M/S. Ancl and Co. (India) Pvt. Ltd. Vs. Corporation Bank and Others

Decided On : Jan-17-2013

Court : Mumbai

LAW: the Indian Contract Act, Section 32, Section 31, Section 32, Section 31, the Contract Act, Section 32, the Contract Act, the Condition No, section 9

DATE: 1996, 2012, September, 2011, 23rd September, 2011, 24th October, 2011, the month of June, 2012, 23rd September, 2011, October, 2011, 25th June, 2012, 24th June, 2012, 24th June, 2012, 25th June, 2012, 24th June, 2012, 25th June, 2012, 30th July, 2012, the 2nd, 2nd January, 2013, 24th June, 2012, 25th June, 2012, August, 2012, August, 2012, 29th August, 2012, 30th October, 2012, 11th October, 2012, 27th October, 2012, November, 2012, November, 2012, 31st October, 2012, 1st November, 2012, 3rd November, 2012, 2nd November, 2012, 6th November, 2012, 22nd November, 2012, 2012, 24th November, 2012, 22nd November, 2012, 28th November, 2012, 21, 28th November, 2012, 28th November, 2012, 28th November, 2012, November, 2012, November, 2012, the same day, 7,35,67,910/-, 10th January, 2013, 11th October, 2012, 15th November, 2012, 22nd October, 2012, law.” 31, 5, Seventy Two, 48, Seventy two, 19 May, 1990, one month, 30 days, 30 days, 45 days, 75 days, 15th January, 1994, 10th June, 1994, 10.6.1994, 10th of May, 1989, 10.5.1985, 32, 21, 22, 23, 24, 31, 33, 1872, 31, 08/2007-2008, the date and, year, 17.2.2011, 19.02.2008, 19.02.2008, five months, 15th July, 2012, 1st November, 2012, 35, 2, 3, 5, 10th January, 2013, 10 2013, M-3, 37, 1996, 38, 3) days, 6) months, monthly, 6 months, 6) months, 42, 2006, 15, 16, 21

CARDINAL: 2 to 4, 2012/247 to, 2012/255, 2, 3, 19,32,86,971.85, 4, Rs.1,04,62,151/-, 2,53,07,000/-, 10,46,817/-, 5., 6, 11,77,75,049.30, 8, nine, 9, 10, 1, 11, 12, 13, 14., 15, 16, 17, 18, 19, 20, 22, 23, 24, 25, six, six, five, one, 6, two, one, three, 26, 27, three, 28, 29, 30, 22, 26, 28, more than one, 26, one, 27, 28, 10 and 11, 3, 2.72, 122, 126, 124 and 125, 2, Two, Thirty Nine thousand, 1, 2,72,39,850/-, Two, 2, 11, 46, 108, 70.1, 70.2, 70.3, 70.4.01, 92 to 95, 70.1, 70.2, 100, 70.3, 10.6.1994, 2, 70.2, 70.3, 70.4, 21.2.1994, 70.3, 70.4, 122, 126, 2.72, 1, 4, 1, 4, 20, 21, 100, 1, 1, 3, 4, 5., 1, 2, 1, 2, two, 1, 22, 2, 1, 1 Company, 1., 1, 23, 2, 69.79.000/-, 69,79,000/-, 1,54,94,580/-, 19.11.2011, 2,24,73,580/-, 1, 1, 1, 2, 1, 24, 2, 1 Company, 2, 1 Company, 2, 1, 31, 1, 1, 2, 1, 1, 33, 2 to 4, 34, 1, 2, 3, 8, 8, one, Twenty, 2, 3, 5., 8, 36, 4, 2012/247 to, 2012/252, One, 27, 28, 28.3, 39, 19, three, six, six, 40, 41, 43, 2, 9, 26, 29, 9

FAC: 3rd September, Clauses 7therein

PERSON: Nos, Exs, Arun Aggarwal, Grover, Soni, Kamdar, Kamdar, Mula Sahakari Sakhar, Appellant, Naphade, Kamdar, Thirtynine, Contractor, Certain Points, Rajesh Nandlal Biyani, Nagpur, Shree Ram Market, Demand Draft, J.P. Pendse, Nos, Sathe, Contract, Contractor, Contract, Surety, Yours Sincerely, Sathe, Contractor, Rohtagi

ORG: the Letter of Intent, no.2, the Letter of Intent, no.2, RCC, no.2, the Corporation Bank, RCC, the Supreme Court, State Bank of India, AIR 2007, Pentagon, Tourbo Limited, Maharashtra State Electricity Board, AIR 1996, SC, Bank Guarantee, the Citi Bank, Guarantee, CITI BANK N.A., Bank, Bank, Board, Bank, Board, the Maharashtra State Electricity Board, Bank, Board, Performance Guarantee, the Coal Handling Plant, C.H.P., Bank Guarantees, Clauses 7, Clauses 770.2, Plant, Guarantee, the Citi Bank, Guarantee, the Citi Bank, Court, Bank Guarantee, Western Coalfields Limited, MLJ, Bank, Bank, Bank, Bank, Bank, Proforma of Bank, M/s. Western Coalfields Limited, Coal Estate, Civil Lines, M/s. Western Coalfields Limited, Registered Office at Nagpur, Schedule/Nationalized Bank, Nagpur, Bank, Registered Office, Bank, Guarantee, Bank, Bank, Bank, Bank, Guarantee, M/s. Western Coalfields Limited, the Bank (Oriental Bank of Commerce, Bank, Bank, the Company (M/s. Western Coalfields Limited, Bank, Bank, Bank, Clause 5, Bank, Bank, Bank, Bank, Bank, The Oriental Bank of Commerce, Kasturba Chowk, BG No, M/s. Western Coalfields Limited, Nagpur, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, Bank, The Trial Court, the State Government, The Trial Court, Bank, Trial, Clauses 1, Surety, Company, Company, Company, Guarantee, Company, Court, Tribunal, Surety, Surety, Company, Guarantee, Company, Contractors, Suretys, Company, Guarantee, Surety, Guarantee, Company, Corporation Bank, M/s.ANCL, CO (India) Pvt. Ltd, Bank Guarantees, Bank Guarantee No, the Bank Guarantee, Bank Ltd., Reliance Eminent Trading and, the Arbitration and Conciliation Act, Owner, Owner, Owner, the Total Contract Value, Contractors, Retention Money, RA, RA, the Bank Guarantee, the Defects Liability Period, Contractors, Owner, Security Deposit, Contractor if Contractor, Contract, Contract, the Supreme Court, BSES Ltd., Fenner India Ltd., Court, U.P. Cooperative Federation Ltd., MANU, Singh Consultants and Engineers, U.P. Co-operative, Federation

ORDINAL: 5th, 4th, 2nd, 2nd, 2nd, 3rd, 24th, 3rd, 2nd, 3rd, 9th, 24th, 2nd, 3rd, 2nd, 3rd, 3rd, 2nd, 2nd, 2nd, 2nd, 2nd, 2nd, 7th, 26th, 3rd, 3rd, 3rd, 3rd, first, first, first, first, first, first, first, third

GPE: no.4, no.4, Bhilwara, no.3, no.3, no.3, no.3, Larsen, N.A., Bombay, MSEB, DD, Companys, Companys, Greater Kailash, Part–2, New Delhi, Mumbai, Fort, Mumbai

TIME: minutes, minutes, minutes, 100 hours, 20 hours, 2 hours, 1988]1SCR1124

PRODUCT: Rs.10,04,817/-, 2M Part-A, Contingent

EVENT: SC 2361, Volume II, Volume II

WORK_OF_ART: Taking Over Certificate, Contract Agreement Vol, The Company, the Contractor, Sixty Six Lacs Seventy Five Thousand

LOC: Surety, Surety, Surety

NORP: no.3

PERCENT: less than 5%, 5%