Terms. in Cwp No.4698 of 2013 It Has Been Held as Under:- Vs. Punjab Urban Planning and Development Authority and Others

Terms. in Cwp No.4698 of 2013 It Has Been Held as Under:- vs Punjab Urban Planning and Development Authority and Others

Type Court Judgment Court Punjab and Haryana Decided May 20, 2013
~2 min read
https://sooperkanoon.com/case/1071577

For advocates & juniors · 7-day free trial

Brief this judgment before chambers

Stop skimming 50 pages - get an 18-section AI Brief on this case, ask scoped follow-ups, and find related precedents with Semantic Search. Full trial, no card required.

  • 18-section brief - facts, issues, ratio, relief
  • Ask this case - answers cite the judgment
  • Semantic search - find precedents by meaning
  • Research drawer - sections, cites, related cases

No card required · credentials emailed · Log in if you already have an account

Citation
Court
Punjab and Haryana High Court
Decided On
Subject
Education

Case Summary

AI-generated summary - not the official court judgment text.

Education

Key legal issue
Education

Parties & Advocates

Appellant / Petitioner

Terms. in Cwp No.4698 of 2013 It Has Been Held as Under:-

Respondent

Punjab Urban Planning and Development Authority and Others

Excerpt

.....for respondent no.6 1. to be referred to the reporters or not?.”2. whether the judgment should be reported in the digest?.rajiv narain raina, j. (oral) the prayer in this petition is for release of temporary electricity connection in the light of the order passed by this court in cwp no.4698 of 2013 and connected petitions decided on 15.05.2013. learned counsel for the respondent-corporation very fairly concedes that the controvers.raised in the present petition is squarely covered by the decision rendered in the above noted cwp no.4698 of 2013 and, therefore, prays that the instant petition be also disposed of in the same terms.in cwp no.4698 of 2013 it has been held as under:- “learned counsel for the petitioners assert that there is a stay on further construction in cwp no.10331 of 2012 pending before the ist bench. the question of environmental clearance is pending before the ministry of environment, new delhi. it may take some time to resolve the issue. the prayer in these petitions is for grant of temporary domestic electricity connections to the petitioners and the petitioners undertake that the supply of energy to their dwelling units will not give them any equitable right of saving the construction, in case, ultimately it is found that the buildings are required to be demolished.” the writ petition is accordingly disposed of with a direction to the respondent-punjab state power corporation ltd.to install the temporary cwp no.10298 of 2013 -2- domestic electricity connections/meters and energize the same within seven days from the date of receipt of certified copy of this order in terms of the period of mechanism made out in cwp no.11735 of 2010 (heena yadav versus the state of punjab and others.decided on 02.08.2011 and the conditions/undertakings imposed in the aforesaid cwp no.4698 of 2013 (raj kumar and another versus state of punjab and others).disposed of in view of the above terms.(rajiv narain raina) judge 20 05.2013 rajeev

Full Judgment

CWP No.10298 of 2013 -1- IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH CWP No.10298 of 2013 Date of Decision:20.5.2013 Rajinder Kumar and others ....Petitioners Versus Punjab Urban Planning and Development Authority and others ....Respondents CORAM:- HON'BLE Mr.JUSTICE RAJIV NARAIN RAINA Present: Mr.R.K.Arya, Advocate for the petitioneRs.Mr.T.N.Sarup, Addl.

A.G.Punjab.

Mr.Vikas Chatrath, Advocate for respondents No.2 to 5.

Mr.S.K.Yadav, Advocate for respondent No.6 1.

To be referred to the Reporters or not?.”

2. Whether the judgment should be reported in the Digest?.

RAJIV NARAIN RAINA, J.

(Oral) The prayer in this petition is for release of temporary electricity connection in the light of the order passed by this Court in CWP No.4698 of 2013 and connected petitions decided on 15.05.2013.

Learned counsel for the respondent-Corporation very fairly concedes that the controveRs.raised in the present petition is squarely covered by the decision rendered in the above noted CWP No.4698 of 2013 and, therefore, prays that the instant petition be also disposed of in the same terMs.In CWP No.4698 of 2013 it has been held as under:- “Learned counsel for the petitioners assert that there is a stay on further construction in CWP No.10331 of 2012 pending before the Ist Bench.

The question of environmental clearance is pending before the Ministry of Environment, New Delhi.

It may take some time to resolve the issue.

The prayer in these petitions is for grant of temporary domestic electricity connections to the petitioners and the petitioners undertake that the supply of energy to their dwelling units will not give them any equitable right of saving the construction, in case, ultimately it is found that the buildings are required to be demolished.”

The writ petition is accordingly disposed of with a direction to the respondent-Punjab State Power Corporation LTD.to install the temporary CWP No.10298 of 2013 -2- domestic electricity connections/meters and energize the same within seven days from the date of receipt of certified copy of this order in terms of the period of mechanism made out in CWP No.11735 of 2010 (Heena Yadav versus The State of Punjab and otheRs.decided on 02.08.2011 and the conditions/undertakings imposed in the aforesaid CWP No.4698 of 2013 (Raj Kumar and another versus State of Punjab and others).Disposed of in view of the above terMs.(RAJIV NARAIN RAINA) JUDGE 20 05.2013 rajeev