Karnataka Power Transmission Corporation Limited Vs. R.K. Powergen Private Limited
Decided On : Aug-26-2005
Court : Karnataka
LAW: Section 25, Article 2 of PPA, Article 2.2, the Electricity Act, Section 111 of Electricity Act, the Electricity Act 2003, Section 111 of the Act, Article 226, Article 226, Article 226, Article 226 of the Constitution, Article 227 of the Constitution, Article 226 of the Constitution, Article 226, Section 111 of the Electricity Act, Section 112, Constitution, Section 17, Section 111 of the Act, Constitution, Section 111(2, Section 111
PERSON: J. Gunjal, J.1, Nagananda, Uday Holla, Karamchari Sangh, Chairperson, Nagananda, Chintamanarao Madha, Anr
CARDINAL: 226, 227, 3/05, 7.4.2005, 3/2005, 8.10.2001, 20, 12.10.2001, 3.1.2003, 3/05, 5.7.2003, 5.7.2003, 35,79,439/-, 12, 226, 227, 227, 226, 2004)IILLJ9SC, 1985ECR4(SC, 2003]1SCR567, 721, 227, three, 227, 2
GPE: India, O.P., O.P., O.P., India, India, Chandannagar, West Bengal
ORG: the Karnataka Electricity Regulatory Commission, the Karnataka Electricity Regulatory Commission, Annexure-N, Hon'ble Court, MW, the Karnataka Electricity Regulatory Commission, Court, Court, Commission, Commission, Commission, inter alia, Commission, Commission, Commission, Annexure-N, Commission, the Appellate Authority, this Hon'ble Court, Commission, Ministry of Power, the Appellate Tribunal, Learned Senior Counsel, Court, the Appellate Tribunal, Appellate Tribunal, Learned Senior Counsel, the Apex Court, West Bengal Electricity Regulatory Commission, Cesc Ltd., the Apex Court, The Apex Court, U.P. State Corporation Ltd., U.P. Rajya Setunigams, the Apex Court, the High Court, Dunlop India Ltd., the Apex Court, Court, Sadhana Lodh v. National Insurance Co; Ltd., the Apex Court, the High Court, the High Courts, Court, the Appellate Tribunal, the Appellate Tribunal, Appellate Tribunal, Appellate Tribunal, Tribunal, Commission, Commission, Division Bench, L.J. Suppl, Court, Tribunal, Tribunal, Tribunal, the High Court, Commission, Commission, Commission, Commission, Court, Tribunal, The Apex Court, W.B. Electricity Regulatory Commission, Cesc Ltd., follows:'The Commission, Commission, The Central Electricity Regulatory Commission, the High Court, the Supreme Court, the State Commission, the Central Electricity Regulatory Commission, Appellate Tribunal, the Appellate Tribunal, Court, Appellate Tribunal, the Writ Petition, Tribunal, the Appellate Tribunal, Tribunal, Court, the Appellate Tribunal, Court, Tribunal, the Tribunal.
DATE: 1999, 12 months, 18.10.2001, one and half years, 2003, 10.6.2003, 18.10.2001, a period of, 30 days, 2003, '11, 2003, 1964, 13.5.2005, 45 days, 45 days
ORDINAL: first, second, first
LOC: Govt
PRODUCT: Articles 226, Articles 226, Articles 226
WORK_OF_ART: Collector of Central Excise