Skip to content


State of M.P. and anr. Vs. K.K. Shukla and Co. - Court Judgment

SooperKanoon Citation
SubjectArbitration
CourtSupreme Court of India
Decided On
Case NumberCivil Appeal No. 9429 of 1996
Judge
Reported in(2001)10SCC194
ActsM.P. Madhyastham Adhikaran Adhiniyam, 1983 - Sections 7, 19
AppellantState of M.P. and anr.
RespondentK.K. Shukla and Co.
Excerpt:
.....such as questions relating to specifications, designs, quality of workmanship or materials or other claim or matter relating to the contract, designs or drawings etc., held, cannot be stretched so as to elevate it to the level of an arbitration clause -- if any party is not satisfied with the decision of the superintending engineer, it may make a reference to the chief engineer within 30 days from the date of communication of the decision of the superintending engineer and the chief engineer will give his decision after hearing the parties which shall be final, conclusive and binding on the parties. these clauses are sought to be interpreted as clauses for arbitration. neither the superintending engineer nor the chief engineer can be characterised as discharging the functions of an..........of the contract the respondent had invoked the jurisdiction of the superintending engineer and the chief engineer and when their decision went against it, sought to avail of the remedy under provisions of section 7 of the act; that, it is not open to the party having acquiesced in the arbitration proceedings under the contract to seek for second reference for arbitration.3. the superintending engineer under clause 29(2) is empowered to decide all questions relating to the meaning of the specifications, designs, drawings and constructions mentioned in the contract and as to the quality of workmanship or materials used in the work or as to any other question, claim, right, matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specification.....
Judgment:

S. Rajendra Babu and; S.N. Variava, JJ.

1. Disputes having arisen between the appellants and the respondent, a reference was made to arbitration under Section 7 of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (hereinafter referred to as “the Act”). Before the Tribunal, it was contended that having availed of arbitration under clause 29 of the contract it was not open to invoke Section 7 of the Act. This contention was rejected. A revision petition was filed under Section 19 of the Act in the Madhya Pradesh High Court. The High Court upheld the view of the Arbitral Tribunal. Hence this appeal by special leave. In this appeal the limited question raised for consideration is as to the scope of clause 29(2) of the contract between the parties under which the respondent executed certain works and effect of Section 7 of the Act upon the same.

2. The contention put forth before us is that in terms of clause 29 of the contract the respondent had invoked the jurisdiction of the Superintending Engineer and the Chief Engineer and when their decision went against it, sought to avail of the remedy under provisions of Section 7 of the Act; that, it is not open to the party having acquiesced in the arbitration proceedings under the contract to seek for second reference for arbitration.

3. The Superintending Engineer under clause 29(2) is empowered to decide all questions relating to the meaning of the specifications, designs, drawings and constructions mentioned in the contract and as to the quality of workmanship or materials used in the work or as to any other question, claim, right, matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specification estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work or after the completion of abandonment and the Superintending Engineer will have to give his decision after giving an opportunity to the party to the contract. If any party is not satisfied with the decision of the Superintending Engineer, it may make a reference to the Chief Engineer within 30 days from the date of communication of the decision of the Superintending Engineer and the Chief Engineer will give his decision after hearing the parties which shall be final, conclusive and binding on the parties.

4. These clauses are sought to be interpreted as clauses for arbitration. We fail to understand as to how these clauses can be understood to be one referring the matter to arbitration at all. So far as the Superintending Engineer is concerned, he has to decide certain questions which we have adverted to and upon his decision the matter is referred to the Chief Engineer for further decision. These two provisions made in the contract are only to make a fair provision in the contract to settle any of the claims that may arise in the course of execution of contracts and the matter cannot be stretched so as to elevate to the level of an arbitration clause. Neither the Superintending Engineer nor the Chief Engineer can be characterised as discharging the functions of an arbitrator. In that view of the matter, we do not think the contention put forth on behalf of the appellant that the respondent having availed of the arbitration as provided under clause 29 is trying to seek another remedy as provided under Section 7 of the Act is tenable. In the circumstances, the effect of Section 7 upon clause 29 does not arise for consideration at all. In that view of the matter, no interference is called for with the order under appeal. This appeal is therefore dismissed.


Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //