Skip to content


Food Corpn. of India and Ors Vs. Deepak Kumar Singh - Court Judgment

SooperKanoon Citation
CourtJharkhand High Court
Decided On
AppellantFood Corpn. of India and Ors
RespondentDeepak Kumar Singh
Excerpt:
.....written   statement   controverted     the  claim of the plaintiff and also raised a counter claim. according to them, the  plaintiff's cause  of action was barred by limitation and the principles of  waiver,   estoppel   and   acquiescence.   the   suit   was   also   barred   under   the  provisions of arbitration act embodied in the contract. they also averred  that   plaintiff's   engagement   was   on   ad­hoc   basis   with   effect   from   23rd  january, 1978 for transportation of goods. during this period because of his  un­workman like performance defendants suffered a loss of rs. 5,40,171/­,  which he was informed through letter dated 23rd december, 1980 to deposit .....
Judgment:

                                                           Appeal from  original Decree No. 89 of 1996(R) --- Against the judgment and decree dated 14.12.1995/21.12.1995 passed by Sub- Judge, V, Ranchi in Money Suit No. 82 of 1987. ­­ 1. Food Corporation of India 2. District Manager, Food Corporation of India, Ranchi 3. Senior Regional Manager, Food Corporation of  India,Patna ...Appellants Versus Deepak Kumar Singh ...             .....Respondent  ­­­         For the Appellant  : M/s. Satish Bakshi, Nipun Bakshi & Mrinal Singh, Advs. For the Respondents  : M/s. V. K. Prasad & Sahil, Advs. ­­­             PRESENT                     HON'BLE MR. JUSTICE APARESH KUMAR SINGH ---                By Court:  Heard learned counsel for the parties.

2. Appellants were the defendants in Money Suit No. 82 of 1987  instituted by the plaintiff/respondent, who has also preferred cross­objection  being aggrieved by the findings rendered in the same impugned judgment.  3. The case of the parties as borne out from the pleadings before  learned court, inter alia, are as under:  Plaintiff   was   appointed   as   Ad­hoc   contractor   for   the   period  1976­82   by   the   respondent/appellant­F.C.I   to   undertake   handling   and  transportation   of   consignment   of   different   commodities   received   at   the  Railway   Station   Ranchi   and   Hatia   which   included   three   operations   of  unloading   of   the   goods   from   the   railway   wagons,   loading   the   same   on  trucks   provided   by   the   plaintiff   and   its   transportation   to   the   point   of  destination.   The job required the contractor to deposit 50% of the total  security money with the concerned authority of defendant no. 1 either in  cash or through its Bank Demand Draft and remaining 50% to be realized  by way of deduction @ 5% from the running account bill of the contractor.  On completion of the work of contract, he was required to submit his final  bills for payment.  Plaintiff claims to have deposited the required security  2. money   through   different   sums   in   different   years   ranging   from   the   year  1976­1985 and the remainder was duly deducted from his running account  bills. But, according to him, he had not received a single farthing despite the  repeated   requests   and   reminders.   He   protested   through   letter   dated   23rd  December,   1980/8th  January,   1981   to   the   District   Manger   of   Food  Corporation   of   India.     He   also   took   the   plea   that   substantial   amount   of  security deposits and outstanding bills for the work done have remained  unpaid. He had to pay the minimum wages to the workers @ 60 paise per  bag for loading and unloading with variable dearness allowance as per the  rates prescribed by the appropriate authorities of the Govt. of Bihar in terms  of the clause of agreement whereas only 24 paise per bag for loading and  unloading was paid to him, as a result, he suffered a loss of Rs. 5,31,453/­,  which the defendants are obliged to pay.  4. It is not a matter of dispute and as per the case of the parties also  decided in answer to Issue no. 10 by learned trial court, that plaintiff was  awarded contract for handling and transporting of goods in a regular manner  for the period from 25th June, 1983 till 23rd June, 1985.  The nature of work  was same i.e., operation of work from Hatia Railway Station to Hatia Food  Storage Depot. Plaintiff in similar fashion made certain deposits   towards  security   and   certain   sums   were   also   deducted   from   his   running   bills.  Accordingly, he completed the work of handling and transportation for the  period from 24th  June, 1983 till 8th  May, 1985 and requested the Assistant  Manager and District Manager of the Corporation for grant of works done  certificate to enable him to submit his bills. This was avoided one or the  other pretext.   In the month of October, 1985, the defendants issued the  work   done   certificates.   Thereafter   on   3rd  November,   1985   the   plaintiff  submitted his bills for the work done to the tune of Rs. 1,78,717.12/­, but  the   defendants   neglected   to   refund   the   security   deposit.   Plaintiff   also  claimed payment of Rs. 79,845.92 on account of difference between the  contract rate and the rate at which payments were made to the plaintiff for  transportation work for the period from January, 1983. Plaintiff' also in total  claimed a sum of Rs. 8,70,684.60 from the defendants on account of refund  3. of   security   deposits   and   payment   for   value   of   the   works   done   under  different contracts as described in the schedule.  Cause of action according  to him, arose on different dates and finally on 19th November, 1986 when  the defendants failed to make payment to the plaintiff despite issue of legal  notice.

5. Defendants   through   their   written   statement   controverted     the  claim of the plaintiff and also raised a counter claim. According to them, the  plaintiff's cause  of action was barred by limitation and the principles of  waiver,   estoppel   and   acquiescence.   The   suit   was   also   barred   under   the  provisions of Arbitration Act embodied in the contract. They also averred  that   plaintiff's   engagement   was   on   Ad­hoc   basis   with   effect   from   23rd  January, 1978 for transportation of goods. During this period because of his  un­workman like performance defendants suffered a loss of Rs. 5,40,171/­,  which he was informed through letter dated 23rd December, 1980 to deposit  within 30 days, failing which, it would be deducted or adjusted from his  outstanding   bills   and   security   deposits   as   per   the   contract.     They   also  contended that due to breach of the contract, defendants have suffered loss.  The claim of the plaintiff to the extent of Rs. 5,31,423.00 on account of  revision of minimum wages was denied. Plaintiff had left the work during  the   subsistence   of   the   regular   contract   which   entailed   heavy   loss   and  expenses upon which they are entitled to realize   all the cost and damage  charges.     According   to   them,   plaintiff   committed   breach   of   contract  between   1983   to   1985   for   short   transportation   of   wheat,   rice   and   sugar  which entailed a loss of Rs. 1,92,128.12 and was legally recoverable from  them.  According to the defendants, due to abandonment of work, they had  to appoint new contractor to complete the left over work which entailed an  extra expenditure of Rs. 38,215.00.   Defendants incurred total amount of  Rs. 2,97,165.44 on account of violation of contract, out of which a sum of  Rs. 1,47,531.93 was adjusted against the bills submitted by the plaintiff and  the  balance  sum   of   Rs.  1,59,633.51 had remained due. Apart  from that,  defendants had to pay the  demurrage and wharfage  charges amounting to  Rs. 33,84,733.00 to the Railways on account of inadequate handling and  4. transportation facilities on the part of the plaintiff.  After adjustment of the  actual amount payable to the plaintiff, defendants were entitled to recover  a  sum of Rs. 35,34,366.81. Therefore, they sought a decree by way of counter  claim   to   the  aforesaid   extent.     According to them,  demand  notice dated  17th March, 1986 claiming the aforesaid amount was not replied. Again on  19th  November, 1987  they sent  reminder, but without any response.  The  defendants therefore sought dismissal of the suit with compensatory cost  and decree in respect of their counter claim.  6. In reply, plaintiffs contended that the entire counter claim was  malafide,   misconceived   and   not   maintainable   being   barred   by   law   of  limitation   and   principles   of   waiver,   estoppel   and   acquiescence;   that   no  cause of action had arisen for raising counter claim.  Plaintiff' had to leave  work as compelling circumstances were created by the defendants   which  prevented the plaintiff from discharging his part of the contract.  Therefore,  there was no breach of contract on the part of the plaintiff. Defendants have  arbitrarily adjusted the amount and that  demurrage and wharfage  charges  were not on account of any fault on the part of the plaintiff. They attributed  negligence   on the part of the Corporation Railway Head­in­charge as he  was never punctual in attending the goods office and never signed on T. 39  Form.  7. On the basis of the pleadings of the parties, learned trial court  framed 14 issues, inter alia, as follows:  i) Is the suit as framed maintainable?          ii) Has the plaintiff a valid cause of action for this suit? iii)Is the suit barred by the law of limitation and  principles of waiver estoppel and acquiescence? iv) Whether this suit is barred by the Arbitration Act? v) Whether due to the negligence of the plaintiff the  defendants had to pay the demurrage and wharfage  charges to the Railway? vi) Whether the plaintiff is entitled to get a decree  against the defendants? vii)Whether the plaintiff committed breach of contract  leading to the losses and damage to the defendants? viii)Whether the counter claim made by the defendants is legal and maintainable? ix)Whether the counter claim for a decree for               Rs. 35,34,366.81 as sought for by the defendants is  5. barred by the law of limitation? x) Whether the plaintiff was appointed as H/T  contractor on behalf of the Food Corporation of India  by its competent authority w.e.f 23.1.78 and further he  was appointed as the regular contractor in the year 1983  for handling and transportation of the goods from  Railway siding to the go­down of the defendants?  xi)Whether the plaintiff left the work of loading and  transportation of work during the subsistence of the  contract as a result thereof, the defendants had to  appoint another contractor to complete the incomplete  work? xii)Has this court jurisdiction to entertain this suit in  view of the arbitration cause in the contract entered into  by and between the plaintiff and the defendant? xiii) Are the defendants entitled to get a decree for  counter claim against the plaintiff? Xiv) To what other relief or reliefs if any the plaintiff is  entitled for? 8. Plaintiffs examined 8 witnesses, namely, P.W.1 is Suresh Sahani,  P.W.2, Laxman Ram, P.W.3 is Rajendra Pandey, P.W.4 is Deepak Singh  the   plaintiff,   P.W.5   is   Mahendra   Prasad,   P.W.6   is   Satyanarain   Prasad,  P.W.7 is Mohan Roy and P.W.8 is Jagdish Arora and also adduced several  documentary evidence.  9. Defendants   examined   16   witnesses,   namely,   Durga   Charan  Kashyap   (D.W.1),   Rath   Nath   Bhagat   (D.W.2),   Vinod   Kumar   Jaiswal  (D.W.3), Arbind Prasad (D.W.4), Premsagar Prasad Singh (D.W.5), Satya  Narain   Mandal   (D.W.7),   Sheo   Dayal   Mishra   (D.W.8),   Jafirul   Haque  (D.W.9),  B.D.Bishwarkarma  (D.W.10), Mahbool  Ali (D.W.11), Indradeo  Ram   (D.W.12),   R.K.P.Singh   (D.W.13),   Utpal   Bose   (D.W.14)   and  R.K.Pandey (D.W.16) and exhibited several documents in support of their  counter claim as well.   10. Learned trial court first decided more or less an undisputed issue  relating   to   the   appointment   of   plaintiff   as   a   contractor   initially   w.e.f.  23rd January, 1978 and thereafter as a regular contractor in the year 1982 for  handling transportation of goods from Railway Siding to Go­down of the  defendant in accord with the case of the parties also.   Learned trial court  thereafter proceeded to render a finding against the plaintiff on the issue  relating to limitation and also held the suit as being barred by Arbitration  6. Act.  It held that the claim for the period 1976 to 1983 given in the schedule  of the plaint was for a period beyond 3 years from the date of filing of the  suit and was, therefore, barred by limitation.   Plaintiff had completed the  work and work done certificates were also issued, to which no objection  was  raised  and  he  did not either make any claim regarding the amount.  Under   the  arbitration   clause   in   the   Ad­hoc   contract,   all   disputes   and  differences touching any of the items concerning the agreement were to be  adjudicated through the sole Arbitrator appointed by the Managing Director  of Food Corporation of India whose award could be final.  Plaintiff having  failed to refer the dispute to the sole Arbitrator and having remained silent  towards any claim relating to the period prior to 1982 was precluded from  raising such a claim to the present suit. Apart from that, the evidence of the  plaintiff (P.W.4) was also taken into account as he did not whisper a word  about the claim even prior to 1982.  P.Ws. 2 and 6 being his agents, who  had executed the work for the period November, 1982 to May, 1985 also  had not stated in relation to the claim relating to the work done prior to  1982.   No other witness of the plaintiff had spoken a word regarding the  claim prior to 1982.  The claim raised through the schedule were, therefore,  held to be barred by law of limitation and the provisions of the Arbitration  Act.  11. Learned   trial   court  thereafter  proceeded  to determine the Issue  No.   11   in   relation   to   the   counter   claim   raised   by   the   defendants.   Upon  analysis of the material pleadings and the evidences on record, it rendered a  finding that the plaintiff had left the execution of work on 9th  May, 1985,  though   the   stipulated   date   of   completion   of   work   was   23rd  June,   1985.  Plaintiffs had on their part failed to adduce any evidence to the effect that  the defendants were themselves responsible for creating circumstances and  situations   which   persuaded   him   to   leave   the   work   before   expiry   of   the  period. Learned trial court held that the plaintiff had violated the terms and  conditions of the contract causing loss and damage to the defendants with  regard to the work left over by him.   Defendant  had to appoint another  contractor.  7.

12. Learned trial court thereafter proceeding to determine the Issue  nos. 8 and 9 in relation to the counter claim raised by the defendants.  The  counter claim of the defendant were based on these items:  i)  Loss of Rs. 1,92,128.12 on account of breach of contract by the  plaintiff between 1983 to 1985; ii) Loss of Rs. 4,330/­ towards the price of gunny bags due to the  breach of contract by the plaintiff; iii) Incurring of extra expenditure of Rs. 38,215.00 for appointing  another   contractor   to   complete   the   left   over   work   after   the   plaintiff  abandoned the work prior to expiry of period of contract; iv) An amount of Rs. 2,97,165.44 incurred by the defendants on  account of breach of contract towards which they adjusted a sum of Rs.  1.47,531.93   against   the   bills   of   the   plaintiff   and   the   balance   of  Rs. 1,49,633.51 remained due to them; v) Claim of Rs. 33,84,733.30 towards  demurrage and wharfage  charges paid to the Railways due to inadequate handling and transportation  facilities provided by the plaintiff.  13. Learned   trial   court   held   that   period   of   contract   was   from  24th June, 1983 to 23rd June, 1985.  The period of three years of limitation  in raising such a counter claim or for filing a suit for recovery of the amount  should end on 24th June, 1988. The counter claim was laid on 18th July, 1988  beyond the period of limitation.  Therefore, it was not legally maintainable.  Though   the   claim   was   not   admitted   by   the   plaintiff,   but   the   defendant  should have taken legal recourse within 3 years from the aforesaid date to  recover the amount which they failed to do.  The counter claim against the  plaintiff was filed on 17th  July, 1988, which was beyond the period of 3  years.   Accordingly,   the   counter   claim   was   held   to   be   barred   by   law   of  limitation.   Learned trial court then proceeded to deliver a finding against  the defendant in relation to entitlement to counter claim in answer to Issue  no. 13.  At the same time, learned court also did not find substance in the  claim of the plaintiff for a decree for realization of the amount claimed.  8. Plaintiff,   Deep   Kumar   Singh   (P.W.4)   had,   in   his   cross­examination,  admitted that he had not deposited “No Demand Certificate” required for  refund of amount of security deposits.  P.W.3, in his cross­examination, had  also stated that no register was maintained regarding the payment of wages  to the labourers under the Minimum Wages Acts. D.W.9, an Assistant in  Food Corporation of India proved the Cheque of the credit note as Ext.­8  and stated that demurrage and wharfage charges were paid due to the acts of  the  plaintiffs  to the  Railways in mishandling of the transportation work.  D.W.10  also deposed against the plaintiff in relation to the mishandling of  transportation   work   in   an   un­workman­ship   manner   due   to   negligence  which   resulted   in   payment   of  demurrage   and   wharfage  charges   to   the  Railways. No cross­examination of the aforesaid witnesses were undertaken  by the plaintiff.         14. Learned trial court ultimately came to a conclusion that any such  amount  claimed   by  the  plaintiff were legally adjusted by the defendants  from his bills and therefore nothing remained due against the defendants.  Accordingly,  it  held  that  the plaintiff was not entitled to any decree for  realization of the amount claimed.  The counter claim of the defendants was  also dismissed as barred by law of limitation.  15. Learned counsel for the appellants had made elaborate arguments  on the findings of learned trial court in answer to Issue no. 9 where it held  the   counter   claim   as   barred   by   limitation.     The   entire   emphasis   of   his  submission is based upon Clauses 10 and 11 of the agreement, whereunder  in a case of termination of contract or violation of terms and conditions of  the   contract,   liability   of   contractor   is   to   be   ascertained   by   a   designated  officer of the Corporation.  Only after ascertainment of the liability and the  issuance of demand, which is dated  17th March, 1986 on the plaintiff failure  to respond, the cause of action   arose.   According to him, the terms and  conditions of contract contemplated creation of cause of action dependent  upon   ascertainment   of   the   liability   of   the   contractor   in   the   manner   laid  therein.  Therefore, the counter claim  was well within the period of  9. limitation, if it was filed in July, 1998.  16. Learned   counsel   for   the   appellants   has   relied   upon   judgments  rendered by the Apex Court reported in the case of  Syndicate bank Vs.   Channaveerappa Beleri and others reported in (2006) 11 SCC 506 and in  the case of M/s. Aries & Aries Vs. Tamil Nadu Electricity Board reported  in  2017 SCC OnLine SC 537  in support of his contention.   According to  him, if the findings relating to limitation are decided in their favour, the  entire claim on merits are bound to be adjudged in their favour.  17. The determination of the instant appeal so far as present appellant  is concerned, is primarily dependent on the question whether the counter  claim was barred by limitation or not? Whether the findings on Issue no. 9  by learned trial court are proper in the eye of law or on facts or not?   18. Considerable discussion has been undertaken on the point in issue  during the course of submission of learned counsel for the appellants and  the plaintiff/respondent herein. One may usefully referred to the Articles 18  and 55 of the Indian Limitation Act, which read as under:            Description of suit Period of limitation  Time   from   which   period  begins to run 18. For  the  price  of   Three years   When the work is done   work   done   by   the   plaintiff   for   the   defendant   at   his   request,   where   no   time   has   been   fixed   for payment 55.   For   Three years When   the   contract   is   compensation for the   broken or (where there are   breach   of   any   successive breaches) when   contract,   express   or   the   breach   in   respect   of   implied   not   herein   which the suit is instituted   specially   provided   occurs   or   (where   the   for.  breach   is   continuing)   when it ceases.

19. The claim of the appellants herein obviously does not fit in  terms  of Article 18. It provides for realization of price of work done within 3  10. years from the date when the work is done when no time has been fixed for  payment. Here is a case of breach on the part of contractor i.e., plaintiff  which is the basis for the defendants/appellants herein to raise his counter  claim.   Article 55 quoted above provides specific answer  as to the time  period from when cause of action arises in case of a breach of contract.  The  cause   of   action   for   compensation  for  breach of  any contract, express  or  implied  arise when   the  contract  is broken or  where there are successive  breaches, when the breach in respect of which the suit is instituted occurs or  where the breach is continuing, when it ceases.

20. In the  state of facts of the present  case as borne out from the  pleadings and evidence on record, plaintiff had left work on 9th May, 1985  i.e. more than 1 month before the stipulated date of completion of contract  i.e., 23rd June, 1985.  The Food Corporation of India­defendant were clearly  aggrieved on account of abandonment of the work by the contractor and  treated it as a breach of the terms and conditions of the contract. In any case  the contract would have come to an end by 23rd  June, 1985.   Even if, the  breach continued successively, it would have ceased by 23rd June 1985 only.  There are no pleadings or evidence on record on the part of the appellants  shown by the learned counsel for the appellants in support of their case that  there was an express or implied termination of the agreement on their part  on   account   of   the   breach   committed   by   the   plaintiff   contractor.     The  appellant undertook a task for ascertaining the outstanding liability against  the contractor and waited till March, 1986 to issue of notice of demand.  The   ascertainment   of   liability   dependent   upon   whims   and   vagaries   of  defendant­F.C.I on an uncertain future date would in any case not determine  the date of accrual of the cause of action. Cause of action accrued as a result  of  breach of contract on the part of the plaintiff i.e., on 9th May, 1985 and if  period   of   limitation   in   terms   of   Article   55   of   Limitation   Act   is   to   be  reckoned, the suit or counter claim should have been filed within a period of  3 years from that period.   Even if the breach continued, it ceased to have  effect on the stipulated date of completion of the work i.e., 23rd June, 1985.  Learned trial court was therefore not in error in coming to a finding that the  11. counter   claim   raised   by   the   defendant   on  18th  July,   1988  was   definitely  beyond the period of limitation.  21. Learned   counsel   for   the   appellants   has   tried   to   rely   upon   the  residuary   Article   113   under   the   Limitation   Act.   Article   113   however  contemplates of a limitation period in such circumstances when no period of  limitation   is   provided   elsewhere   in   the   schedule.     This   residuary   article  would   therefore   not   come   in   support   of   the   appellants.     The   judgment  rendered by the Apex Court in the case of Syndicate bank (Supra) also does  not come to the help of the appellants as it was rendered in the context of a  guarantor/sureties liability under Sections 128 and 129 of the Contract Act.  The Apex Court had occasion to deal with the special meaning of words 'on  demand'   or   'payable   forthwith   without   demand'   in   the   facts   and  circumstances  of the  case.   It was found that sureties liability would be  enforceable even if the principle debtor's liability has become time barred.  The limitation period would begin to run for sureties liability in such a case  from the date of such demand and refusal/non­compliance therewith.  It was  also held that the extent of liability under a guarantee and question when the  liability will arise, would depend on terms of the contract. The facts of the  present   case   are   therefore   clearly   distinguishable   as   it   is   not   a   case   of  realization of a liability from a surety or guarantor. If there was a clear  breach of the contract by the plaintiff the period of limitation would run in  terms   of   Article   55   of   the   Act   for   defendant   to   raise   a   claim   of  compensation,   which   they  failed  to do  within the  stipulated  period of  3  years.     The   appellant   is   also   unable   to   take   the   help   of   the   judgment  rendered by the Apex Court in the case of M/s. Aries & Aries(Supra). As  per the facts of the said case,   despite the date of final payment i.e., 13 th  January, 1981, the parties had exchanged correspondences between them  and   the   plaintiff   had   reiterated   its   claim   on   different   counts     including  execution  for extra work done, which the defendant  had entertained and  also   kept   the  matter   pending.   Finally, on 6th  November, 1981, the said  claims were rejected. In those circumstances, the apex court held that it  12. would be reasonable to assume that the cause of action in respect of rejected  claim arose on 6th November, 1981 and the suit could have been filed  prior  to   expiry   of   3   years   from   the   said   date   in   view   of   Article   113   of   the  Limitation Act, 1963.  The findings of High Court in holding to the contrary were therefore not justified.  22. In view of the discussions made hereinabove, this Court is of the  considered view that the counter claim raised by the defendant/appellant  was definitely barred by limitation.  23. Coming to the case of the plaintiff/cross­objector in the present  appeal, on consideration of the submission of learned counsel for the cross  objector,  I  find  that they have miserably failed to demolish the findings  rendered by the learned trial court in respect of claim related to the period  1978 to 1982 both on the point of limitation and being hit by the existence  of arbitration clause in the agreement during the period of Ad­hoc contract.  They have also not been able to establish their claim on the merits relating  to the period of 1982 to May, 1985.   Plaintiff had committed breach of  contract and had completely failed to bring on record any evidence to show  that the failure to perform their promise was actuated on account of refusal  of   defendant­FCI   to   perform   the   reciprocal   part   of   their   promise.     The  performance of the contract on the part of the plaintiff was not rendered  impossible on account of any refusal on the part of F.C.I. to comply their  reciprocal promise.   It also appears from the evidence on record that the  plaintiff had failed to adduce any evidence in relation to the payments made  under   the   Minimum   Wages   Act   and   also   not   deposited   No   Demand  Certificate for refund of the amount of security deposits which is a pre­ condition as per the evidence of P.Ws. 3 and 4 discussed hereinabove as  well.  Whatever amount had remained legally due in favour of the plaintiff'  for the work executed were duly adjusted by the Railways  after breach of  the contract on their part and engagement of a new contractor by the FCI to  get the work executed.   24. In totality of the facts and circumstances, the material evidence on  13. record and for the discussions made above, the respondents/cross­objectors  herein have completely failed to dislodge the findings of learned trial court  on any of the counts warranting interference in the impugned judgment.  Accordingly, both the instant appeal and cross­objection stands dismissed.                                         (Aparesh Kumar Singh,J)                          Jharkhand High Court, Ranchi                              Dated   4th January, 2018                           Jk/NAFR               


Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //