| SooperKanoon Citation | sooperkanoon.com/640030 |
| Subject | Commercial |
| Court | Supreme Court of India |
| Decided On | Jan-30-1979 |
| Judge | Y.V. Chandrachud, C.J.,; V.D. Tulzapurkar and; A.P. Sen, JJ. |
| Reported in | AIR1979SC720; (1979)2SCC70; [1979]2SCR1147 |
| Acts | Code of Civil Procedure (CPC) - Sections 80 |
| Appellant | Hind Construction Contractors by Its Sole Proprietor Bhikamchand Mulchand JaIn (Dead) by Lrs |
| Respondent | State of Maharashtra |
| Cases Referred | and Charles Rickards Ltd. v. Oppenheim
|
Excerpt:
-
[b.p. sinha, c.j.,; j.c. shah,; j.r. mudholkar,; k. subba rao,; m. hidayatullah, jj.] the ruler of the state of sant had issued a tharao dated 12th march 1948, granting full right and authority to the jagirdars over the forests in their respective villages. pursuant to the agreement dated march 19, 1948, the state of sant merged with the dominion of india. on october 1, 1948, shree v. p. menon, secretary to the government of india, wrote a letter to the maharana of sant state expressly declaring that no order passed or action taken by the maharana before the day of april 1st 1948, would be questioned. after merger there was obstruction by the forest officers when the respondents were cutting the forests, but after some correspondence they were permitted to cut the trees on furnishing an undertaking that they would abide by the decision of the government. the government of bombay, after considering the implications of the tharao, decided that the order was mala fide and cancelled it on 8th july 1949 in the meantime these respondents were stopped from working the forests by the government of bombay. thereupon these respondents filed suits for declaration of rights in the forests and for a permanent injunction against interference with those rights by the state. the respondents claimed in these suits that the rights of the grantees to the forests were not liable to be cancelled by the dominion of india after the merger of the state of sant in june, 1948, by executive action, and that the government of bombay was not competent to obstruct them in the exercise of those rights. their claims were opposed by the state of bombay mainly on the ground that in the absence of recognition, express or implied, by the successor state of the rights conferred by the former ruler on the jagirdars the respondents could not enforce them in the municipal courts. these respondents filed five suits against the state of gujarat. all suits except one were dismissed by the trial court. the district judge on appeal ordered the dismissal of that suit also and dismissed the appeals of the plaintiffs in the other suits. the plaintiffs then appealed to the high court and the high court allowed all appeals and the suits were decreed.' the high court held on the basis of the letter written by shri v. p. menon, secretary that the succeeding sovereign had waived or relinquished its right to repudiate the tharao. the high court further held that the tharao was not a legislative action of the ruler of sant state. the state government appealed to this court by special leave. hence the appeal. per majority: hidayatullah j. (i) the act of state comes to an end only when the new sovereign recognises either expressly or impliedly the rights of the aliens. it does not come to an end by an action of subordinate officers who have no authority to bind the new sovereign. till recognition, either express or implied, is granted by the new sovereign, the act of the state continues. in the present case, the act of state could only come to an end if government recognised the rights flowing from tharao. that government never did. there was thus no recognition of the tharao or the rights flowing from it at any time. in the present case, the subordinate officers of the forest department allowed each respondent to cut the trees on furnishing an undertaking that he would abide by the decision of the government and so the question of waiver or relinquishment does not arise. secretary of state in council for india v. kamachee boye sahaba, (1859) 13 moore p. c. 22, secretary of state v. sardar rustom khan and others, (68) i. a. 109, mis. dalmia dadri cement co. ltd. v. commissioner of income-tax, [1959] s.c.r. 729, the state of saurashtra v. memon haji ismale haji, [1960] 1 s.c.r. 537, jagan nath agarwala v. state of orissa, [1962] 1 s.c.r. 205, state of saurashtra v. jamadar mohamed abdulla and ors., [1961] 3 s.c.r. 970 and vaje singhji jorwar singh v. secretary of state for india, (1924) l.r. 51 i.a. 357, relied on. virendra singh and ors. v. the state of uttar pradesh [1955] 1 s.c.r. 415, disapproved. bhola nath v. state of saurashtra, a.i.r. 1954 s.c. 680, bhojrajji v. the state of saurashtra, 61 bom. l.r. 20, referred to. (ii) the act of state did not come to an end by virtue of article 299(1) of government of india act, 1935 and so the respondents could not claim the protection of that section. section 299(1) did not come into play because it could only come into play after the rights were recognised. in the present case the rights were never recognised by the government. (iii) the original act of state continued even after january 26, 1950, because there was no state succession on january 26, 1950 in so far as the people of sant state were concerned. for them state succession was over some time in 1948. the act of state which began in' 1948 could continue uninterrupted even beyond 1950 and it did not lapse or get replaced by another act of state. these rights in question cannot be protected under the constitution because these rights were not recognised even before 1950. (iv) that the impugned tharao was not a law as it did not lay down any rule of conduct. it was a grant made to the jagirdars mentioned in the tharao.. the fact that maharana's tharao was passed to benefit a larger number of persons en bloc does not make it any the more a law if it did not possess any of the indicia of a law. the tharao did give rights to the grantees but did not lay down any rule of conduct. it is a grant and as a grant it was open to the new sovereign not to recognise it. madhorao phalke v. the state of madhya bharat, [1961] 1 s.c.r. 957, distinguished. ameer-unnissa begum and ors. v. mahboob begum and ors. a.i.r. 1955 s.c. 352. distinguished. maharaja shri umaid mills ltd. v. union of india and others. a.i.r. 1963 s.c. 953 and the bengal nagpur cotton mill ltd. v. the board of revenue, madhya pradesh and others, a.i.r. 1964 s.c. 888 relied on. (v) the right claimed here is not even a concessionary right such as has received the support of the international writers. it is more of the nature of a gift by the ruler at the expense of the state. it lacks bona fides which is one of the things to look for. there is no treaty involved and whatever guarantee there is, art. 363 of the constitution precludes the municipal courts from considering. this distinguishes the jurisdiction and power of the supreme court of the united states in which consideration of treaties is included. in the united states the constitution declares a treaty to be the law of the land. in india the position is different. article 253 enables legislation to be made to implement international treaties. this court has accepted the principles laid down by the courts in england in regard to the limits of the jurisdiction of municipal courts. the view of the supreme court of united states or the view taken in international law has not been accepted by this court. politically and ethically there might have been some reason to accept and respect such concessions but neither is a reason for the municipal courts to intervene. the rule that the act of the state can be questioned in a municipal court has never been adopted and it has been considered that it is a matter for the political departments of the state. however desirable it may be that solemn guarantees should be respected, this court should not impose its will upon the state, because this is outside its jurisdiction. in this case, the present respondents who were not parties to the merger agreement or to the letter written by mr. menon which was made expressly a part of the agreement cannot take advantage of cl. 7. if they were parties, article 363 would bar such plea. maharaj umeg singh and others v. the state of bombay and others. [1955] 2 s.c.r. 164, relied on. u.s. v. percheman, 32 u.s. 51 at 86, disapproved: shapleigh v. miar, 299 u.s. 468, referred to. salaman v. secretary of state for india, [1906] 1 k. b. 613, referred to. cook v. sprigg. [1899] a.c. 572, referred to. foster v. nielson. (1829) 2 pet. 253, referred to. birma v. the state, a.i.r. 1951 rajasthan 1 to 7, referred to. amodutijani v. secretary southern nigeria, [1921] 2 a.c. 399, referred to. clark v. allen, 331 u.s. 503. referred to. west rand central gold minning co. v. regem, [1905] 2 k.b. 391, referred to. secretary of state v. bai raj bai, (1915) l.r. 42 i.a. 229, relied on. per shah j. (1) the rule that cession of territory by one state to another is an act of state and the subjects of the former state may enforce only those rights in municipal courts which the new sovereign recognises has been accepted by this court. m/s. dalmia dadri cement co., ltd. v. commissioner of incometax, [1959] s.c.r. 729, jagannath agarwala v. state of orissa, [1962] 1 s.c.r. 205, promod chandra dev v. state of orissa, [1962] suppl. 1 s.c.r. 405 and the state of saurashtra v. jamadar mohd. abdullah, [1962] 3 s.c.r. 970, relied on. the secretary of state in council of india v. kamachee boye sahaba, 7 moore's i.a. 476, vajesinghji joravarsinghji v. secretary of state for india in council, l.r. 51 i.a. 357 and secretary of state v. sardar rustam khan and others, l.r. 68 i.a. 109, relied on. (ii) the constitutional provisions in the united states are somewhat different. under the constitution of the united states each treaty becomes a part of the law of the land; the provisions thereof are justiciable and the covenants enforceable by the courts. in india the treaties have not the force of law and do not give rise to rights or obligations enforceable by the municipal courts. in the present case by virtue of art. 363 of the constitution, it is not open to the respondents to enforce the covenants of the agreement as stated in the letter of guarantee written by mr. v. p. menon in the municipal courts. united states v. parcheman, [1833] 32 u.s. 51 at 86, 87, not relied on. cook v. sprigg. [1899] a.c. 572, referred to. maharaj umeg singh and others v. the state of bombay and others, [1955] 2 s.c.r. 164, relied on. (iii) an act of state may be spread over a period and does not arise merely an the point of acquisition of sovereign right. nor is the new sovereign required to announce his decision when he assumes or accepts sovereignty over foreign territory, about the rights created by the quondam sovereign, on pain of being held bound by the right so created. there. fore till the right to property of the subjects of the former indian state was recognized by the new sovereign there was no title capable of being enforced in the courts of the dominion or the union. (iv) the functions of a state whether it contains a democratic set up or is administered by an autocratic sovereign fall into three broad categories--executive, legislative and judicial. the line of demarcation of these functions in an absolute or autocratic form of government may be thin and may in certain cases not easily discernible. but on that account it is not possible to infer that every act of an autocratic sovereign has a legislative content or that every direction made by him must be regarded as law. the legislative power is the power to make, alter, amend or repeal laws and within certain definite limits to delegate that power. therefore it is power to lay down a binding rule of conduct. executive power is the power to execute and enforce the laws, and judicial power is the power to ascertain, construe. and determine the rights and obligations of the parties before a tribunal. in the present case the order dated march 12, 1948, is expressly in the form of a grant of the rights which were not previously granted and does not either expressly or by implication seek to lay down any binding rule of conduct. the impugned order was not a law or an order made under any law within the meaning of cl. 4 of the administration of the indian states order of 1948. promod chandra deb and others v. the state of orisa and others, (1962] suppl. 1 s.c.r. 405,ameer-un-nissa begum and others v. mahboob begwn and others, a.i.r. (1955) s.c. 352, director of endow-134-159 s.c.-30. ments, government of hyderabad v. akram ali, a.i.r. (1956) s.c. 60, tilkayat shri govindlalji maharaj etc. v. state of rajasthan and others, a.i.r. (1963) s.c. 1638, distinguished, discussed. madhorao phalke v. the state of madhya bharat, [1961] 1 s.c r 957 discussed. maharaja shree umaid mills ltd. v. union of india, a.i.r. 1963 s.c. 953, relied on. the bengal nagpur cotton mills ltd. v. the board of revenue, madhya pradesh and others, c.a. no. 416 of 1961 decided on july 30, 1963, relied on. (v) to attract s. 299(1) of the government of india act, 1935, there must, exist a right to property which is sought to be protected. the subjects of the acceding state are entitled only to such rights as the new sovereign chooses to recognize, in the absence of the any recognition of the rights of the respondents or their predecessor jagirdars, there was no right to property of which protection could be claimed. on the sam* reasoning, grantees of the ruler could not claim protection under art 31(1) of the constitution. per mudholkar j. (i) the rule of international law on which the several privy council decisions as to the effect of conquest or cession on the private rights of the inhabitants of the conquered or coded territory are founded has become a part of the common law of this country. this being a "law in force" and at the commencement of the constitution is saved by art. 372 of the constitution. the courts in india are, therefore, bound to en. force that rule and not what according to marshall c.j. is the rule at. international law governing the same matter, though the latter has also, received the approval of several text book writers. the rule which has. been applied in this country is not inequitor nor can it be regarded to be an anachronism. virendra singh v. the state of uttar pradesh, [1955] s.c.r. 415 united state v. percheman, (1833) 32 u.s. 51. disapproved. secretary of state for india v. kamachee boye sahiba, (1859) is moore p. c. 22, asrar ahmed v. durgah committee, ajmer, a.i.r. 1947 p.c. 1, dalmia dadri cement co. ltd. v. the commissioner of incometax, [1959] s.c.r. 729, state of saurashtra v. memon haji ismail [1960] 1 s.c.r. 537,state of saurashtra v. jamadar mohamed abdullah and ors., (1962] 3 s.c.r. 970, vajesinghji v. secretary of state for india,, 51 i.a. 357 and secretary of state for india v. bai rajbai, 42 i.a. 229promod chandra dev v. state of orissa and ors. [1962] supp. 1 s.c.r. 405, relied on (ii) two concepts underlie our law. one is that the inhabitants of acquired territories bring with them no rights enforceable against the new sovereign. the other is that the municipal courts have no jurisdiction to enforce any rights claimed by them, against the sovereign despite the provisions of a treaty unless their rights have been recognised by the new sovereign after cession or conquest. in other words a right which cannot on its own strength be enforced against a sovereign in the courts of that sovereign must be deemed to have ceased to exist. it follows therefore that a right which has ceased to exist does not, require repudiation. municipal courts derive their jurisdiction from the municipal law and not from the laws of nations and a change in the laws of nations brought about by the consent of the nations of the world cannot confer upon a municipal court a jurisdiction which it does not enjoy under the municipal law. (iii) the grantees of the ruler could not claim the protection of s 299 of government of india act, 1935 or of art. 31 of the constitution of india as they possessed no right to property enforceable against the new sovereign. (iv) the impugned tharao was not law. madhorao phalke v. the state of madhya pradesh [1961] 1 s.c.r. 957, referred to. per minority sinha c.j. and ayyangar j. (i) the juristic basis of the theory underlying the privy council decisions is that with the extinction of the previous sovereign the rights theretofore exerciseable by the subjects of that sovereign by virtue of grants for that sovereign were likewise extinguished and that without recognition which is really tantamount to a fresh grant by the new sovereign, no title enforceable in the municipal courts of the succeeding sovereign came into being. the doctrine of act of state evolved by english courts is one purely of municipal law. it denies to such a court jurisdiction to enquire into the consequences of acts which are inseparable from an extension of its sovereignty. that doctrine was, however. not intended to deny any rule of international law. the british practice that has prevailed in this country has not proved in actual practice to lead to injustice, but has proceeded on a just balance between the acquired rights of the private individual and the economic interests of the community, and therefore there is nothing in it so out of tune with notions of propriety or justice to call for its rejection. even in the case of virendra singh this court did not express any decisive opinion in favour of accepting the observations in percheman's case as proper to be applied by the municipal courts in india. this court has in subsequent decisions followed the privy council decisions. the view of the supreme court of the united states has not been accepted by this court for the reason that the constitutional position in regard to the recognition of treaties in both countries are different. in the united states a treaty has the force of law, which is not the position here. besides, in india by virtue of article 363 of the constitution, municipal courts are deprived of jurisdiction to enforce any rights arising from treaties. vinrendra singh v. the state of uttar pradesh, [1955] 1 s.c.r. 415, disapproved. vajesinghji v. secretary of state for india, 51 i.a. 357, cook v. sprigg, [1899] a.c. 572, relied on. walker v. baird, [1892] a.c. 491, johnstone v. pedlar, [1921] 2 a.c. 262, referred to. united states v. percheman, 32 u.s. 51, disapproved. m/s, dalmia dadri cement co. ltd. v. the commissioner of incometax, [1959] s.c.r. 729, jagan nath agarwala v. the state of orissa, [1962] 1 s.c.r. 205, promodh chandra dev v. the state of orissa, [1962] 1 supp. s.c.r. 405, the state of saurarhtra v. jamadar mohamad abdulla, [1962] 3 s.c.r. 970, secretary of state for india v. kanzachee boye sahiba [1859] 7 moore, i.a. 476, secretary of state for india in council v. bai rai bat, 42 i.a. 229 and secretary of state v. rustom khan, 68 ia. 109. relied on. amodu tijani v. secretary southern nigeria, [1921] 2 a.c. 399, referred to. west rand central gold mining co., v. rex, [1905] 2 k.b. 391. referred to. asrar ahmed v. durgha committee, ajmer, a.i.r. 1947 p.c. 1, relied on attorney-general of canada v. attorney-general of ontario, [1937] a.c. 326, referred to. (ii) where the new sovereign assumes jurisdiction and it does some act and there is ambiguity as to whether the same amounts to a recognition of a pre-existing right or not, the covenant and the treaty right be looked at in order to ascertain the intention and purpose of that equivocal act, but beyond this the covenant and the treaty cannot by them- selves be used either as a recognition pure and simple or, as waiver of a right to repudiate the pre-excisting rights. it is needless to point out that since the enforceability of the rights against the succeeding sovereign springs into existence only on recognition by the sovereign, there la no, question of a waiver or the right to repudiate. in the present case the high court erred in holding on the basis of cl. 7 of the letter of shri v. p. menon that the government waived their right to repudiate the grant made by the previous ruler. bhola nath v. the state of saurashtra, a.i.r. (1954) s.c. 680. distinguished (iii) just previous to the constitution the grantee had no right of property enforceable against the state. the coming into force of the constitution could not, therefore, make any difference, for the constitution, did,not create rights in property but only protected rights which otherwise existed. (iv) in the present case the "tharao" was not a grant to any individual but to the holders of 5 specified tenures in the state. the 'tharao' is more consistent with its being a law effecting an alteration in the tenures of the 5 classes of jagirdars by expanding the range of the beneficial enjoyment to the forests lying within the boundaries of the villages which had already been granted to them. in this light, the 'tharao' would not 'be administrative order in any sense but would partake of the character of legislation by which an alteration was effected in the scope and content of tenures referred to. the "tharao" dated march 12, 1918 satisfies the requirement of "a law" within art. 366(10) of the constitution and in consequence, the executive orders of the government of bombay by which the forests right% of the plaintiffs were sought to be denied were illegal and void. the "tharao" was in truth and substance a law which was continued by art. 372 of !he constitution and therefore it could be revoked by the appellant by legislative authority and not by an executive act. madhorao phalke v. the state madhya bharat [1961] 1 s.c.r 957, ameer-un-nissa begum v. mahboob begum, a.i.r. 1955 sup 4 court, 352 and director of endowments, government of hyderabad akram ali, a.i.r. 1956 s.c. 60, relied on. per subha rao j. (i) the decision in virendra singh's case is not only correct, but. is also in accord with the progressive trend of modern international law. it may, therefore, be stated without contradiction that in none of the decisions of this court that were given subsequent to vires. dra singh's ease the correctness of that decision was doubted. after all, an act of state is an arbitrary act not based on law, but on the modern version of 'might is right'. it is an act outside the law. there were two different lines of approach. one adopted by the imperialistic nations and the other by others who were not. that divergence was reflected in english and american courts. all the jurists of international law recognise the continuity of title to immovable property of the erstwhile citizens of the ceding state after the sovereignty changed over to the absorbing state. it may, therefore, be held that so far as title to immovable property is concerned the doctrine of international law has become crystallized and thereunder the change of sovereignty does not affect the title of the erstwhile citizens of the ceding state to their property. in america the said principle of international law has been accepted without any qualification. m/s. dalmia dadri cement co. ltd. v. the commissioner of income-tax, [1959] s.c.r. 729,jagannath agarwala v. the state of orissa, [1962] 1 s.c.r. 205, promodh chandra dev. v. the state of orrissa [1962] supp. 1 s.c.r. 405, state of saurashtra v. jamadar mohmed abdulla, [1962] 3 s.c.r. 970, discussed and distinguished. united states v. percheman, (1833) 32 u.s. 51, relied on. foster v. neilson, (1829) 2 p.e.t., 253, the american insurance co. and the ocean insurance co. v. bales of cotton (1828) 7 l.ed. 511, charles dehault v. united states, (1835) 9 ed. 117, vajeenngli joravarsingji v. secretary of state for india in council, (1951) i.a. 357, referred to. (ii) the law in england is that the municipal courts cannot enforce the acquired rights of the erstwhile citizens of the ceding state against the absorbing state unless the said state has recognized or acknowledged their title. this court accepted the english doctrine of act of state in a series of decisions. the word "recognize" means "to admit, to acknowledge, something existing before". by recognition the absorbing state does not create or confer a new title, but only confirms a pre-existing one. non-recognition by the absorbing does not divest the title, but only makes it unenforceable against the state in municipal courts. pramod chandra dev. v. the state of orissa, [1962] supp. 1 s.c.r. 503, relied on. (iii) the doctrine of acquired rights, at any rate in regard to immovable property has become crystallized in international law. under the said law the title of a citizen of a ceding state is preserved and not lost by cession. the change of sovereignty does not affect his title. the municipal laws of different countries vary in the matter of its enforceability against the state. as the title exists, it must be held that even in those countries, which accepted the doctrine of act of state and the right of a sovereign to repudiate the title, the title is good against all except the state. before the constitution came into force the state did dot repudiate the title. when the constitution of india came into force the respondent and persons similarly situated who had title to immovable pro- perty in the sant state had a title to the said property and were in actual possession thereof. they had title to the property except against the state and they had, at any rate, possessory title therein. the constitution in article 31(1) declares that no person shall be deprived of his property save by authority of law. that is, the constitution recognised the title of the citizens of erstwhile state of sant, and issued an injunction against the sovereign created by it not to interfere with that right except in accordance with law. a recognition by the supreme law of the land must be in a higher position than that of an executive authority of a conquering state. it was held that the title to immovable property of the respondent was recognised by the constitution itself and, therefore, necessarily by the sovereign which is bound by it. in the present case the letter written by the government of india dated 'october 1, 1948, clearly recognized the title of the respondents to their properties. the letter clearly contains a statement in paragraphs 5 and 7 thereof that enjoyment of jagirs, grants etc., existing on april 1, 1948, were guaranteed and that any order passed or action taken by the ruler before the said date would not be questioned. this is a clear recognition of the property rights of the respondent and similar others. virendra singh v. the state of uttar pradesh, [1955] 1 s.c.r. 415, relied on. m/s. dalmia dadri cement co. ltd. v. the commissioner of incometax [1959], s.c.r. 729, jagan nath agarwala v. the state of orissa [1962], 1 s.c.r. 205, promodh chandra dev v. the state of orissa' [1962], supp. 1 s.c.r. 405 and state of saurashtra v. jamadar mohamed abdullah [1962], 3 s.c.r. 970, discussed and distinguished.
- 34) containing the terms and conditions as well as the schedules, specifications etc. 3. the state of maharashtra resisted the claim contending that time was of the essence of the contract, that the date fixed for commencement was real and not nominal and the 12 months period was fixed after all aspects of the matter had been taken into account, it was further contended that the appellant-plaintiff knew the situation of the site and the so-called difficulties, that there was no excuse for him for not doing the work during the months of july to november, that the appellant-plaintiff failed to carry out the proportionate work during the periods fixed in the contract and that since the appellant-plaintiff had rendered himself incompetent to complete the work in proper time it had to rescind the contract and the recision was proper and for adequate reasons; he further urged that the high court had clearly erred in assuming that the appellant-plaintiff could not have completed the work even within the next three mouths a and, therefore, the contract was rightly rescinded by the respondent-defendant. on the other hand, counsel for the respondent-defendant sought to support the judgment and decree of the high court on both the grounds first that time was of the essence of the contract having regard to the express provision contained in clause (2) of the 'conditions of contract' and, therefore, on appellant-plaintiff's failure to complete the same within the stipulated time the recision of the contract was legal and justified and secondly, that even if time was not of the essence of the contract, having regard the circumstances the high court rightly came to the conclusion that the recision of the contract by the respondent-defendant could not be regarded as unreasonable or unjustified and that, therefore, the appellant-plaintiff being in breach the security deposit had been rightly forfeited. indisputably, in the work order dated july 2, 1955 the executive engineer had directed the appellant-plaintiff to commence the work by july 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from july 5, 1955. both the trial court as well as the high court have found that mentioning of july 5, 1955 as the date for starting the work was not nominal but was real date intended to be acted upon by the parties. on the other hand counsel for the respondent-defendant contended that time had been expressly made of the essence of the contract and in that behalf reliance was placed upon clause (2) of the 'conditions of contract' where not only time was stated to be of the essence of the contract on the part of the contractor but even for completion of proportionate works specific periods had been specified and, therefore, the appellant-plaintiff's failure to complete the work within the stipulated period entitled the respondent-defendant to rescind it. exceptionally, the completion of the work by a specified date may be a condition precedent to the contractor's right to claim payment the parties may expressly provide that time is of the essence of the contract and where there is power to determine the contract on a failure to complete by the specified date, the stipulation as to time will be fundamental. where time has not been made of the essence of the contract or, by reason of waiver, the time fixed has ceased to be applicable, the employer may by notice fix a reasonable time for the completion of the work and dismiss the contractor on a failure to complete by the date so fixed. and further to ensure good progress during the execution of the work, the contractor shall be bound, in all cases in which the time allowed for any work exceeds one month, to complete. two aspects emerge very clearly from the aforesaid two clauses, in the first place under clause 6 power was conferred upon the executive engineer to grant extension of time for completion of the work on reasonable grounds on an application being made by the contractor (appellant-plaintiff) in that behalf; such a provision would clearly be inconsistent with parties intending to treat the stipulated period of 12 months in clause 2 as fundamental. counsel for the appellant-plaintiff further pointed out and, in our view, rightly that the five or six factors, namely, (1) the contract having been given at the threshold of monsoon, the period of monsoon (4 months) ought not to have been reckoned, (2) absence of proper road and approach to the work site during the rainy season and a couple of months thereafter, (3) unreasonable rejection by the government officers of material brought on the site, which material was later on allowed to be used, (4) difficulty in procuring labour due to malarious climate at the site, (5) delay in issuing quarry permit and (6) extra time taken for doing extra work that was entrusted ought to have been taken into account-were put forward by the appellant-plaintiff merely for the purpose of showing that the refusal to extend the time by the superintending engineer although recommended by the s. if time was not of the essence of the contract or if the stipulation as to the time fixed for completion had, by reason of waiver, ceased to be applicable then the only course open to the respondent-defendant was to fix some time making it the essence and if within the time so fixed the appellant-plaintiff had failed to complete the work the respondent-defendant could have rescinded the contract. 69) had recommended extension upto december 1956 as sought while by his letter dated june 23, 1956 (ex. 70) addressed to the superintending engineer, the executive engineer had recommended that extension of time up to october 30, 1956 may be granted to the appellant-plaintiff with clear intimation that if he failed to complete the work by then, the maximum penalty allowable under clause 2, namely, 10% of the cost of the work will be inflicted on him, but the recommendation did not receive approval of the superintending engineer. instead it rescinded the contract straightaway by letter dated august 27, 1956. such recision on the part of the respondent-defendant was clearly illegal and wrongful and thereby the respondent-defendant committed a breach of contract, with the result that there could be no forfeiture of the security deposit.v.d. tulzapurkar, j.1. these appeals by certificate of fitness granted by the high court of judicature at bombay are directed against that court's common judgment and decree dated september 9/10, 1968, passed in two cross appeals being first appeal nos. 245 of 1962 and 844 of 1961.2. a contract for the construction of an aqueduct across the alandi river at mile no. 2 of the nasik left bank canal of the total value of rs. 1,07,000/- was granted to the appellant-plaintiff (originally a partnership but later a proprietary firm of contractors) by the respondent-defendant (the state of maharashtra) after the former's tender was accepted on june 17, 1955. on july 2, 1955 the executive engineer issued the work order to the appellant-plaintiff directing him to commence the work by july 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from july 5, 1955. the formal regular contract in prescribed form b-2/1 of 1955-56 (ex. 34) containing the terms and conditions as well as the schedules, specifications etc. was executed by the parties on july 12, 1955. a security deposit of rs. 4,936/- was kept by the appellant-plaintiff with the respondent-defendant. the period for completion of work was fixed as 12 months from the date stipulated for commencement of the work, that is to say, it was expected to be completed on or before july 4, 1956. it appears that on the ground that the appellant-plaintiff had not completed the work as expected within the stipulated time the executive engineer by his letter dated august 27, 1956 (ex. 78) rescinded the said contract with effect from august 16, 1956. after serving a notice under section 80 of the civil procedure code the appellant-plaintiff filed a suit (being special civil suit no. 23 of 1959) on august 28, 1959 in the court of the joint civil judge, senior division, nasik making a claim for rs. 65,000/- in the aggregate against the respondent-defendant alleging wrongful and illegal recision of the contract on the part of the respondent-defendant the appellant-plaintiff's case was that the initial fixation of july 5, 1955 as the date for commencement of the work was nominal, that the area where the work was to be done had usually heavy rainfall rendering it impossible to carry out any work from july to november and that, therefore, it was the practice of the public works department to deduct the period of monsoon in case of such type of works and that the appellant-plaintiff had been orally informed that this period would be deducted or not taken into account for calculating the period of 12 months under the contract and that oft this assurance he had commenced the work towards the end of december 1955. his case further was that in any event time was not of the essence of the contract, that on account of several difficulties, such as excessive rains, lack of proper road and means of approach to the site, rejection of materials on improper grounds by government officers, etc., over which he had no control, the completion of the work was delayed and that the extension of the time which was permissible under the contract had been wrongfully refused by the officers of the respondent-defendant. according to him none of these factors had been taken into account by the government while refusing the extension and the contract was wrongfully rescinded and, therefore, the respondent-defendant was liable in damages. the total claim of rs. 65,000/- comprised six items-(1) rs. 4,936/- being the amount of security deposit wrongfully forfeited by the respondent-defendant, (2) rs. 10,254/- being the amount due to him for the actual work done by him under bill no. 1253 dated september 20, 1956 and which had not been paid for, (3) rs. 7,375/- being the value of the material collected by him on the site for work but which had been rendered useless on account of wrongful recision, the 4th and 5th items sounded in damages, while the last item was interest from date of recision to the date of the suit.3. the state of maharashtra resisted the claim contending that time was of the essence of the contract, that the date fixed for commencement was real and not nominal and the 12 months period was fixed after all aspects of the matter had been taken into account, it was further contended that the appellant-plaintiff knew the situation of the site and the so-called difficulties, that there was no excuse for him for not doing the work during the months of july to november, that the appellant-plaintiff failed to carry out the proportionate work during the periods fixed in the contract and that since the appellant-plaintiff had rendered himself incompetent to complete the work in proper time it had to rescind the contract and the recision was proper and for adequate reasons; it was further contended that the state was entitled to forfeit the security deposit which it did on the date when the contract was rescinded. the several items claimed by the appellant-plaintiff were denied by the state. it was denied that the material of the value of rs. 7,375/- remained on the sits or that it was responsible for its non-removal from the site. regarding items 4 and 5 the state denied its liability to pay the same as it was the appellant-plaintiff who had committed the breach of the contract. as regards the amount due under bill no. 1253 dated september 20, 1956 for the actual work done, it was contended that the state had to deduct the amount of penalty leviable under the contract and for the actual cement supplied to the appellant-plaintiff and after making deductions in that behalf only a sum of rs. 700/- would be due to the appellant-plaintiff.4. on a consideration of the documentary evidence including the terms and conditions of the contract (ex. 34) and the oral evidence led by the parties, the learned trial judge held that the date july 5, 1955 fixed as the date for commencement of the work was not nominal but that time was not of the essence of the contract between the parties, that the respondent-defendant (state government) had wrongfully, rescinded the contract, that the appellant-plaintiff was entitled to damages but that he had not established the two items claimed as damages and he was entitled to a nominal sum of rs. 120/- as damages. he further held that since the recision of the contract was wrongful the state was not entitled to forfeit the security deposit nor levy any penalty. he accordingly decreed the appellant-plaintiff's claim in respect of refund of security deposits and as regards the amount of bill no. 1253 dated september 20, 1956 for actual work done he held that a sum of rs. 5,845/- only would be due to him after giving credit for rs. 4,409/- due from the appellant-plaintiff to the state. he accordingly decreed the appellant-plaintiff's suit to the extent of rs. 10,901/- with interest thereon at 6% per annum from the date of recision till date of suit and allowed proportionate costs to him.5. two appeals were preferred against the aforesaid decree of the trial court, one by the appellant-plaintiff in respect of the claims that had been disallowed (first appeal no. 245 of 1962) and the other by the state in respect of the claims allowed against it (first appeal no. 844 of 1961). curiously enough the high court did not decide the main issue that arose between the parties, namely, whether time was of the essence of the contract, as it took the view that a decision on that question was really unnecessary for disposal of the appeals. it proceeded to decide the appeals on the assumption that time was not of the essence of the contract by considering the question whether the recision of the contract by the state could be regarded as mala fide or so unreasonable that it must in the place of the judgment of the officers concerned substitute its own judgment and hold that the recision was wrongful. the high court observed that even the appellant-plaintiff had not alleged any mala fide on the part of any of the officers of the state but had pressed into service five or six factors the non-consideration whereof by the respondent-defendant rendered the recision of the contract arbitrary, unreasonable and, therefore, unjustified. after discussing each one of those five or six factors the high court held that some of them had not been proved by the appellant-plaintiff while others did not head to the inference that the recision of the contract was arbitrary, unreasonable or unjustified. it found that by about july 21, 1956 (vide ex. engineer's letter ex. 74) the appellant-plaintiff had done only 1/3rd of the contract work and that in the circumstances the appellant-plaintiff could not have completed the work even within the next three months and, therefore, the respondent's officers had rightly rescinded the contract and, therefore, it was the appellant-plaintiff and not the respondent-defendant who had committed a breach of the contract. however, the high court took the view that for such breach on the part of the appellant-plaintiff, the respondent-defendant, on a reading of the clauses 2 and 3 of the conditions of contract, was not entitled both to levy compensation and also to forfeit the security deposit. accordingly, the high court upheld the forfeiture of the security deposit made by the respondent-defendant and while modifying the trial court's decree it confirmed it only to the extent of rs. 5,845/-, being the amount due to the appellant-plaintiff for the work actually done by him under bill no. 1253 and which had not been paid. in the result, the appellant-plaintiff's appeal was dismissed and that of the state was partly allowed with appropriate order of proportionate costs.6. in support of the present appeal counsel for the appellant-plaintiff raised two or three contentions. in the first place he contended that the high court was in error in not deciding the main issue whether the time was of the essence of the contract or not he urged that the said issue could not be avoided in the manner done by the high court, for, if time was not of the essence of the contract then just before the expiry of the 12 months' period or immediately after its expiry it was up to the respondent-defendant to grant some reasonable time to the appellant-plaintiff for completing the work undertaken and make the same the essence of the contract and only if the work was not completed by the appellant-plaintiff within that time the contract could have been rescinded on the ground that the appellant-plaintiff had committed a breach of a contract. according to him such course of action on the part of the respondent-defendant was obligatory, when the initial period of 12 months was not of the essence, especially when the request of the appellant-plaintiff for extension of time was pending before the concerned officers of the government since before the expiry of the initial period. he contended that instead of adopting the aforesaid course the respondent-defendant had without making time of the essence of the contract rescinded the same with effect from august 16, 1956 by a letter dated august 27, 1956 (ex. 7:8), which recision must be regarded as wrongful and illegal. secondly counsel contended that the high court further erred in considering the question whether the recision of the contract by the state was either mala fide or wholly unreasonable and, therefore, unjustified. he pointed out it was not the appellant-plaintiff's case that the recision was mala fide and, according to him, the question was not whether the recision of the contract on the part of the respondent-defendant was unreasonable, and, therefore, unjustified but whether the respondent-defendant was entitled in law to rescind the contract in the manner done when time was not of the essence of the contract. he further urged that the high court had clearly erred in assuming that the appellant-plaintiff could not have completed the work even within the next three mouths a and, therefore, the contract was rightly rescinded by the respondent-defendant. he, however, fairly stated that even if this court held in his favour that the recision was wrongful and, therefore, the respondent-defendant had committed a breach he would merely press for the restoration of the decree passed by the trial court and not press any other item forming the subject-matter of the original claim in the suit. on the other hand, counsel for the respondent-defendant sought to support the judgment and decree of the high court on both the grounds first that time was of the essence of the contract having regard to the express provision contained in clause (2) of the 'conditions of contract' and, therefore, on appellant-plaintiff's failure to complete the same within the stipulated time the recision of the contract was legal and justified and secondly, that even if time was not of the essence of the contract, having regard the circumstances the high court rightly came to the conclusion that the recision of the contract by the respondent-defendant could not be regarded as unreasonable or unjustified and that, therefore, the appellant-plaintiff being in breach the security deposit had been rightly forfeited.7. the first question that arises for our consideration, therefore, is whether time was of the essence of the contract that was executed between the. parties on july 12, 1955 (ex. 34). it cannot be disputed that question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. the contract in the instant case is for the construction of an aqueduct across the alandi river at mile no. 2 of the nasik left bank canal and unquestionably 12 months' period commencing from the date of the commencement of the work had been specified within which the construction had to be completed by the appellant-plaintiff. indisputably, in the work order dated july 2, 1955 the executive engineer had directed the appellant-plaintiff to commence the work by july 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from july 5, 1955. both the trial court as well as the high court have found that mentioning of july 5, 1955 as the date for starting the work was not nominal but was real date intended to be acted upon by the parties. it is, therefore, clear that 12 months' period mentioned for the completion of the work was to expire on july 4, 1956. the question is whether this period of 12 months so specified in the contract was of the essence of the contract or not on the one hand, counsel for the appellant-plaintiff contended that the contract being analogous to a building contract the period of 12 months would not ordinarily be of the essence of the contract as the subject-matter there of was not such as to make completion to time essential, that an agreement to complete it within reasonable time would be implied and that reasonable time for completion would be allowed. on the other hand counsel for the respondent-defendant contended that time had been expressly made of the essence of the contract and in that behalf reliance was placed upon clause (2) of the 'conditions of contract' where not only time was stated to be of the essence of the contract on the part of the contractor but even for completion of proportionate works specific periods had been specified and, therefore, the appellant-plaintiff's failure to complete the work within the stipulated period entitled the respondent-defendant to rescind it. in the latest 4th edn. of halsbury's laws of england in regard to building and engineering contracts the statement of law is to be found in vol. 4, para 1179, which runs thus:1179. where time is of the essence of the contract. the expression time is of the essence means that a breach of the condition as to the time for performance will entitle the innocent party to consider the breach as a repudiation of the contract. exceptionally, the completion of the work by a specified date may be a condition precedent to the contractor's right to claim payment the parties may expressly provide that time is of the essence of the contract and where there is power to determine the contract on a failure to complete by the specified date, the stipulation as to time will be fundamental. other provisions of the contract may, on the construction of the contract, exclude an inference that the completion of the works by a particular date is fundamental, time is not of the essence where a sum is payable for each week that the work remains incomplete after the date fixed, nor where the parties contemplate a postponement of completion.where time has not been made of the essence of the contract or, by reason of waiver, the time fixed has ceased to be applicable, the employer may by notice fix a reasonable time for the completion of the work and dismiss the contractor on a failure to complete by the date so fixed.(emphasis supplied)8. it will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental, for instance, if the contract were to include causes providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract. the emphasised portion of the aforesaid statement of law is based on lamprell v. billericay union [1849] 3 ex 283, webb v. hughes [1870] l.r. 10 eq 281 and charles rickards ltd. v. oppenheim [1950] 1 kb 616. it is in light of the aforesaid position in law that we will have to consider the several clauses of the contract ex. 34 in the case. the material clauses in this behalf are clauses 2 and 6 of the 'conditions of contract' which run as follows:clause 2:the time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be reckoned from the date on which the order to commence work is given to the contractor. the work shall throughout the stipulated period of the contract be proceeded with, with all due diligence (time being deemed to be of the essence of the contract on the part of the contractor) and the contractor shall pay as compensation an amount equal to one per cent or such smaller amount as the superintending engineer (whose decision in writing shall be final) may decide, of the amount of the estimated cost of the whole work as shown by the tender for every day that the work remains uncommenced, or unfinished, after the proper dates. and further to ensure good progress during the execution of the work, the contractor shall be bound, in all cases in which the time allowed for any work exceeds one month, to complete.1/4 of the work in 1/4 of the time1/2 of the work in 1/2 of the time3/4 of the work in 3/4 of the time.clause 6: if the contractor shall desire an extension of the time for completion of the work on the ground of his having been unavoidably hindered in its execution or on any other ground, he shall apply in writing to the executive engineer before the expiry of period stipulated in the tender or before expiry of 30 days from the date on which he was hindered as aforesaid or on which the cause for asking for extension occurred, whichever is earlier and the executive engineer, may if in his opinion there are reasonable grounds for granting an extension, grant such extension as he thinks necessary or proper. the decision of the executive engineer in this matter shall be final.two aspects emerge very clearly from the aforesaid two clauses, in the first place under clause 6 power was conferred upon the executive engineer to grant extension of time for completion of the work on reasonable grounds on an application being made by the contractor (appellant-plaintiff) in that behalf; in other words, in certain contingencies parties had contemplated that extension of time would be available to the contractor. such a provision would clearly be inconsistent with parties intending to treat the stipulated period of 12 months in clause 2 as fundamental. similarly, in clause 2 itself provision was made for levying and recovering penalty/compensation from the appellant-plaintiff at specified rates during the period the work shall remain unfinished after the expiry of the fixed date. such provision also excludes the inference that time (12 months period) was intended to be of the essence of the contract. further with regard to the provision that is to be found in clause 2 whereunder a time schedule for proportionate work had been set out (namely, 1/4 of the work in 1/4 of the time, 1/2 of the work in 1/2 of the time and 3/4 of the work in 3/4 of the time ), the evidence of the superintending engineer pandit (d.w. 1) is very eloquent. in para 13 of his deposition this is what he has stated:in the agreement (ex. 34) the rate of work is based on the valuation 1/4th time mentioned means 1/4th in 12 months. the suit contract is for rs. 1,07,000/-. 1/4th work means the work of about rs. 27,000/-. it is not possible to do the work of rs. 27,000/- in 1/4th time as the days were rainy. this was not reasonable.the witness in para 12 of his deposition has also given the following admission:it is not specifically mentioned in the agreement (ex. 34), that the suit work was urgent and that it was to be completed within 12 months. in this agreement (ex. 34) there are the clauses of imposing a penalty and extension of time.9. having regard to the aforesaid material on record, particularly the clauses in the agreement pertaining to imposition of penalty and extension of time it seems to us clear that time (12 months period) was never intended by the parties to be of the essence of the contract. further from the correspondence on the record, particularly, the letter (ex. 78) by which the contract was rescinded it does appear that the stipulation of 12 months' period was waived, the contractor having been allowed to do some more work after the expiry of the period, albeit at his risk, by making the recision effective from august 16, 1956.10. once either of the aforesaid conclusions is reached it would be difficult to accept the high court's finding that the recision of the contract on the part of the respondent-defendant was proper and justified on the basis that the same was neither shown to be mala fide nor unreasonable. it must be observed that it was never the case of the appellant-plaintiff that the recision of the contract on the part of the respondent-defendant was mala fide. counsel for the appellant-plaintiff further pointed out and, in our view, rightly that the five or six factors, namely, (1) the contract having been given at the threshold of monsoon, the period of monsoon (4 months) ought not to have been reckoned, (2) absence of proper road and approach to the work site during the rainy season and a couple of months thereafter, (3) unreasonable rejection by the government officers of material brought on the site, which material was later on allowed to be used, (4) difficulty in procuring labour due to malarious climate at the site, (5) delay in issuing quarry permit and (6) extra time taken for doing extra work that was entrusted ought to have been taken into account-were put forward by the appellant-plaintiff merely for the purpose of showing that the refusal to extend the time by the superintending engineer although recommended by the s.d.o. and executive engineer was unreasonable and not for showing that the recision of the contract was unreasonable or unjustified. in our view, the question would not be whether the recision of the contract was unreasonable and, therefore, unjustified but whether the recision of the contract in the circumstances of the case was wrongful and illegal. if time was not of the essence of the contract or if the stipulation as to the time fixed for completion had, by reason of waiver, ceased to be applicable then the only course open to the respondent-defendant was to fix some time making it the essence and if within the time so fixed the appellant-plaintiff had failed to complete the work the respondent-defendant could have rescinded the contract. the high court has taken the view that the contract was rightly rescinded by the respondent-defendant because by about july 21, 1956 (vide letter ex. 74) the appellant-plaintiff had done work of the value of rs. 35,000/- as against the tender value of rs. 1,07,000/-, that is to say, only 1/3rd of the total work had been completed and, therefore, even though time was not of the essence of the contract, the appellant-plaintiff, in the circumstances, could not have completed the work even within the next three months. in our view, this approach adopted by the respondent-defendant and upheld by the high court is not correct. long before the expiry of the period of 12 months the appellant-plaintiff had by his letter dated june 6, 1956 (ex. 68) requested for extension of period of completion up to the end of december, 1956; this request was repeated by another letter dated june 23, 1956 (ex. 69). may be the reasons or grounds on which the request was made may not have appealed to the superintending engineer but some reasonable time making it the essence ought to have been granted. in this behalf it may be stated that the s.d.o. by his letter (ex. 69) had recommended extension upto december 1956 as sought while by his letter dated june 23, 1956 (ex. 70) addressed to the superintending engineer, the executive engineer had recommended that extension of time up to october 30, 1956 may be granted to the appellant-plaintiff with clear intimation that if he failed to complete the work by then, the maximum penalty allowable under clause 2, namely, 10% of the cost of the work will be inflicted on him, but the recommendation did not receive approval of the superintending engineer. it appears that the appellant-plaintiff had an interview with the superintending engineer on august 24, 1956 when a written representation (ex. 99) was handed over and the whole position was sought to be explained to the superintending engineer but within three days of the interview by the letter dated august 27, 1956 (ex. 78) the contract was rescinded and the full security deposit was forfeited to government. it will thus appear clear that though time was not of the essence of the contract, the respondent-defendant did not fix any further period making time the essence directing the appellant-plaintiff to complete the work within such period; instead it rescinded the contract straightaway by letter dated august 27, 1956. such recision on the part of the respondent-defendant was clearly illegal and wrongful and thereby the respondent-defendant committed a breach of contract, with the result that there could be no forfeiture of the security deposit. in our view, therefore, the trial court was right in coming to the conclusion that the appellant-plaintiff was entitled to a refund of their full security deposit of rs. 4,936/- as also to rs. 5845/- being the balance of their bill no. 1253 dated september 20, 1956 for work actually done by them and not paid for and nominal damages of rs. 120/-. the appellant-plaintiff was also entitled to interest on the aforesaid sums and costs of suit as directed by the trial court.11. in the result we allow the appeal, set aside the common judgment and decree in f.a. no. 844 of 1961 passed by the high court and restore that of the trial court. the appellant-plaintiff will get costs of this appeal as also costs of f.a. no. 844 of 1961. the high court's decree dismissing f.a. no. 245 of 1962 is confirmed.
Judgment:V.D. Tulzapurkar, J.
1. These appeals by certificate of fitness granted by the High Court of Judicature at Bombay are directed against that Court's common judgment and decree dated September 9/10, 1968, passed in two cross appeals being First Appeal Nos. 245 of 1962 and 844 of 1961.
2. A contract for the construction of an aqueduct across the Alandi River at Mile No. 2 of the Nasik Left Bank Canal of the total value of Rs. 1,07,000/- was granted to the appellant-plaintiff (originally a partnership but later a proprietary firm of contractors) by the respondent-defendant (the State of Maharashtra) after the former's tender was accepted on June 17, 1955. On July 2, 1955 the Executive Engineer issued the work order to the appellant-plaintiff directing him to commence the work by July 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from July 5, 1955. The formal regular Contract in prescribed Form B-2/1 of 1955-56 (Ex. 34) containing the terms and conditions as well as the Schedules, specifications etc. was executed by the parties on July 12, 1955. A security deposit of Rs. 4,936/- was kept by the appellant-plaintiff with the respondent-defendant. The period for completion of work was fixed as 12 months from the date stipulated for commencement of the work, that is to say, it was expected to be completed on or before July 4, 1956. It appears that on the ground that the appellant-plaintiff had not completed the work as expected within the stipulated time the Executive Engineer by his letter dated August 27, 1956 (Ex. 78) rescinded the said contract with effect from August 16, 1956. After serving a notice under Section 80 of the Civil Procedure Code the appellant-plaintiff filed a suit (being Special Civil Suit No. 23 of 1959) on August 28, 1959 in the Court of the Joint Civil Judge, Senior Division, Nasik making a claim for Rs. 65,000/- in the aggregate against the respondent-defendant alleging wrongful and illegal recision of the contract on the part of the respondent-defendant The appellant-plaintiff's case was that the initial fixation of July 5, 1955 as the date for commencement of the work was nominal, that the area where the work was to be done had usually heavy rainfall rendering it impossible to carry out any work from July to November and that, therefore, it was the practice of the Public Works Department to deduct the period of monsoon in case of such type of works and that the appellant-plaintiff had been orally informed that this period would be deducted or not taken into account for calculating the period of 12 months under the contract and that oft this assurance he had commenced the work towards the end of December 1955. His case further was that in any event time was not of the essence of the contract, that on account of several difficulties, such as excessive rains, lack of proper road and means of approach to the site, rejection of materials on improper grounds by Government Officers, etc., over which he had no control, the completion of the work was delayed and that the extension of the time which was permissible under the contract had been wrongfully refused by the officers of the respondent-defendant. According to him none of these factors had been taken into account by the Government while refusing the extension and the contract was wrongfully rescinded and, therefore, the respondent-defendant was liable in damages. The total claim of Rs. 65,000/- comprised six items-(1) Rs. 4,936/- being the amount of security deposit wrongfully forfeited by the respondent-defendant, (2) Rs. 10,254/- being the amount due to him for the actual work done by him under Bill No. 1253 dated September 20, 1956 and which had not been paid for, (3) Rs. 7,375/- being the value of the material collected by him on the site for work but which had been rendered useless on account of wrongful recision, the 4th and 5th items sounded in damages, while the last item was interest from date of recision to the date of the suit.
3. The State of Maharashtra resisted the claim contending that time was of the essence of the contract, that the date fixed for commencement was real and not nominal and the 12 months period was fixed after all aspects of the matter had been taken into account, it was further contended that the appellant-plaintiff knew the situation of the site and the so-called difficulties, that there was no excuse for him for not doing the work during the months of July to November, that the appellant-plaintiff failed to carry out the proportionate work during the periods fixed in the contract and that since the appellant-plaintiff had rendered himself incompetent to complete the work in proper time it had to rescind the contract and the recision was proper and for adequate reasons; it was further contended that the State was entitled to forfeit the security deposit which it did on the date when the contract was rescinded. The several items claimed by the appellant-plaintiff were denied by the State. It was denied that the material of the value of Rs. 7,375/- remained on the sits or that it was responsible for its non-removal from the site. Regarding items 4 and 5 the State denied its liability to pay the same as it was the appellant-plaintiff who had committed the breach of the contract. As regards the amount due under Bill No. 1253 dated September 20, 1956 for the actual work done, it was contended that the State had to deduct the amount of penalty leviable under the contract and for the actual cement supplied to the appellant-plaintiff and after making deductions in that behalf only a sum of Rs. 700/- would be due to the appellant-plaintiff.
4. On a consideration of the documentary evidence including the terms and conditions of the contract (Ex. 34) and the oral evidence led by the parties, the learned trial Judge held that the date July 5, 1955 fixed as the date for commencement of the work was not nominal but that time was not of the essence of the contract between the parties, that the respondent-defendant (State Government) had wrongfully, rescinded the contract, that the appellant-plaintiff was entitled to damages but that he had not established the two items claimed as damages and he was entitled to a nominal sum of Rs. 120/- as damages. He further held that since the recision of the contract was wrongful the State was not entitled to forfeit the security deposit nor levy any penalty. He accordingly decreed the appellant-plaintiff's claim in respect of refund of security deposits and as regards the amount of Bill No. 1253 dated September 20, 1956 for actual work done he held that a sum of Rs. 5,845/- only would be due to him after giving credit for Rs. 4,409/- due from the appellant-plaintiff to the State. He accordingly decreed the appellant-plaintiff's suit to the extent of Rs. 10,901/- with interest thereon at 6% per annum from the date of recision till date of suit and allowed proportionate costs to him.
5. Two appeals were preferred against the aforesaid decree of the trial court, one by the appellant-plaintiff in respect of the claims that had been disallowed (First Appeal No. 245 of 1962) and the other by the State in respect of the claims allowed against it (First Appeal No. 844 of 1961). Curiously enough the High Court did not decide the main issue that arose between the parties, namely, whether time was of the essence of the contract, as it took the view that a decision on that question was really unnecessary for disposal of the appeals. It proceeded to decide the appeals on the assumption that time was not of the essence of the contract by considering the question whether the recision of the contract by the State could be regarded as mala fide or so unreasonable that it must in the place of the judgment of the officers concerned substitute its own judgment and hold that the recision was wrongful. The High Court observed that even the appellant-plaintiff had not alleged any mala fide on the part of any of the officers of the State but had pressed into service five or six factors the non-consideration whereof by the respondent-defendant rendered the recision of the contract arbitrary, unreasonable and, therefore, unjustified. After discussing each one of those five or six factors the High Court held that some of them had not been proved by the appellant-plaintiff while others did not head to the inference that the recision of the contract was arbitrary, unreasonable or unjustified. It found that by about July 21, 1956 (vide Ex. Engineer's letter Ex. 74) the appellant-plaintiff had done only 1/3rd of the contract work and that in the circumstances the appellant-plaintiff could not have completed the work even within the next three months and, therefore, the respondent's officers had rightly rescinded the contract and, therefore, it was the appellant-plaintiff and not the respondent-defendant who had committed a breach of the contract. However, the High Court took the view that for such breach on the part of the appellant-plaintiff, the respondent-defendant, on a reading of the Clauses 2 and 3 of the Conditions of Contract, was not entitled both to levy compensation and also to forfeit the security deposit. Accordingly, the High Court upheld the forfeiture of the security deposit made by the respondent-defendant and while modifying the trial court's decree it confirmed it only to the extent of Rs. 5,845/-, being the amount due to the appellant-plaintiff for the work actually done by him under Bill No. 1253 and which had not been paid. In the result, the appellant-plaintiff's appeal was dismissed and that of the State was partly allowed with appropriate order of proportionate costs.
6. In support of the present appeal counsel for the appellant-plaintiff raised two or three contentions. In the first place he contended that the High Court was in error in not deciding the main issue whether the time was of the essence of the contract or not He urged that the said issue could not be avoided in the manner done by the High Court, for, if time was not of the essence of the contract then just before the expiry of the 12 months' period or immediately after its expiry it was up to the respondent-defendant to grant some reasonable time to the appellant-plaintiff for completing the work undertaken and make the same the essence of the contract and only if the work was not completed by the appellant-plaintiff within that time the contract could have been rescinded on the ground that the appellant-plaintiff had committed a breach of a contract. According to him such course of action on the part of the respondent-defendant was obligatory, when the initial period of 12 months was not of the essence, especially when the request of the appellant-plaintiff for extension of time was pending before the concerned officers of the Government since before the expiry of the initial period. He contended that instead of adopting the aforesaid course the respondent-defendant had without making time of the essence of the contract rescinded the same with effect from August 16, 1956 by a letter dated August 27, 1956 (Ex. 7:8), which recision must be regarded as wrongful and illegal. Secondly counsel contended that the High Court further erred in considering the question whether the recision of the contract by the State was either mala fide or wholly unreasonable and, therefore, unjustified. He pointed out it was not the appellant-plaintiff's case that the recision was mala fide and, according to him, the question was not whether the recision of the contract on the part of the respondent-defendant was unreasonable, and, therefore, unjustified but whether the respondent-defendant was entitled in law to rescind the contract in the manner done when time was not of the essence of the contract. He further urged that the High Court had clearly erred in assuming that the appellant-plaintiff could not have completed the work even within the next three mouths A and, therefore, the contract was rightly rescinded by the respondent-defendant. He, however, fairly stated that even if this Court held in his favour that the recision was wrongful and, therefore, the respondent-defendant had committed a breach he would merely press for the restoration of the decree passed by the trial Court and not press any other item forming the subject-matter of the original claim in the suit. On the other hand, counsel for the respondent-defendant sought to support the judgment and decree of the High Court on both the grounds first that time was of the essence of the contract having regard to the express provision contained in Clause (2) of the 'Conditions of Contract' and, therefore, on appellant-plaintiff's failure to complete the same within the stipulated time the recision of the contract was legal and justified and secondly, that even if time was not of the essence of the contract, having regard the circumstances the High Court rightly came to the conclusion that the recision of the contract by the respondent-defendant could not be regarded as unreasonable or unjustified and that, therefore, the appellant-plaintiff being in breach the security deposit had been rightly forfeited.
7. The first question that arises for our consideration, therefore, is whether time was of the essence of the contract that was executed between the. parties on July 12, 1955 (Ex. 34). It cannot be disputed that question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. The contract in the instant case is for the construction of an aqueduct across the Alandi River at Mile No. 2 of the Nasik Left Bank Canal and unquestionably 12 months' period commencing from the date of the commencement of the work had been specified within which the construction had to be completed by the appellant-plaintiff. Indisputably, in the work order dated July 2, 1955 the Executive Engineer had directed the appellant-plaintiff to commence the work by July 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from July 5, 1955. Both the trial court as well as the High Court have found that mentioning of July 5, 1955 as the date for starting the work was not nominal but was real date intended to be acted upon by the parties. It is, therefore, clear that 12 months' period mentioned for the completion of the work was to expire on July 4, 1956. The question is whether this period of 12 months so specified in the contract was of the essence of the contract or not On the one hand, counsel for the appellant-plaintiff contended that the contract being analogous to a building contract the period of 12 months would not ordinarily be of the essence of the contract as the subject-matter there of was not such as to make completion to time essential, that an agreement to complete it within reasonable time would be implied and that reasonable time for completion would be allowed. On the other hand counsel for the respondent-defendant contended that time had been expressly made of the essence of the contract and in that behalf reliance was placed upon Clause (2) of the 'Conditions of Contract' where not only time was stated to be of the essence of the contract on the part of the contractor but even for completion of proportionate works specific periods had been specified and, therefore, the appellant-plaintiff's failure to complete the work within the stipulated period entitled the respondent-defendant to rescind it. In the latest 4th edn. of Halsbury's Laws of England in regard to building and engineering contracts the statement of law is to be found in Vol. 4, Para 1179, which runs thus:
1179. Where time is of the essence of the contract. The expression time is of the essence means that a breach of the condition as to the time for performance will entitle the innocent party to consider the breach as a repudiation of the contract. Exceptionally, the completion of the work by a specified date may be a condition precedent to the contractor's right to claim payment The parties may expressly provide that time is of the essence of the contract and where there is power to determine the contract on a failure to complete by the specified date, the stipulation as to time will be fundamental. Other provisions of the contract may, on the construction of the contract, exclude an inference that the completion of the works by a particular date is fundamental, time is not of the essence where a sum is payable for each week that the work remains incomplete after the date fixed, nor where the parties contemplate a postponement of completion.
Where time has not been made of the essence of the contract or, by reason of waiver, the time fixed has ceased to be applicable, the employer may by notice fix a reasonable time for the completion of the work and dismiss the contractor on a failure to complete by the date so fixed.
(Emphasis supplied)
8. It will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental, for instance, if the contract were to include causes providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract. The emphasised portion of the aforesaid statement of law is based on Lamprell v. Billericay Union [1849] 3 Ex 283, Webb v. Hughes [1870] L.R. 10 Eq 281 and Charles Rickards Ltd. v. Oppenheim [1950] 1 KB 616. It is in light of the aforesaid position in law that we will have to consider the several clauses of the contract Ex. 34 in the case. The material clauses in this behalf are Clauses 2 and 6 of the 'Conditions of Contract' which run as follows:
Clause 2:The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be reckoned from the date on which the order to commence work is given to the contractor. The work shall throughout the stipulated period of the contract be proceeded with, with all due diligence (time being deemed to be of the essence of the contract on the part of the contractor) and the contractor shall pay as compensation an amount equal to one per cent or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide, of the amount of the estimated cost of the whole work as shown by the tender for every day that the work remains uncommenced, or unfinished, after the proper dates. And further to ensure good progress during the execution of the work, the contractor shall be bound, in all cases in which the time allowed for any work exceeds one month, to complete.
1/4 of the work in 1/4 of the time
1/2 of the work in 1/2 of the time
3/4 of the work in 3/4 of the time.
Clause 6: If the contractor shall desire an extension of the time for completion of the work on the ground of his having been unavoidably hindered in its execution or on any other ground, he shall apply in writing to the Executive Engineer before the expiry of period stipulated in the tender or before expiry of 30 days from the date on which he was hindered as aforesaid or on which the cause for asking for extension occurred, whichever is earlier and the Executive Engineer, may if in his opinion there are reasonable grounds for granting an extension, grant such extension as he thinks necessary or proper. The decision of the Executive Engineer in this matter shall be final.
Two aspects emerge very clearly from the aforesaid two clauses, In the first place under Clause 6 power was conferred upon the Executive Engineer to grant extension of time for completion of the work on reasonable grounds on an application being made by the contractor (appellant-plaintiff) in that behalf; in other words, in certain contingencies parties had contemplated that extension of time would be available to the contractor. Such a provision would clearly be inconsistent with parties intending to treat the stipulated period of 12 months in Clause 2 as fundamental. Similarly, in Clause 2 itself provision was made for levying and recovering penalty/compensation from the appellant-plaintiff at specified rates during the period the work shall remain unfinished after the expiry of the fixed date. Such provision also excludes the inference that time (12 months period) was intended to be of the essence of the contract. Further with regard to the provision that is to be found in Clause 2 whereunder a time schedule for proportionate work had been set out (namely, 1/4 of the work in 1/4 of the time, 1/2 of the work in 1/2 of the time and 3/4 of the work in 3/4 of the time ), the evidence of the Superintending Engineer Pandit (D.W. 1) is very eloquent. In para 13 of his deposition this is what he has stated:
In the agreement (Ex. 34) the rate of work is based on the valuation 1/4th time mentioned means 1/4th in 12 months. The suit contract is for Rs. 1,07,000/-. 1/4th work means the work of about Rs. 27,000/-. It is not possible to do the work of Rs. 27,000/- in 1/4th time as the days were rainy. This was not reasonable.
The witness in para 12 of his deposition has also given the following admission:
It is not specifically mentioned in the agreement (Ex. 34), that the suit work was urgent and that it was to be completed within 12 months. In this agreement (Ex. 34) there are the clauses of imposing a penalty and extension of time.
9. Having regard to the aforesaid material on record, particularly the clauses in the agreement pertaining to imposition of penalty and extension of time it seems to us clear that time (12 months period) was never intended by the parties to be of the essence of the contract. Further from the correspondence on the record, particularly, the letter (Ex. 78) by which the contract was rescinded it does appear that the stipulation of 12 months' period was waived, the contractor having been allowed to do some more work after the expiry of the period, albeit at his risk, by making the recision effective from August 16, 1956.
10. Once either of the aforesaid conclusions is reached it would be difficult to accept the High Court's finding that the recision of the contract on the part of the respondent-defendant was proper and justified on the basis that the same was neither shown to be mala fide nor unreasonable. It must be observed that it was never the case of the appellant-plaintiff that the recision of the contract on the part of the respondent-defendant was mala fide. Counsel for the appellant-plaintiff further pointed out and, in our view, rightly that the five or six factors, namely, (1) the contract having been given at the threshold of monsoon, the period of monsoon (4 months) ought not to have been reckoned, (2) absence of proper road and approach to the work site during the rainy season and a couple of months thereafter, (3) unreasonable rejection by the Government Officers of material brought on the site, which material was later on allowed to be used, (4) difficulty in procuring labour due to malarious climate at the site, (5) delay in issuing quarry permit and (6) extra time taken for doing extra work that was entrusted ought to have been taken into account-were put forward by the appellant-plaintiff merely for the purpose of showing that the refusal to extend the time by the Superintending Engineer although recommended by the S.D.O. and Executive Engineer was unreasonable and not for showing that the recision of the contract was unreasonable or unjustified. In our view, the question would not be whether the recision of the contract was unreasonable and, therefore, unjustified but whether the recision of the contract in the circumstances of the case was wrongful and illegal. If time was not of the essence of the contract or if the stipulation as to the time fixed for completion had, by reason of waiver, ceased to be applicable then the only course open to the respondent-defendant was to fix some time making it the essence and if within the time so fixed the appellant-plaintiff had failed to complete the work the respondent-defendant could have rescinded the contract. The High Court has taken the view that the contract was rightly rescinded by the respondent-defendant because by about July 21, 1956 (vide letter Ex. 74) the appellant-plaintiff had done work of the value of Rs. 35,000/- as against the tender value of Rs. 1,07,000/-, that is to say, only 1/3rd of the total work had been completed and, therefore, even though time was not of the essence of the contract, the appellant-plaintiff, in the circumstances, could not have completed the work even within the next three months. In our view, this approach adopted by the respondent-defendant and upheld by the High Court is not correct. Long before the expiry of the period of 12 months the appellant-plaintiff had by his letter dated June 6, 1956 (Ex. 68) requested for extension of period of completion up to the end of December, 1956; this request was repeated by another letter dated June 23, 1956 (Ex. 69). May be the reasons or grounds on which the request was made may not have appealed to the Superintending Engineer but some reasonable time making it the essence ought to have been granted. In this behalf it may be stated that the S.D.O. by his letter (Ex. 69) had recommended extension upto December 1956 as sought while by his letter dated June 23, 1956 (Ex. 70) addressed to the Superintending Engineer, the Executive Engineer had recommended that extension of time up to October 30, 1956 may be granted to the appellant-plaintiff with clear intimation that if he failed to complete the work by then, the maximum penalty allowable under Clause 2, namely, 10% of the cost of the work will be inflicted on him, but the recommendation did not receive approval of the Superintending Engineer. It appears that the appellant-plaintiff had an interview with the Superintending Engineer on August 24, 1956 when a written representation (Ex. 99) was handed over and the whole position was sought to be explained to the Superintending Engineer but within three days of the interview by the letter dated August 27, 1956 (Ex. 78) the contract was rescinded and the full security deposit was forfeited to Government. It will thus appear clear that though time was not of the essence of the contract, the respondent-defendant did not fix any further period making time the essence directing the appellant-plaintiff to complete the work within such period; instead it rescinded the contract straightaway by letter dated August 27, 1956. Such recision on the part of the respondent-defendant was clearly illegal and wrongful and thereby the respondent-defendant committed a breach of contract, with the result that there could be no forfeiture of the security deposit. In our view, therefore, the trial court was right in coming to the conclusion that the appellant-plaintiff was entitled to a refund of their full security deposit of Rs. 4,936/- as also to Rs. 5845/- being the balance of their Bill No. 1253 dated September 20, 1956 for work actually done by them and not paid for and nominal damages of Rs. 120/-. The appellant-plaintiff was also entitled to interest on the aforesaid sums and costs of suit as directed by the trial court.
11. In the result we allow the appeal, set aside the common judgment and decree in F.A. No. 844 of 1961 passed by the High Court and restore that of the trial court. The appellant-plaintiff will get costs of this appeal as also costs of F.A. No. 844 of 1961. The High Court's decree dismissing F.A. No. 245 of 1962 is confirmed.