Muhammad Habib-ullah Vs. Bird and Company - Court Judgment

SooperKanoon Citation
SubjectContract
CourtAllahabad
Decided On
Judge
Reported in(1921)ILR43All257
AppellantMuhammad Habib-ullah
RespondentBird and Company
Excerpt:
.....goods - failure to deliver at agreed time--extension of time--failure to deliver within extended time--damages--loss of profit--indian contract act (ix of 1872), sections 55, 63. - cantonments act[c.a. no. 41/2006]. section 346 & cantonment fund (servants rules, 1937, rules 13, 14 & 15: [h.l. gokhale, ag. cj, p.v. hardas, naresh h. patil, r.m. borde & r.m. savant, jj] jurisdiction of school tribunal constituted under maharashtra employees of private schools (conditions of service) regulations act, (3 of 1978) held, school run by the cantonment board is a primary school and it is not a school recognised by any such board comparable to the divisional board or the state board. the school tribunal constituted under section 8 of the maharashtra act cannot entertain appeals filed under..........of may, and had in response to application to that effect by the appellant's agent, allowed the time of delivery to be prorogued until the 30th of november; that non-delivery having been then made the appellant was in breach; that, although the liquidated damages condition could no longer apply, the respondents were entitled to damages for the non-delivered portion on the calculation of the profit which they would have made comparing the price under the principal contract with the railway company with the price they had to pay under the contract with the appellant. they accordingly dismissed the appellant's claim for damages, and gave him a decree for the deposit under deduction of the damages due to the respondents as above calculated.3. the view of the evidence which commended.....
Judgment:

Dunedin, J.

1. The present appeal arises out of a contract made between the appellant and the respondents by which the appellant was to supply 4,000 sleepers of a special pattern at any station on the Bengal-Nagpur Railway by the 31st of May, 1913. As a condition of the contract, the appellant had to deposit and did deposit Rs. 5,000 with the respondents as security for liquidated damages at a certain rate per foot for all sleepers not delivered on the said 31st of May. The sleepers had to pass inspection. Only 1,746 sleepers were delivered and passed inspection. The time for delivery was extended, but no more deliveries were made and the parties in December, 1913, broke off negotiations. The appellant then raised action asking for (1) the return of the deposit; and (2) damages in respect of his profit on the balance of sleepers not supplied. The respondents counter-claimed for damages in respect of sleepers not delivered.

2. The Subordinate Judge held that time was of the essence of the contract as originally made, but that the respondents had by delaying inspection not given the appellant proper opportunity of supplying the whole of the sleepers by the 31st of May; that thereafter both parties were willing and anxious that the contract should go on, time being, he held, under these circumstances no longer of the essence. He further held that when in the month of December the respondents alleged non-performance, and maintained that they would claim the penalty, that was equivalent to putting an end to the contract on their part, and he gave judgment for a return of the deposit and for damages calculated on the profit which would have accrued in respect of the unsupplied balance. On appeal, this judgment was reversed. The High Court, agreeing with the Subordinate Judge that time was of the essence of the contract as originally made, held that the fault in non-delivery by that date lay with the appellant, who never had 4,000 sleepers ready for delivery by that time, and could not excuse himself because at one particular station of the railway there was no room to lay out 4,00 0 sleepers at one time. They held that the respondents had excused non-delivery at the 31st of May, and had in response to application to that effect by the appellant's agent, allowed the time of delivery to be prorogued until the 30th of November; that non-delivery having been then made the appellant was in breach; that, although the liquidated damages condition could no longer apply, the respondents were entitled to damages for the non-delivered portion on the calculation of the profit which they would have made comparing the price under the principal contract with the Railway Company with the price they had to pay under the contract with the appellant. They accordingly dismissed the appellant's claim for damages, and gave him a decree for the deposit under deduction of the damages due to the respondents as above calculated.

3. The view of the evidence which commended itself to the High Court is set out with great minuteness in the judgment of the High Court, and as their Lordships agree with the learned Judges, they do not think it necessary to repeat what is there said. The crucial facts are as follows: (1) Time was of the essence of the original contract; (2) the appellant was in default in not making complete delivery in time i.e., at 31st of May, 1913; (3) the appellant applied for and was granted by the respondents an extension of time until the 30th of November, 1913, for delivery of the balance over the 1,746 sleepers which had been delivered; and (4) delivery of the balance was not made by the respondents on the 30th of November, and they were consequently in default. Their Lordships, however, think it necessary to give their opinion as to the law which applies to the above facts, The first point is settled by the Indian Contract Act, which enacts, Section 55, paragraph 1:

When a party to a contract promises to do a contain thing at or before a specified time, or contain thing at or before specified times, and fails to do any such thing at or before the specified time, the contract, or so much of it as has not bean performed, becomes voidable at the option of the promisee, if the intention of the parties was that time would be of the essence of the contract.

4. The respondents hero did not elect to void the contract; they held it as subsisting, and agreed to prorogue the time of performance, This they were entitled to do, see Section 63 of the Indian Contract Act, which explicitly says so:

63. Every promisee may dispense with or ramit, wholly or in part, the performance of the promise made to him, or may extend the time for such performance, or may accept instead of it any satisfaction which he thinks fit.

5. The learned Subordinate Judge in their Lordship opinion misread the third paragraph of Section 55; that paragra is as follows:

If, incase of a contract voidable on account of the promisor's 11 failure to perform his promise at the time agreed, the promisee accepts performance of such promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of; such acceptance, he gives notice to the promisor of his intention to do so.

6. This clearly means that the promisee cannot claim damages for nonperformance at the original agreed time, not that he cannot claim damages for non-performance at the extended time, yet the learned Judge says:

Subsequent extension of time could not legally bind the plaintiff to complete it within the time so generously extended by defendant and intimated to plaintiff months after.

7. Now apart from the terms of the Indian Contract Act, the law is as laid down in Tyers v. Rosedale and Ferryhill Iron Co. (1873) L.R. 8 Ex. 305. Baron Martin in that case said:

The second question is one of law, and is a most important one--it arises over and over again every day in the ordinary transactions of mankind. It is this: There is a contract for the sale of goods to be delivered, say, in January or upon a day of January. On the day before the delivery is to take place the vendor meets the vendee and says: 'It is not convenient for me to deliver the goods upon the day named, and I will be obliged if you will agree that the goods shall be delivered at a later period,' and the vendee assents; or the vendee goes to the vendor and says: 'It is not convenient for me to receive the goods in January or upon the day named and will you agree that the delivery shall he postponed?' and the vendor assents; the latter is the present case, and the contention on the part of the defendants is that this puis an end to the contract, and that the defendants are not bound to deliver upon the latter day. In my opinion, the contention is not well founded. It is impossible to distinguish the case of the application coming from the vendors and one coming from the vendee.

8. This opinion was affirmed in the Exchequer Chamber. The effect of the 55th section of the Indian Contract Act above quoted is, where the party having the option elects not to avoid, to put agreement after the original date on the same footing as an agreement as put by Baron Martin just before the original date. In England the matter is often complicated by the necessity of considering the 17th section of the Statute of Frauds and the 4th section of the Sales of Goods Act, but in the Indian Contract Act there is no section analogous to this. It is not necessary, therefore, to inquire whether the case of Plevins v. Downing (1876) I.C.P.D. 220 is or is 'not reconcilable with the case of Tyers v. Rosedale and Ferryhill Iron Co. (1875) L.R. 10 EX. 195. Difficulties which confronted the Court in Plevins v. Downing (1876) I.C.P.D. 220 do not arise here, so that the law may safely be stated as in Tyers v. Rosedale and Ferryhill Iron Co. (1875) L.R. 10 Ex. 195. Where, as here, specific time is stated, then that substituted date must hold. If there were a simple waiver of the right to extension of the original time, then a reasonable time would be the proper time for delivery. It follows that there being no delivery on the 30th of November, the appellant was in breach, and damages are calculable in the ordinary way.

9. The appellant, however, before the Board argued that the damages could not be recovered, because as a matter of fact the respondents supplied the sleepers from other wood which they had and made a profit on that supply greater than the profit which they would ,have made by the contract wood. The answer to this argument is to be found in the well-known case of Rodocanachi v. Milburn (1886) 18 Q.B.D. 67, which was applied by the House of Lords in the recent case of Williams v. Agius (1914) A.C. 570.

It is well settled that in an action for non-delivery or non-acceptance of goods under a contract of sale the law does not take into account in estimating the damages anything that is accidental as between the plaintiff and the defendant, as, for instance, an intermediate contract entered into with a third party for the purchase or sale of the goods.

10. In the present case had the appellant supplied the timber the respondents would have made their profit and would have still had the other timber to sell, upon which they were entitled to make such profit as they could.

11. Their Lordships will humbly advise His Majesty to dismiss the appeal with costs.