Bihar Electricity Board and ors. Vs. Usha MartIn Industries Ltd.

Decided On : Jul-28-1997

Court : Patna

LAW: the Companies Act, Section 26, the Electricity Act, Section 26, Section 26, the Indian Electricity Act, Article 55 of the Limitation Act, Section 26 of the Act, Section 26 of the Act, Section 26, the Indian Electricity Act

PERSON: Nagendra Rai, Counsel, Counsel, Bill, Bill, Jeevan Reddy

NORP: J.1

GPE: C.W.J.C., 31.12.1990, Gamharia, the State of Bihar, F.I.R., C.T., C.T., C.T.

ORG: Court, a Public Limited Company, Usha Alloys and Steel Division, MVA, the Electricity Board, the Electricity (Supply) Act, Board, Board, the Electrical Inspector, Board, Arc Furnace, Structure and Consumers, the Vigilance Department, MVA, Electric Arc Furnace, Furnace, Electric Arc Furnace, Energy Conservation Report, Board, Board, Board, Clauses, Clauses 6, Court, Board, Board, Board, Board, consumer.10, Board, Board, Board, Board, Energy Conservation Report, Board, Board of Arbitrators, the Supreme Court, Arbitrators, the Board of Arbitrators, the Board of Arbitrators, the Board of Arbitrators--(i, National PhysicalLaboratory, the Department of Metallurgical Engineering, I.I.T., Clauses 6, the Board of Arbitrators, The Board of Arbitrators, the Board of Arbitrators, the Board of Arbitrators, the Board of Arbitrators

CARDINAL: 4.4.1996, 683, 19.5, 33, 49, 1, 19.5, 33, about 3.50, 400/5, as high as, 334, 13.4.1974, 4.4.1996, 6, 9, M.T., three, two

DATE: 42, 34, 17.4.1974.3, 1948, February, 1996, six months, the year 1974, the year 1989, 1990, 7.1.1991, 1991-92 to 1994-95, follows--'6, 1963, 1963, 1919-91 to 1994-95, a period of, six months, monthly

ORDINAL: first

PERCENT: 180%

LOC: Single, Single Judge, Single, Single Judge