward the copy of this order to the forum urgently.

Full Judgment

JUSTICE SHRI.K.R.UDAYABHANU,PRESIDENT

The appellant is the opposite party who is under orders to pay a sum of Rs.5000/- as compensation and Rs.1000/- as costs.

2. The case of the complainant is that the opposite party had agreed to erect concrete rings in the well. After inspection of the well, it was informed that 14 rings are to be erected. The amount was fixed at Rs.15,400/-. The complainant paid Rs.10,000/- and subsequently, Rs.1,500/- by cheques. During the work, opposite party demanded higher amount. The complainant paid Rs.1,800/- .

The opposite party inserted 8 rings. He did not do the work properly. The rings inserted slipped towards one side and fell into the well. The same was occasioned on account of the defect in the works executed. The request of the complainant to rectify the defects went unheeded. The complainant in order to complete the work would require an amount of Rs.9000/-. He has claimed also a sum of Rs. 5000/- as compensation.

3. The case of the opposite parties/appellant is that the complainant made him believe that the well is having a depth of 17-18 kole and that there is no rock under neath. The well was filled with soil. The complainant had also told that labour charges will have to be paid in addition. While removing the soil the rings stipped down and settled on the sloppy rock. The complainant became violent and directed the opposite party to leave the place. Thereafter, a mediation was conducted and complainant agreed to pay Rs.6,000/- for completing the work. But the complainant did not allow him to complete the work.

4. The evidence adduced consisted of the proof affidavits filed by both sides and Exts.A1 to A4.

5. On a perusal of the order it appears that the appellant did not complete the work undertaken. Being an expert engaged in such works, it is for the appellant to fix the amounts exactly. Evidently, the appellant has left the work after executing it in part in a defective manner.

6. In the circumstances, we find that there is scope for admitting the appeal. Hence the appeal is dismissed in limine.

Office will forward the copy of this order to the Forum urgently.

Continue Your Research