Reliance Communication Ltd., Mumbai Vs. Bharat Sanchar Nigam Ltd., New Delhi - Court Judgment |
| Telecom Disputes Settlement and Appellate Tribunal TDSAT |
| Feb-11-2011 |
| Petition No.96 OF 2011 |
| S.B. SINHA, CHAIRPERSON, THE HONOURABLE MR. G.D. GAIHA, MEMBER & THE HONOURABLE MR. P.K. RASTOGI, MEMBER |
| Reliance Communication Ltd., Mumbai |
| Bharat Sanchar Nigam Ltd., New Delhi |
| For Petitioner: Mr.C.S. Vaidyanathan, Sr. Advocate with Ms. Manali Singhal and Mr. Santosh Sachin, Advocates. For Respondent: Ms.Pratibha M. Singh, Mr.Tejveer Singh Bhatia, Advocates. |
p.k. rastogi we have passed interim orders in petitions no.86/2011, 87/2011 and 92/2011. for the reasons stated therein, herein also we direct that the petitioner shall deposit the principal amount and 50% of the amount of interest calculated in terms of the agreement entered into by and between the parties. the said amount should be deposited with the respondent within one week from date. subject to the aforementioned, the respondent shall not disconnect the bpo/pois of the petitioner.
P.K. RASTOGI
We have passed interim orders in Petitions No.86/2011, 87/2011 and 92/2011.
For the reasons stated therein, herein also we direct that the petitioner shall deposit the principal amount and 50% of the amount of interest calculated in terms of the agreement entered into by and between the parties. The said amount should be deposited with the respondent within one week from date.
Subject to the aforementioned, the respondent shall not disconnect the BPO/POIs of the petitioner.