Skip to content


M/S Ncr Developers vs.university of Delhi - Court Judgment

SooperKanoon Citation
CourtDelhi High Court
Decided On
AppellantM/S Ncr Developers
RespondentUniversity of Delhi
Excerpt:
.....in the clause to the effect “it is also a term of this contract that no person other than a person appointed by v.c./administrative v.c as aforesaid should act as arbitrator and if for any reason that is not possible the matter is not to be referred to arbitration at all” it is contended that arbitration clause does not survive. arb.p. 180/2019 page 2 of 18 submission of the parties:4. the court has heard the learned counsels for the parties at considerable length. mr. nishit kush learned counsel for the... petitioner argues that notwithstanding the wording of the clause noted above, the court is not denuded of it’s power to appoint an arbitrator. the arbitration clause has to be given a meaningful construction. there is no named arbitrator and the clause provides for.....
Judgment:

$~22 * + % IN THE HIGH COURT OF DELHI AT NEW DELHI ARB.P. 180/2019 M/S NCR DEVELOPERS ........ Petitioner

Through: Mr. Nishit Kush, Ms. Mercy Hussain and Ms. Asma, Advocates. versus UNIVERSITY OF DELHI ..... Respondent Through: Ms. Aakansha Kaul, Advocate. CORAM: HON'BLE MR. JUSTICE SANJEEV NARULA ORDER

2504.2019 SANJEEV NARULA, J.:

1. The present petition under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (herein after referred to as the 'Act') seeks appointment of an independent Arbitrator. Brief Facts 2. The... Petitioner

was awarded the contract for Recasting dilapidated/Broken RCC Chajjas, exterior wall painting plasteraluminum work and repair works in the New Administrative Block,University of Delhi by the Respondent on 4th February 2015 for an amount of Rs. 47,39,140/- (forty seven lacs thirty nine thousand one hundred forty only). A formal contract was executed between the... Petitioner

and the Respondent on 13th February 2015. It is the case of the... Petitioner

that the work was successfully completed on 31st ARB.P. 180/2019 Page 1 of 18 March 2016. Respondent issued a completion certificate dated 14th December 2016.... Petitioner

wrote several letters to the Respondent calling upon them to release the payment for the completed work. The Respondent called upon the... Petitioner

for negotiation and was informed by the Registrar, DU that the outstanding amount will not be released unless it is lowest in terms of the excess expenditure. Having no alternative,... Petitioner

agreed to settle for an amount Rs. 62,75,716.19/- (Sixty Two Lacs Seventy Five ThousandSeven Hundred Sixteen) as full and final settlement of it’s outstanding dues. Against the said amount, the Respondent released part payment of Rs. 24,60,030/- (Twenty Four Lacs Sixty ThousandThirty).... Petitioner

contends that since the Respondent has failed to release the entire amount of Rs. 62,75,716.19/- (Sixty Two Lacs Seventy Five ThousandSeven Hundred Sixteen), it is entitled to recover the actual cost/expenditure incurred for completion of the work.... Petitioner

invoked the Arbitration Clause vide notice dated 14th September 2018 and called upon the Respondent to appoint the Sole Arbitrator. Since the Respondent has failed to appoint an Arbitrator within a period of 30 days of the receipt of the notice, the... Petitioner

has approached this Court by way of the present petition.

3. Respondent does not dispute the existence of the Arbitration clause or it's invocation. However, relying on the condition contained in the clause to the effect “It is also a term of this contract that no person other than a person appointed by V.C./Administrative V.C as aforesaid should act as arbitrator and if for any reason that is not possible the matter is not to be referred to arbitration at all” it is contended that Arbitration clause does not survive. ARB.P. 180/2019 Page 2 of 18 Submission of the parties:

4. The Court has heard the learned counsels for the parties at considerable length. Mr. Nishit Kush learned counsel for the... Petitioner

argues that notwithstanding the wording of the clause noted above, the Court is not denuded of it’s power to appoint an Arbitrator. The arbitration clause has to be given a meaningful construction. There is no named Arbitrator and the clause provides for appointment by designation of the Appointing Authority i.e VC, Delhi University or the administrative head of the Delhi University as the case may be. Since the Respondent has failed to appoint an Arbitrator within a period of 30 days of the invocation notice, the Court has the power to appoint an independent Arbitrator under Section 11 (6) of the Act. In support of his submission, the... Petitioner

has relied upon the following judgments of this Court as well as the Supreme Court: I. Nandyal Coop. Spinning Mills Ltd. v. K.v. Mohan Rao (1993) 2 SCC654II. Nav Nirman Construction Company v. Executive Engineer CD-IX, Irrigation and Flood Control Department, GNCTD2011SCC Online Del 3948 III. Indian Oil Corporation Ltd. V. Raja Transport Private Ltd. (2009) 8 SCC520IV. M/s AnsalBuildwell Ltd. v. M/s Centre for Development of Telecom (Arb. Pet. No.318/2008) V. HCIL-Arsspl-Triveni(JV) v. Rites Ltd. (2009 SCC Online Del 2966) ARB.P. 180/2019 Page 3 of 18 VI. North Eastern Railways v. Tripple Engineering Works (AIR2014SC5306 5. The Respondent has not filed a reply and has instead filed brief note of submissions, which contains only legal objections/submissions. However, during the arguments, Ms. Akansha Kaul learned Counsel for the Respondent objected to the appointment of the Arbitrator on the ground that the Arbitration Clause does not survive any more. She highlights that the condition contained in the arbitration clause which stipulates that “no person other than a person appointed by VC/Administrative VC as aforesaid should act as arbitrator and if for any reason, that is not possible the matter is not to be referred to arbitration at all” and argues that the understanding between the parties is clear that an arbitrator can only be the person appointed by the Vice Chancellor, Delhi University and if for any reason that is not possible, the matter is not to be referred to Arbitration. Since the appointment has not been done by the Vice Chancellor of the Delhi University, irrespective of the reasons, the parties cannot be referred to Arbitration at all. Learned counsel for the Respondent additionally argued that in case the Court were to exercise the power under Section 11 (6) of the Act, the Court should at the first instance call upon the Respondent to make an appointment of the Arbitrator as per the said clause. In support of her argument, the learned counsel for the Respondent has relied upon the following judgments: I. Newton Engineering and Chemicals Ltd. v. Indian Oil Corporation Ltd. &Ors (2013) 4 SCC44ARB.P. 180/2019 Page 4 of 18 II. Oriental Insurance Company Ltd. v. M/s Narbheram Power and Steel Pvt. Ltd. (Civil Appeal No.2268/2018) judgment dated 2nd May 2018. III. Union of India v. Mohan Aggarwal Construction Co. (Civil Appeal No.1167 of 2015) order dated 22nd January 2015. IV. M/s AnsalBuildwell Ltd. v. M/s Centre for Development of Telecom (Arb. Pet. No.318/2008) V. HCIL-Arsspl-Triveni(JV) v. Rites Ltd. (2009 SCC Online Del 2966) VI. ACC Ltd. v. Global Cements Ltd. (2012) 7 SCC71VII. Union of India v. Parmar Construction Company (Civil Appeal No.3303/2019) judgment dated 29th March 2019. Analysis and Findings 6. The controversy in the present petition is centered around the wording of the Arbitration Clause. It would thus be apposite to first note the Arbitration Clause which reads as under:

"Settlement of Disputes & Arbitration CLAUSE25Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in before mentioned and as to the quality of workrnanship or materials used on the work or asto any other question, claim, right, matter or thing whatsoever in anyway arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, ARB.P. 180/2019 Page 5 of 18 other than completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by the V.C,D.U. in office, at the time or if there be no VC the administrative head of the Delhi University , at the time of such appointment that the arbitrator so appointment. It will be no objection toany such appointment that the arbitrator so appointed is a University servant,that he had to dial with the matters to which the contract relates and that in the course of his duties a University servant he had expressed views on all or any of the matters indispute of difference. The arbitrator to whom the matter is originally referred beingtransferred or vacating his office or being unable to act for any reason, such head as - aforesaid at the time of such transfer, vacation of officer or inability to act, shall appoint-another person to act as an arbitrator in accordance with the terms of thecontract. Such person shall bebe entitled to proceed with the reference from the stage at which it was left by his predecessor. It is also a terms of this contract that no a person by V.C./Administrative V.C as aforesaid should act as arbitrator and if for any reason that is not possible the matter is not to be referred to arbitration at all. In all case where the amount of the claim in dispute is Rs. 1,00,000.00 and above shall give the reasons for the award. It is a term of the contractor that party invoking the arbitration shall specify the dispute or disputes to be referred to arbitration under this clause together with theamounts claimed in respect of each such dispute. It also a term of this contract that no person other than a person appointed by Vice Chancellor, Delhi University or the administrative head of the Delhi University, as aforesaid should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all. xxx xxxxxx" appointed person ARB.P. 180/2019 Page 6 of 18 Maintainability of the Petition under Section 11(6) of the Act.

7. The existence of an arbitration agreement is not in dispute. The question before the court is whether the arbitration agreement survives or not and consequently whether the application under Section 11(6) of the Act is maintainable or not?. If the answer to the question is in the affirmative, what directions can be issued?. The arbitration clause inter alia provides that all questions in dispute relating to the conditions or otherwise concerning the works shall be referred to the sole arbitration of the person appointed by the VC, Delhi University. If there is no VC, the Administrative Head of the Delhi University would have the power to make the appointment. In that context, it is further provided that it is also the term of the Contract that no person other than the person appointed by the VC/Administrative VC should act as an Arbitrator and if for any reason that is not possible, the matter is not to be referred to Arbitration at all.

8. There cannot be any dispute that the parties to the Contract specifically agreed that no person other than one appointed by the Vice Chancellor of Delhi University could act as an Arbitrator.... Petitioner

has agreed to give the right of appointment to the Vice Chancellor of Delhi University and in his absence to the Administrative Head of the Delhi University. The Respondent relying on the aforesaid Clause, has taken a stance that the Arbitration Clause does not survive. It is not disputed that despite the invocation of the Arbitration, the Respondent has failed to exercise it’s right under the Contract. It is also not the case of the Respondent that the Arbitrator could not be appointed due to some specific reason. Respondent argues that since ARB.P. 180/2019 Page 7 of 18 the appointment has not been made, irrespective of the reason, the Arbitration Clause does not survive.

9. The stand of the Respondent is not only unreasonable but is contrary to the intention of the parties as it emerges from the reading of the Clause. The condition of the Clause which provides that no person other than the person appointed as Vice Chancellor, Delhi University should act as an Arbitrator only reinforces that the... Petitioner

agreed to give the Respondent the right to make an appointment. The stipulation that "if for any reason that is not possible, the matter shall not be referred to Arbitration at all" reaffirms that the parties agreed to go for arbitration under a person appointed by the Respondent. The arbitration clause here does not name an individual as an arbitrator. The appointment is by way of designation of the appointing authority. The Respondent had the opportunity to make an appointment and having willfully neglected and failed to do so, it cannot rely on its inaction to deprive the... Petitioner

to avail the remedy of alternative dispute resolution mechanism.

10. The Court cannot decipher the understanding between the parties in a manner the Respondent is canvassing. The arbitration clause has to be given a meaningful construction. The clause gives the Respondent a right to make an appointment but not to extinguish or abandon the clause all together. If the objection of the Respondent is sustained, it would mean that arbitration can be resorted to solely as per the choice of the Respondent. The Respondent has the right to appoint an Arbitrator but not an exclusive right to decide whether to arbitrate or not. Respondent’s interpretation of the ARB.P. 180/2019 Page 8 of 18 clause is not correct.Therefore, since the Respondent has failed to act as per the agreed procedure,... Petitioner

is well within it’s right to approach this court under Section 11 (6) (a) of the Act and the power of the court, in the facts of the present case, is not impinged.

11. The Court's power to appoint an Arbitrator under Section 11 (6) of the Act, has been subject matter of several decisions of this Court and the Supreme Court. In the case of Nandyal Coop. Spinning Mills Ltd (supra), relied upon by the... Petitioner

, a question arose with respect to the jurisdiction of the Court to make an appointment under Section 8 (1) (a) of the Arbitration Act,1940 in view of a para materia Arbitration Clause. This Court held that an aggrieved party has the right to file an application under Section 8 of the Arbitration Act,1940 Act, where the opposite party fails to appoint an Arbitrator(s) as per the terms of the Contract. The judgment of the Division Bench of this Court, in Nav Nirman Construction Company Ltd.(supra) also fortifies the aforementioned view. In the said case, the Single Judge while deciding objections to the award under section 34 of the Act arrived at a conclusion that in view of the arbitration clause [containing a para materia condition]. failure of the designated authority to appoint an arbitrator would give a go bye to arbitration. Over turning the said decision, the Division Bench held that the failure of the designate authority to appoint an arbitrator cannot be construed to denude the Chief Justice or his designate to appoint an Arbitrator. Respondent has placed reliance upon Newton Engineering and Chemical Ltd. (supra) wherein the arbitration clause inter alia provided that no person other than ED(NR) or the person designated by the ED (NR) should act as an arbitrator. The question arose that if the office ARB.P. 180/2019 Page 9 of 18 of ED (NR) ceased to exist in the Corporation and the parties were unable to reach at an agreed solution, whether the arbitration clause survives?. The Court while interpreting the clause, expressed the view that in such a situation, the Court has no power to appoint an arbitrator for resolution of the disputes. However, it is apposite to state that on a perusal of the judgment, one cannot conclude whether the arbitration clause had a similar condition to the effect that in a certain event, there would be, "no arbitration at all" and therefore the case is distinguishable on facts. The learned counsel for the Respondent has also placed reliance on a decision of the Supreme Court in the case of ACC Ltd. (supra). A perusal of the judgment elucidates the facts in the said case are distinct and distinguishable and therefore the Court is not persuaded to rely on the aforementioned case.

12. Thus, Respondent’s interpretation of the clause is not correct.Since the Respondent has failed to act as per the agreed procedure,... Petitioner

is well within it’s right to approach this court under section 11 (6) (a) of the Act and the power of the Court, in the facts of the present case has not been encroached. Whether an independent arbitrator can be appointed?.

13. The mainstay of the Respondent’s contention is that the procedure and mechanism provided under the Contract should be given effect to, as closely as possible. There is no quarrel on this proposition. The Supreme court in Datar Switchgears Ltd v.Tata Finance Ltd (2000) 8 SCC151;Union of India v. Bharat Battery Manufacturing Co.(P)Ltd. (2007) 7 SCC684and Punj Lloyd Ltd. v. Petronet MHB Ltd. (2006) 2 SCC638 while ARB.P. 180/2019 Page 10 of 18 discussing the Court's power to appoint an arbitrator under Section 11(6) of the Act, the Court deviated from the terms of the contract and appointed an independent arbitrator1.

14. At the same time it is also noteworthy that in a recent decision of Supreme Court in Union of India v. Parmar Construction Company (supra), while taking note of Northern Railway Administration, Ministry of Railway, New Delhi v. Patel Engineering Company Limited (2008) 10 SCC240and Union of India v. Singh Builders Syndicate has taken another approach. The Supreme Court in aforenoted cases has expressed the opinion that where an application under Section 11(6) of the Act is filed, the procedure for appointment of an arbitrator prescribed in the agreement, be given effect to and the Court ought not to appoint an independent arbitrator without resorting to the inbuilt mechanism as agreed between the parties.

15. There is no dispute that there is an unequivocal intention of the parties to go for arbitration for the adjudication of the disputes. The arbitration clause when read as a whole, emphasizes for an arbitration under a person appointed by the Respondent. If the court were to appoint an independent arbitrator in the present case, it would amount to rewriting the terms of the arbitration clause.The peculiar wording of the arbitration clause in the present case, prevails upon this court to follow the ratio of the judgment in Union of India v. Parmar Construction Company (supra).It is pertinent to 1 It is noted that the Arbitration Clause (s) in Datar Switchgears Ltd. (supra) and Punj. Lloyd Ltd. (supra) do not stipulate a condition similar to the one in the present case. However, in Bharat Battery Manufacturing Co. Ltd. (supra), though a similar condition in the Arbitration Clause exists, there has been no dispute with regard to the survivability of Arbitration. ARB.P. 180/2019 Page 11 of 18 note that the Court in the said case (supra), has noticed and discussed it’s earlier judgments of Datar Switchgears Ltd. (supra); Union of India v. Bharat Battery Manufacturing Co.(P)Ltd (supra) and Punj Lloyd Ltd.(supra) held that the Chief Justice or his Designate, in exercise of power under Section 11(6) of the Act cannot directly make an appointment of an independent arbitrator without, in the first instance, resorting to ensure that the remedies provided under the arbitration agreement are exhausted. The relevant paragraphs of the aforementioned judgment read as under: by the for learned counsel placed case (supra) 42. The judgments in Datar Switchgears Ltd. case (supra); Punj Lloyd and Union ofIndia v. Bharat Battery Manufacturing Co. (P) Ltd. case (supra) on which reliance has been the respondents/contractors may not be of assistance for the reason that the question for consideration before this Court was that if one party demands the opposite party to appoint an arbitrator and the other party fails to appoint an arbitrator within 30 days what will be its legal consequence and it was held in the cases (supra) that if one party demands the opposite party to appoint an arbitrator and if the opposite party has failed to make an appointment within 30 days, the right to make appointment is not forfeited but continues, but an appointment has to be made before the former makes an application under Section 11 seeking appointment of an arbitrator. In the instant cases, the question for consideration is as to whether the Chief Justice or his Designate in exercise of power under Section 11(6) of the Act should directly make an appointment of an independent arbitrator without, in the first instance, resorting to ensure that the remedies provided under the arbitration agreement are ARB.P. 180/2019 Page 12 of 18 clause 64(3)(a)(ii) the present batch of appeals, exhausted.

43. In independence and impartiality of the arbitrator has never been doubted but where the impartiality of the arbitrator in terms of the arbitration agreement is in doubt or where the Arbitral Tribunal appointed in terms of the arbitration agreement has not functioned, or has failed to conclude the proceedings or to pass an award without assigning any reason and it became necessary to make a fresh appointment, Chief Justice or his designate in the given circumstances after assigning cogent reasons in appropriate cases may resort to an alternative arrangement to give effect to the appointment of independent arbitrator under Section In North Eastern Railway v. Tripple 11(6) ofthe Act. Engineering Works (supra), though the panel ofarbitrators as per general conditions of contract under GCC was appointed in the year 1996 but for two decades, the arbitrator failed to pass the award and no explanation came forward. In the given situation, this Court observed that general conditions of the contract do not prescribe any specific qualification of the arbitrators to be appointed under the agreement except that they should be railway officers further held that even if the arbitration agreement was to specifically provide for any particular qualification(s) of an arbitrator the same would not denude the power of the Court acting under Section 11(6) to depart therefrom and accordingly, confirmed the appointment of an independent arbitrator appointed by in exercise of Section 11(6) of the Act, 1996. Almost the same situation was examined by this Court in Union of India v. Uttar Pradesh State Bridge Corporation Ltd. (supra) and after placing reliance on North Eastern Railway v. Tripple Engineering works (supra) held that since Arbitral Tribunal has failed to the High Court and (iii) of the ARB.P. 180/2019 Page 13 of 18 perform and to conclude the proceedings, appointed an independent arbitrator in exercise of power under Section 11(6) of the Act, 1996. In the given circumstances, it was the duty of the High Court to first resort to the mechanism in appointment of an arbitrator as per the terms of contract as agreed by the parties and the default procedure was opened to be resorted to if the arbitrator appointed in terms of the agreement failed to discharge its obligations or to arbitrate the dispute which was not the case set up by either of the parties.

44. To conclude, in our considered view, the High Court was not justified in appointing an independent arbitrator without resorting to the procedure for appointment of an arbitrator which has been prescribed under clause 64(3) of the contract under the inbuilt mechanism as agreed by the parties."

(emphasis supplied) 16. Pertinently, in Ansal Buildwell Limited case (supra), this court in a petition filed by the aggrieved party under Section 11(6) of the Act noticed the Arbitration clause containing a similar condition upheld the right of the Respondent to appoint the arbitrator and declined to appoint an independent Arbitrator holding as under:-

""4. Learned counsel for the petitioner relied upon the text of Section 11 and a decision of the Bombay High Court in Satya Kailash chandraSahuvs. M/s.Vidarbha Distillers, Nagpur, AIR1998BOMBAY210 It was argued that when an arbitration agreement provides for appointment of a named person or persons as Arbitrator and when they refuse to act, the procedure required to be follows is as provided in Section 11. It was argued ARB.P. 180/2019 Page 14 of 18 analogically, where the process containing the Agreement, envisions appointment by one of the parties and also provides for contingency, a similar inference has to be drawn, that upon the happening of that contingency, the power to appoint an Arbitrator stands exhausted.

5. The Court is un-persuaded by the submission of the petitioner.The Arbitration Agreement, i.e. clause 67.1 is no doubt unusually worded. That does not detract from its real effect. The contracting parties categorically agreed that no person other than one appointed by the Executive Director, C-DOT, could act as Arbitrator and that if for any reason that was not possible, there could not be any reference for arbitration at all. In essence what the condition says is that the foundation of the Arbitration Agreement itself is appointment by the Executive Director, in the manner contemplated. If this condition which is fundamental to the Arbitration Agreement itself, were to be seen with the preceding terms, it would be apparent that the C-DOT, (subject to other provisions of law such as Section 11, i.e. fixing time limits etc., as interpreted by the Supreme Court in Datar Switch Gear vs. Tata Finance Ltd., 2002 (8) SCC151, retained the right to appoint Arbitrator at all times. This condition is unlike the one which the Bombay High Court had occasioned to deal with in Satya Kailashchadra?.s case (supra).

7. From the above discussion, it is apparent that the right of the C-DOT to appoint an Arbitrator in the manner contemplated in Clause 67.1.4 did not get exhausted upon the named Arbitrator refusing to act further. Mr. J.C.Seth, learned Counsel appearing for C-DOT, submits that by an office order dated 26.8.2008, Mr. P.S. Saran (Retd.), Secretary, Department of Telecom Services, and Member (Services) Telecom Commission, has ARB.P. 180/2019 Page 15 of 18 been since appointed as Arbitrator."

(emphasis supplied) 17. The decision of this Court in HCIL- Arsspl-Triveni (JV)(supra) is also relevant. The Court was dealing with a similar clause, has followed Ansal Buildwell Limited (supra) and directed the Respondent to make an appointment of the arbitrator and did not appoint an independent arbitrator.

18. In this regard another significant decision of a coordinate Bench of this Court in the case of Ess Ess Constructions v. Union of India [Arb. P8012016]. decided on 2nd February, 2017 requires to be mentioned. The court while deciding the petition for appointment of an independent arbitrator on the basis of a clause containing a similar condition first made an attempt to appoint an arbitrator as per the terms of the contract2. The relevant paragraphs of the judgment read as under:-

""9. xxx xxxxxx CLAUSE25It is also a term of this contract that no person, other than a person appointed by such Chief Engineer CPWD or Additional Director General or Director General of works, CPWD, as aforesaid, should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all.....

13. In Nandyal Coop. Spinning Mills Limited v. K.V. Mohan Rao (supra), the Supreme Court interpreted the above clause as permitting the contractor to approach the Court for the appointment 2In the said case, this Court has also distinguished the decision of Mohan Aggarwal Construction Company (supra) i.e. the judgment relied upon by the Respondent on the ground that the earlier decision of a Bench of same strength in Nandyal Coop. Spinning Mills Ltd (supra) was not brought to the notice of the Supreme Court while deciding Mohan Aggarwal Construction (supra). ARB.P. 180/2019 Page 16 of 18 of an Arbitrator in the event of the Respondent declining to appoint an Arbitrator. The specific contention of the Appellant in that case was that if the administrative head of the Appellant rejected the prayer to appoint an Arbitrator, "the only remedy open to the contractor was to have recourse to civil court" was "without force". In the present case, the Clause itself envisages that the arbitration will be conducted in accordance with the provisions of the Act as amended from time to time. 14.It may also be noticed that the attention of the Supreme Court in Union of India v. Mohan Aggarwal Construction Co. (supra) does not appear to have drawn to theafore mentioned earlier judgment in Nandyal Coop. Spinning Mills Limited v. K.V.Mohan Rao (supra) which has interpreted the identical clause.

15. In the present case, it might still have been possible for the Chief Engineer to be asked to appoint an Arbitrator. However, learned counsel for the Respondent states that it is practically impossible for the Chief Engineer to now appoint an Arbitrator as such person would not be qualified in terms of the Act as amended from 23rd October, 2015. The clause in the present case envisages the applicability of the Act "or any statutory modification or re-enactment learned counsel for the Respondent was right in contending that under the amended Act it is not possible for the Respondent to appoint an Arbitrator. When asked whether the Chief Engineer could appoint an independent person who may not be disqualified to act as an arbitrator, learned counsel for the Respondent answered in the in the negative stating that the Chief Engineer would not be permitted to appoint a person other than an employee of the government itself."

thereof."

Therefore, (emphasis supplied) 19. In Raja Transport Private Ltd.(supra) and Oriental Insurance Company Ltd. (supra) as well, the Court has held that endeavour shall be ARB.P. 180/2019 Page 17 of 18 made to give effect to the appointment procedure prescribed in the arbitration clause.

20. Before parting, it is also apposite to note that bare perusal of the scheme of Section 11 of the Act shows that the emphasis is on the terms of the agreement being adhered to and/or given effect as closely as possible. In other words, the Court must ensure that the remedies provided for are exhausted.

21. Having regard to the intention of the parties and the wordings of the Arbitration clause which provides that the foundation of the Arbitration is by way of appointment by the Respondent, the court directs the Respondent to appoint an arbitrator in terms of Clause 25 of the Contract within four weeks from today. Respondent while making an appointment is to take into consideration the mandate of Section 12(5) and Schedule VII of the Act as amended by Arbitration and Conciliation (Amendment) Act, 2015.

22. Petition is allowed in above terms. APRIL25 2019 nk SANJEEV NARULA, J ARB.P. 180/2019 Page 18 of 18


Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //