Arm Construction Co. Vs. Union of India
Delhi
Apr-09-1979
Arbitration
Arbitration Act, 1940 - Sections 20
1980RLR307
Sultan Singh, J.(1) [PETITIONER contracted with Railway for constructing a certain building. Work was completed on 20.9.76. Petitioner was allowed payment of final bill only after he had given 'No claim Certificate' under clause 43 (2)...