Section Text
1[183B. Completing notice
Every person to whom sanction for the erection or re-erection of any building in any area in a cantonment has been given or deemed to have been given under section 181 by the Board or the Executive Officer, as the case may be, shall, within thirty days after completion of the erection or re-erection of the building give a notice of completion in writing to the Board or the Executive Officer, as the case may be, and the Board or the Executive Officer shall on receipt of such notice cause the building to be inspected in order to ensure that the building has been completed in accordance with the sanction given by the Board of the Executive Officer, as the case may be.]
________________________
1. Inserted by Act 15 of 1983, section 106 w.e.f. 1-10-1983.