Skip to content


Badarpur thermal Power Station Vs. Delhi Transco Limited - Court Judgment

SooperKanoon Citation
CourtCentral Electricity Regulatory Commission CERC
Decided On
Judge
Reported in(2007)LCCERC1259
AppellantBadarpur thermal Power Station
RespondentDelhi Transco Limited
Excerpt:
.....on the order dated, 9th may, 2006, limited to the aspect of payment of incentive, that is, whether incentive is payable based on target plf of 80 per cent or 75 per cent.2. we have heard the representatives of the parties present at the hearing.3. the commission by its order dated, 9th may, 2006 had approved tariff for badarpur thermal power station (hereinafter referred to as "the generating station") for the period 1st april, 2004 to 31st march, 2009. the commission, inter alia, decided as under: on consideration of the analysis of the situation.... target availability/plf at 75 per cent has been considered for recovery of full fixed charges and computation of fuel element in the working capital for the period from 1st april, 2004 to 31st march, 2009. 70. in addition to the charges.....
Judgment:
1. The application is made for clarification on the Order dated, 9th May, 2006, limited to the aspect of payment of incentive, that is, whether incentive is payable based on target PLF of 80 per cent or 75 per cent.

2. We have heard the representatives of the parties present at the hearing.

3. The Commission by its order dated, 9th May, 2006 had approved Tariff for Badarpur Thermal Power Station (hereinafter referred to as "the generating station") for the period 1st April, 2004 to 31st March, 2009. The Commission, inter alia, decided as under: On consideration of the analysis of the situation.... Target Availability/PLF at 75 per cent has been considered for recovery of full fixed charges and computation of fuel element in the working capital for the period from 1st April, 2004 to 31st March, 2009.

70. In addition to the charges approved above, the Petitioner is entitled to recover other charges also like incentive, claim for reimbursement of income tax, other taxes, cess levied by a Statutory Authority, and other charges in accordance with the Regulations 2004, as applicable 5. The Applicant has pointed out that in terms of Clause (ii) of Regulation 16 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff), 2004, Regulations (hereinafter referred to as "the 2004 regulations"), incentive is payable on attaining PLF of 80 per cent. The representative of the Applicant pointed out that by reason of the Order dated, 9th May, 2006, target availability/PLF of 75 per cent have been considered for recovery of full fixed charges and computation of fuel element of the working capital and the Order does not speak of payment of incentive. It has also been urged that in view of para 70 of the Order dated, 9th May, 2006 reproduced above, the Applicant is liable to pay incentive based on target PLF of 80 per cent as stipulated in Clause (ii) of Regulation 16 of the 2004 regulations.

It has been stated that the Petitioner (NTPC) has claimed incentive on PLF exceeding 75 per cent. The Applicant is said to have released the full amount claimed by NTPC, reserving its right to approach the Commission for a clarification. Accordingly, the present application has been made.

6. We have very carefully considered the issue raised by the Applicant.

For proper appreciation of the matter, we consider it appropriate to extract the relevant provisions of the 2004 regulations, which regulate determination of Tariff for the period 2004-09.

2. Scope and extent of application: (1) Where Tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government, the Commission shall adopt such Tariff in accordance with the provisions of the Act.

(2) These regulations shall apply in all other cases where Tariff is to be determined by the Commission based on capital cost.

Provided that the Commission may prescribe the relaxed norms of operation, including the norms of target availability and Plant Load Factor contained in these regulations for a generating station the Tariff which is not determined in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2001, and the relaxed norms shall be applicable for determination of Tariff for such a generating station.

16. Norms of Operation: The norms of operation as given hereunder shall apply: (i) Target Availability for recovery of full Capacity (Fixed) charges (a) All thermal power generating stations, except those covered under Clauses (b) and (c) below - 80 per cent (b) Thermal power generating stations of Neyveli Lignite Corporation Ltd (TPS-I, TPSII, Stage I&II and TPS-I Expansion) and Talchar Thermal Power Station of National Thermal Power Corporation Ltd. - 75 per cent (c) Tanda Thermal Power Station of National Thermal Power Corporation Ltd. -60 per cent Note: Recovery of capacity (fixed) charges below the level of target availability shall be on pro rata basis. At zero availability, no capacity charges shall be payable.

(a) All thermal power generating stations, except those covered under Clauses (b) and (c) below - 80 per cent (b) Thermal power generating stations of Neyveli Lignite Corporation Ltd (TPS-I, TPSII, Stage I&II and TPS I Expansion) and Talcher Thermal Power Station of National Thermal Power Corporation Ltd. - 75 per cent (c) Tanda Thermal Power Station of National Thermal Power Corporation Ltd. - 60 per cent 23. Incentive: Incentive shall be payable at a flat rate of 25.0 paise/kWh for exbus scheduled energy corresponding to scheduled generation in excess of exbus energy corresponding to target Plant Load Factor.

7. As may be noted from the proviso under Regulation 2 of the 2004 regulations reproduced above, the Commission is empowered to prescribe the relaxed norms of operation including the norms of target availability and PLF for the generating stations whose Tariff was not determined in accordance with the Central Electricity Regulatory Commission (Terms & Conditions of Tariff) Regulations, 2001 (the 2001 regulations) and the relaxed norms as may be prescribed by the Commission are applicable for determination of Tariff. In case of the generating station the Tariff for the period prior to 1st April, 2004 was not determined in accordance with the 2001 regulations. Therefore, by virtue of power under Regulation 2 of the 2004 regulations, the Commission by its order dated, 9th May, 2006 prescribed the relaxed norms of target availability and PLF considering the peculiar facts applicable to the generating station. The Commission prescribed target availability and PLF of 75 per cent.

8. Historically, target availability and target PLF have been considered two different concepts, the former is related to recovery of fixed charges whereas payment of incentive is linked to the latter. In the Order dated, 9th May, 2006 the Commission has prescribed the threshold limits for these two purposes, which are same. Under Clause (i) of Regulation 16, target availability for recovery of fixed charges has been specified and under Clause (ii) thereof target PLF is laid down, but the levels fixed under both these Clauses are the same. It necessarily follows that in case of the generating station incentive will be recoverable at PLF exceeding 75 per cent, as the Commission in the Order dated, 9th May, 2006 has decided to fix target PLF of 75 per cent. Regulation 23 of the 2004 regulations lays down that incentive is payable at flat rate of 25 paise per kWh for exbus scheduled energy corresponding to scheduled generation in excess of ex-bus energy corresponding to target PLF. Para 70 of the Order dated, 9th May, 2006 reproduced above is to be read, inter alia, in the context of Regulation 23. As the Commission in Para 35 of its order dated, 9th May, 2006, extract placed at para 3 above, has specifically decided the target PLF of 75 per cent, Clause (ii) of Regulation 16 of the 2004 regulations, which is a general provision, has no application to the generating station. For this purpose, the two paras of the Order dated, 9th May, 2006 (Paras 35 and 70) are to be read together.

9. We, therefore, clarify that threshold PLF level for recovery of incentive in the present case is 75 per cent and NTPC is entitled to recover incentive at the flat rate of 25 paise/kWh for ex-bus scheduled energy corresponding to scheduled generation in excess of ex-bus energy corresponding to 75 per cent PLF.


Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //