Skip to content


M/S Durga Industries Vs. the State of Madhya Pradesh - Court Judgment

SooperKanoon Citation

Court

Madhya Pradesh High Court

Decided On

Appellant

M/S Durga Industries

Respondent

The State of Madhya Pradesh

Excerpt:


.....  whereon,   the   above   two   plots   were   alloted   to   the  petitioner with the stipulation to execute the lease­deed within  one month from the date of issue of letter with a direction the  registered documents in quadruplicate along with the original  be deposited within the said period.  it was further stipulated by  said allotment order that in case formalities are not completed  within   the   time,   the   allotment   order   will   be   liable   to   be  cancelled.   the   petitioner   instead   of   getting   the   lease­deed  executed   within   one   month   from   the   date   of   issuance   of  allotment order, i.e. 10.9.2007 got the lease executed after more  than three years from the date of issuance of allotment order,  i.e.,  10.9.2007  got  the lease  executed  on 15th  september,  2010  and got the same registered on 30th november 2010.   clause 1 (a) of the lease deed clearly stipulated that “the  lessee hereby agrees to take possession of the land lease out to .....

Judgment:


1 W.P. No. 1701 Of  2013 21.3.2013 Shri Girish Kekre, learned counsel for the petitioner.

Shri   S.M.  Lal,   learned   Government   Advocate   for  respondent No. 1.

Ms. Surabhi Nigam, learned counsel for respondent Nos.  2 to 5.

With consent of the learned counsel for the parties, the  matter is heard finally.

Orders dated 13.8.2012 and 15.1.2013 are being assailed  vide this petition.

By   order   dated   13.8.2012,   Managing   Director,   M.P.  Audyogik   Kendra   Vikas   Nigam   (Jabalpur)   LTD.  cancelled   the  allotment of Industrial Plot No. 2 and 3 situated at Integrated  Infrastructure   Development   Centre   (IIDC).  Industrial   Area,  Lamtara district Katni for the reasons assigned therein that the  petitioner violated clauses 3, 7 (A), 7 (B) and 19 of the lease­deed  dated   15.9.2010.

    The   order   has   been   purportedly   passed   in  exercise of powers conferred vide clause 34 of the lease­deed.  Whereas, by order dated 15.1.2013 an appeal preferred by the  petitioner against the order of cancellation has been dismissed.

By letter of intent dated 15.6.2007, it was proposed to allot  plot Nos. 2 and 3 in IIDC area, Lamtara, Katni, admeasuring 20 x  35 m x 2 m admeasuring 1400 sq. meter (i.e., 15064 sq. ft.) area  of land being 0.346 Acre, 0.140 Hectares for setting up Daal Mill  industry.

2 Besides other terms and conditions, clause 6 of letter of  intent   clearly   stipulated   that   the   allottee   will   complete   the  formalities   of   executing   and   registering   the   lease   deed   and  taking over the possession of plot within 30 days from the date  of issue of allotment order.   An allotment order was issued on  10.9.2007;   whereon,   the   above   two   plots   were   alloted   to   the  petitioner with the stipulation to execute the lease­deed within  one month from the date of issue of letter with a direction the  registered documents in quadruplicate along with the original  be deposited within the said period.  It was further stipulated by  said allotment order that in case formalities are not completed  within   the   time,   the   allotment   order   will   be   liable   to   be  cancelled.

  The   petitioner   instead   of   getting   the   lease­deed  executed   within   one   month   from   the   date   of   issuance   of  allotment order, i.e. 10.9.2007 got the lease executed after more  than three years from the date of issuance of allotment order,  i.e.,  10.9.2007  got  the lease  executed  on 15th  September,  2010  and got the same registered on 30th November 2010.   Clause 1 (A) of the lease deed clearly stipulated that “the  lessee hereby agrees to take possession of the land lease out to  him within thirty days from the date of execution of the lease  deed and he further agrees to take possession of the land in the  condition it exist on that date.”

.   Furthermore Clause 3 of the  deed   stipulated   that   “If   the   yearly/Monthly   rent   of   the  land/premises and annual development fund for maintenance  of   industrial   area   or   any   part   thereof   is   No.  paid   within   one  month after the date prescribed by the Managing Director, M.P.  Audyogik Kendra Vikas Nigam (J) Ltd., Jabalpur the same will  3 have to be deposited with interest @ 18 % per annum for the  first one year 12 months of such default and @ 24 % per annum  the remaining period thereafter.”

That, clauses 7 (A) and 7 (B) respectively stipulated: “7 (A) THE LESSEE hereby agrees that he shall within  a   period   of   one   year,   being   the   small   scale  industry/three   yeaRs.  being   the   Medium/Large   Scale  Industry from the date of taking over possession of the  land, shall commence commercial production.

7 (B) THE LESSEE hereby agrees that he shall utilise  the   complete   land   leased   out   to   him   hereunder   for  implementation of project or for its expansion within a  period of 3 years in case of SSI and five years in case of  Medium/Large   Scale   Industry   for   the   above   said  purpose, from the date of taking possession of the land.”

Furthermore clause 19 stipulates that: “19.

THE LESSEE shall continuously run, during the  period of lease, the factory for which the land is allotted.  Closure of the factory for a continuous period exceeding  six months without proper reason to the satisfaction of  allotting authority shall be considered as breach of the  condition.”

That, the consequences of breach of above conditions are  mentioned in clauses 12 (B) and 33 of the lease deed.

Clause 12 (B) stipulates that “12.(B) THE   LESSEE   agrees   that   in   case   where   the  lessee   has   neither   taken   any   effective   steps   No.  the  4 industry is established or running within the time period  as mentioned in clause '7' and the constitution of the  Firm/partnership/Company   is   changed   without  permission of the lessor, the lessor has right to cancel  the allotment of land in such cases.”

Clause 33 stipulates that: “33.

Any notice required to be made or given to the  lessee   hereunder   shall   be   deemed   to   have   been   duly  served on him.   If sent by the Managing Director M.P.  Audyogik Kendra Vikas Nigam (J) Ltd., Jabalpur or any  other officer authorized by him in this behalf, through  post   by   registered   letter   addressed   to   the   lessee   at  premises of the said business or at registered office of  the firm.  Failing above if it is affixed at the entrance of  the said premises in the presence of the witnesses.

The petitioner despite of getting the lease­deed registered  on 30th November 2010 did not take any step to take possession  of the land leased out to him and to establish Daal, Chuni, Bhusi  industries   thereover.

    This   non­action   on   the   part   of   the  petitioner led to issuance of notice on 16.11.2011, calling upon  the petitioner that within 30 days the petitioner shall deposit the  amount   of   arrears   and   establish   the   industry   and   commence  production failing which action would be taken as per clause 21  of   Madhya   Pradesh   Udhyog   Bhoomi   Avantan   Niyam,   1974,  clause   28     of   Madhya   Pradesh   Rajya   Audyogik   Bhoomi   Avam  Audyogik   Bhavan   Prabandhan   Niyam,   2008   and   clause   33   of  lease­deed dated 15th September 2010.

5 Pertinent it would be to note that the letter was addressed  to the petitioner on the address on which the letter of intent  dated   15.6.2007   (Annexure   P­3)  and  10.9.2007  (Annexure  P­5)  were   served.

    Thereafter   again   by   letter   dated   18.1.2012   the  petitioner was called upon to effect compliance as stipulated in  clauses 7 (A) and 7 (B) of the deed dated 15.7.2010.  This letter  was   also   addressed   to   the   petitioner   on   the   address   given   in  letter   of   intent   and   allotment   order.

    When   there   was   no  response   from   the   petitioner   the   reminder   was   sent   on  21.5.2012.   The petitioner since did not respond to the notices  sent   to   him,   led   the   Managing   Director   to   pass   an   order   on  13.8.2012 cancelling the allotment of plot Nos. 2 and 3.  The said  order has subsequently been affirmed by the appellate authority  by impugned order dated 15.1.2013.

Though it is contended on behalf of the petitioner that no  notices were served on him as the address on the notice was not  that   of   the   petitioner.

    This   contention   of   the   petitioner   is,  however,   belied   from   the   document   brought   on   record   and  cumulatively   marked   as   Annexure   P­11,   i.e.,   notices   dated  16.11.2011 and 18.1.2012, which were sent on the same address  on which letter of intent and allotment order were sent.  Since  the petitioner had already received the letter of intent and the  allotment order, it has to be presumed as per clause 33 of the  deed that the subsequent letters/notices sent on same address  were also served on him.

Petitioner has filed Annexure P­12 to substantiate that the  letter   dated   21.5.2012   was   No.  served   on   him.

    It   is   to   be  remembered that letter dated 21.5.2012 was reminder of earlier  6 letter dated 16.11.2011 and was not a fresh show cause notice to  the   petitioner.

    Therefore,   the   contention   put­forth   by   the  petitioner that show cause notice was not properly served on  him and that he did not have proper opportunity to reply and  defend his case cannot be accepted.   Even otherwise it is apparent from the record that as per  letter   of   intent   the   petitioner   was   required   to   execute   and  register   the   lease­deed   and   take   over   the   possession   of   land  within 30 days from the date of issuance of allotment order.  The  allotment order was issued on 10.9.2007 and instead of getting  the lease­deed executed and registered within 30 days, the same  was got executed after a period of over three years, i.e., on 15th  September, 2010 and got it registered thereafter a period of two  months on 30th November 2010.  Furthermore, as per the terms  of   lease­deed   as   noticed   above   the   petitioner   was   to   take  possession of the plot in question and was to commence  the  production within a period stipulated therein. No material has  been commended at by the petitioner as to what steps he had  taken   immediately   after   receiving   the   allotment   order   dated  10.9.2007.

    There   is   also   no   material   on   record   to   show   that  effective steps were taken by the petitioner after execution and  registration   of   lease­deed   for   establishing   an   industry   and  commencing production.  It is, therefore, the petitioner who has  to blame himself for cancellation of allotment of plots as it is he  who committed the breach of the terms and conditions agreed  at by the petitioner vide lease­deed dated 15th September 2010.

In   view   whereof   the   cancellation   order   having   been  passed   on   the   basis   of   finding   of   fact   that   the   petitioner   has  7 committed a breach of terms and conditions agreed upon, the  same   canNo.  be   found   fault   with   as   would   warrant   an  interference.

In the result petition fails and is hereby dismissed.

 (SANJAY YADAV) JUDGE Vivek Tripathi


Save Judgments// Add Notes // Store Search Result sets // Organize Client Files //